Pharma4i home

Ungated worked example

See what Pharma4i produces

Six documents for one Water for Injection storage and distribution system, from specification through site acceptance. Every document inherits from the one before it, and every finding is traceable back to a requirement ID in the URS.

Project
PRJ-2026-0009
Equipment
EQ-02
System
WFI Storage and Distribution System

One requirement, all six documents

Every requirement has a row like this. The project traceability matrix builds it automatically.

1

URS

User Requirements Specification

What the system must do, written as numbered, testable requirements the design can be judged against.

  • 19 pages
  • 74 requirements
  • 11 worst-case conditions
2

DQ

Design Qualification

Whether the proposed design meets each requirement, verdict by verdict, against the supplier's documents.

  • 24 pages
  • 74 verdicts
  • 46 observations

Factory acceptance — protocol and report

3

FAT Protocol

Factory Acceptance Test Protocol

The tests to be run at the supplier's works before shipment, each traced to a requirement ID, with empty result columns for the executor.

  • 26 pages
  • 40 test scripts
  • 36 requirements deferred
4

FAT Report

Factory Acceptance Test Report

What the executed protocol found, with the deviations classified and a conclusion the reviewer confirms rather than the software asserting it.

  • 29 pages
  • 14 deviations
  • 14 punch list items

Site acceptance — protocol and report

5

SAT Protocol

Site Acceptance Test Protocol

The tests run after delivery: installation verification, the requirements the works could not test, and closure steps for every factory deviation and punch list item.

  • 29 pages
  • 39 test scripts
  • disposition of all 36 FAT deferrals
6

SAT Report

Site Acceptance Test Report

What site acceptance found with the plant installed, what remains open, and the requirements handed forward to Installation Qualification.

  • 31 pages
  • 18 deviations
  • 12 of 14 FAT deviations closed
Download all six (ZIP)

These documents were produced with Pharma4i and reviewed by a qualified engineer. Pharma4i drafts documents; it does not approve them. Every generated document requires review and approval in your own quality system.

No email, no form, no account. Later examples — IQ, OQ, PQ and the Validation Summary Report — will be added here for this same system, in lifecycle order.

URSUser Requirements Specification

Download Word
Full document text — PRJ-2026-0009 · EQ-02

USER REQUIREMENTS SPECIFICATION

Water for Injection Storage and Distribution System

URS-WFI-001 · REVISION 0.1

Document status Draft
System name [Enter system name]
Equipment type Pharmaceutical Water — WFI Storage and Distribution
Site [Enter site]
GxP impact Direct impact
Prepared by [Enter author]
Date [DD-MMM-YYYY]
This document was drafted with software assistance. It is a draft and has no validity until reviewed and approved by qualified personnel in accordance with the site quality system. All bracketed values must be supplied and all Section 6 assumptions confirmed before this document is issued. Pharma4i does not perform or record document approval; responsibility for review, approval, signature and document control rests with the approving persons named in Section 8.

HOW TO USE THIS TEMPLATE

Values shown as [TO BE CONFIRMED] are deliberate. They are parameters that must be supplied by the user department; the template does not assume them because an assumed capacity, sanitisation temperature or hold time is a specification error that reaches a supplier as though it were a decision.

Section 6 lists the configuration assumptions carried while drafting. Each must be confirmed or corrected before the document is issued. Appendix A defines the worst-case conditions that govern design verification and qualification; every one of them should be challenged during qualification, not only the convenient ones.

Table of Contents

1. Purpose and Scope

1.1 Purpose

This User Requirements Specification defines the requirements of the user for a Water for Injection storage and distribution system to be installed at [site]. It states what the user requires; it does not state how those requirements are to be achieved, which is the responsibility of the supplier and is assessed during Design Qualification.

1.2 Scope of the system

  • The WFI storage tank, including its vent filter, spray ball, level instrumentation and relief devices.

  • The distribution loop, including supply and return pipework, distribution pumps, heat exchanger and all valves.

  • All points of use listed in the point-of-use schedule, including point-of-use coolers and sample valves.

  • The thermal sanitisation function and its control.

  • Online monitoring instrumentation for temperature, flow, pressure, level, conductivity and total organic carbon.

  • The control system, operator interface, and the GMP records it generates.

1.3 Out of scope

  • The WFI generation system upstream of the storage tank, which is the subject of a separate specification.

  • Pretreatment and feed water systems.

  • Point-of-use hoses, connectors and their management.

  • Site utilities upstream of the connection points defined in the utility schedule.

  • Building services, room HVAC and environmental monitoring.

  • Laboratory testing methods and the sampling programme itself, which are defined in site procedures.

2. System Overview

2.1 System description

The system stores Water for Injection produced by the existing generation system and distributes it under continuous hot circulation to the points of use listed in the point-of-use schedule. Water is held and circulated at not less than 80 °C to maintain microbial control, with point-of-use coolers provided where a lower temperature is required at the outlet.

The distribution loop is a single circulating loop returning to the storage tank. Loop temperature is maintained by a heat exchanger of double tube sheet construction. Duty and standby distribution pumps provide continuous circulation with automatic changeover on failure.

2.2 Process context

WFI from this system is used in [state the uses: final rinse of product contact equipment, formulation, injection preparation, and similar]. Water quality therefore has a direct impact on product quality and on patient safety, and the system is classified as direct impact.

2.3 Interfaces to other systems

  • WFI generation system — demand signal, generation status, out-of-specification diversion status.

  • Building management system — alarm annunciation only, with no control authority over the WFI system.

  • Points of use — mechanical and, where applicable, control interfaces to formulation, washing and filling equipment.

  • Laboratory information management system — export of online monitoring data for correlation with laboratory results.

2.4 GxP impact assessment

The system is classified as GxP, direct impact. WFI is in direct contact with product or with product contact surfaces; its quality attributes are product quality attributes; and the system generates GMP records used in the assessment of batch quality. All requirements in this specification are therefore subject to qualification, and the control system is subject to EU GMP Annex 11 and, where applicable, 21 CFR Part 11.

3. Definitions and Abbreviations

Term Definition
ALCOA+ Attributable, Legible, Contemporaneous, Original, Accurate, plus Complete, Consistent, Enduring, Available
ASME BPE American Society of Mechanical Engineers Bioprocessing Equipment standard
CFU Colony Forming Unit
DQ Design Qualification
EU Endotoxin Unit
FAT Factory Acceptance Test
GAMP Good Automated Manufacturing Practice
GMP Good Manufacturing Practice
IQ Installation Qualification
OQ Operational Qualification
P&ID Piping and Instrumentation Diagram
POU Point of Use
PQ Performance Qualification
Ra Roughness average, surface finish
SAT Site Acceptance Test
TOC Total Organic Carbon
URS User Requirements Specification
WFI Water for Injection

4. Referenced Documents

  • EU GMP Annex 1 — Manufacture of Sterile Medicinal Products (2022 revision), where WFI is used in aseptic processing.

  • EU GMP Annex 11 — Computerised Systems.

  • EU GMP Annex 15 — Qualification and Validation.

  • 21 CFR Parts 210, 211 and 11, where the site supplies the United States market.

  • USP General Chapter <1231> — Water for Pharmaceutical Purposes; USP <643> Total Organic Carbon; USP <645> Water Conductivity.

  • USP and Ph. Eur. monographs for Water for Injection.

  • ASME BPE — Bioprocessing Equipment.

  • GAMP 5 — A Risk-Based Approach to Compliant GxP Computerised Systems.

  • [Site validation master plan, site engineering standards, point-of-use schedule, utility schedule.]

5. Requirements

Each requirement carries a unique identifier, a category, a priority and the qualification stage at which it is verified. Requirements are written to be verifiable. Where a requirement is governed by a worst-case condition, that condition is named and cross-referenced to Appendix A.

ID Category Requirement Priority / Verification
URS-001 Operational The system shall store and distribute Water for Injection meeting the requirements of the current USP and Ph. Eur. monographs for Water for Injection.

Mandatory

PQ

URS-002 Operational

The system shall deliver a peak instantaneous demand of [TO BE CONFIRMED] L/min and an average daily consumption of [TO BE CONFIRMED] L/day.

Worst case: Peak demand with all high-draw points open simultaneously, as defined in Appendix A, WC-01.

Mandatory

PQ

URS-003 Operational The system shall operate continuously, 24 hours per day, 7 days per week, with planned shutdown limited to [TO BE CONFIRMED] hours per year.

Mandatory

PQ

URS-004 Operational

The storage tank shall have a nominal capacity of [TO BE CONFIRMED] L, sized to buffer peak demand without the generation system falling below its minimum turndown.

Worst case: Minimum tank level coincident with peak draw, WC-05.

Mandatory

DQ

URS-005 Operational The distribution loop shall serve [TO BE CONFIRMED] points of use, listed with their location, required flow and required temperature in the point-of-use schedule.

Mandatory

DQ

URS-006 Operational The system shall recover to full specification within [TO BE CONFIRMED] hours following a planned shutdown, without requiring drain and refill.

Desirable

PQ

URS-007 Functional

WFI shall be stored and distributed under continuous hot circulation at a temperature not less than 80 °C at every point in the loop, measured at the least favourable location.

Worst case: Coldest point in the loop, normally the return leg at maximum draw, WC-02.

Mandatory

OQ / PQ

URS-008 Functional

The distribution loop shall maintain a return flow velocity of not less than 1.0 m/s, or a demonstrated turbulent flow with Reynolds number greater than 10,000, at all operating conditions.

Worst case: Minimum return velocity at maximum simultaneous draw, WC-01.

Mandatory

OQ

URS-009 Functional

The system shall be fitted with duty and standby distribution pumps with automatic changeover on failure, and an automatic duty rotation to prevent stagnation in the standby pump.

Worst case: Standby pump branch is a low-flow zone; see WC-07.

Mandatory

OQ

URS-010 Functional Loop temperature shall be maintained by a heat exchanger of double tube sheet construction with a monitored and drainable interspace, providing leak detection between the WFI and the heating medium.

Mandatory

IQ / OQ

URS-011 Functional

The storage tank shall be fitted with a spray ball providing demonstrated full wetted coverage of the internal surface, including the headspace, at the specified supply pressure and flow.

Worst case: Tank at minimum operating level with the highest headspace to wet, WC-05.

Mandatory

OQ

URS-012 Functional

The storage tank shall be fitted with a hydrophobic vent filter of 0.22 micrometre rating, electrically heated to prevent condensate blinding, and capable of in-place integrity testing without breaking the sterile boundary.

Worst case: Maximum tank discharge rate creating maximum air ingress through the vent filter, WC-06.

Mandatory

IQ / OQ

URS-013 Functional

Points of use requiring water below loop temperature shall be served by dedicated point-of-use coolers arranged so that the cooled volume is returned to loop temperature, or drained, when the point of use is not drawing.

Worst case: Point-of-use cooler branch is the highest microbial risk location in the system, WC-04.

Mandatory

OQ

URS-014 Functional

The system shall provide a thermal sanitisation cycle capable of raising every point in the loop, including every point-of-use branch and cooler, to not less than [TO BE CONFIRMED] °C for not less than [TO BE CONFIRMED] minutes.

Worst case: Coldest point during sanitisation, normally the most hydraulically remote point-of-use branch, WC-03.

Sanitisation temperature and hold time drive the sterility assurance of the system and shall be specified by the user; they are not assumed.

Mandatory

OQ

URS-015 Functional Tank level shall be controlled automatically, with high, high-high, low and low-low alarms, and with pump protection preventing operation below the minimum level.

Mandatory

OQ

URS-016 Functional

The system shall deliver a minimum dynamic pressure of [TO BE CONFIRMED] bar g at the most hydraulically remote point of use under peak demand.

Worst case: Most remote point of use at peak simultaneous draw, WC-01 and WC-08.

Mandatory

PQ

URS-017 Data / records The control system shall continuously record loop supply temperature, loop return temperature, tank level, loop flow, loop pressure, online conductivity and online TOC, at an interval not exceeding one minute.

Mandatory

OQ

URS-018 Data / records The system shall record every sanitisation cycle, capturing the temperature profile at each monitored location, the hold period achieved, the operator who initiated the cycle, and the cycle outcome.

Mandatory

OQ

URS-019 Data / records All alarms shall be recorded with the alarm condition, time of onset, time of acknowledgement, the acknowledging operator and time of clearance.

Mandatory

OQ

URS-020 Data / records Records shall be retained for not less than [TO BE CONFIRMED] years and shall be exportable in a human-readable format that retains the associated audit trail and metadata.

Mandatory

OQ

URS-021 Data integrity

Records shall be attributable, legible, contemporaneous, original and accurate, and shall remain complete, consistent, enduring and available throughout the retention period.

ALCOA+; EU GMP Annex 11, MHRA and FDA data integrity guidance.

Mandatory

OQ

URS-022 Data integrity

The system clock shall synchronise with the site time server. Users shall not be able to alter system time, and any time synchronisation change shall be recorded.

Annex 11 clause 9.

Mandatory

OQ

URS-023 Data integrity

The system shall support automated backup of all GMP records, and restoration of those records shall be demonstrated during qualification.

Annex 11 clause 7.2.

Mandatory

OQ

URS-024 Data integrity No function shall permit deletion or overwriting of a recorded value. Corrections shall be made by a new entry that preserves the original.

Mandatory

OQ

URS-025 Security and access

The control system shall provide role-based access control with individual named user accounts. Shared or generic accounts shall not be permitted.

Annex 11 clause 12; 21 CFR 11.10(d).

Mandatory

OQ

URS-026 Security and access The system shall provide at least the roles Operator, Supervisor, Engineer and Administrator, with the permissions of each defined in the functional specification and configurable only by an Administrator.

Mandatory

OQ

URS-027 Security and access Critical setpoints, including sanitisation temperature and hold time, alarm limits and calibration parameters, shall be modifiable only by authorised roles and every change shall be recorded.

Mandatory

OQ

URS-028 Security and access The system shall enforce automatic session timeout after a configurable period of inactivity, and shall require re-authentication to resume.

Mandatory

OQ

URS-029 Audit trail

The system shall maintain a secure, computer-generated, time-stamped audit trail recording the operator identity, date, time, previous value and new value for every GMP-relevant change.

Annex 11 clause 9; 21 CFR 11.10(e).

Mandatory

OQ

URS-030 Audit trail The audit trail shall not be editable or disableable by any user, including administrators, and shall be reviewable within the application without recourse to the database.

Mandatory

OQ

URS-031 Audit trail The system shall support periodic audit trail review, with a filterable view and an exportable report of changes over a selected period.

Mandatory

OQ

URS-032 Interfaces The system shall interface with the upstream WFI generation system, exchanging demand signal, generation status and out-of-specification diversion status.

Mandatory

SAT

URS-033 Interfaces The system shall provide monitored signals to the site building management system for alarm annunciation, without permitting control of the WFI system from that system.

Mandatory

SAT

URS-034 Interfaces The system shall provide the physical and electrical interface at each point of use defined in the point-of-use schedule, including any interface to filling or formulation equipment.

Mandatory

SAT

URS-035 Interfaces Where sample results are managed in a laboratory information management system, the system shall support export of online monitoring data in a defined format for correlation with laboratory results.

Desirable

OQ

URS-036 Environmental The system shall operate within the site utility envelope: electrical supply [TO BE CONFIRMED], plant steam or heating medium [TO BE CONFIRMED], cooling medium [TO BE CONFIRMED], and compressed air [TO BE CONFIRMED].

Mandatory

IQ

URS-037 Environmental All drain connections shall discharge through an air break to prevent backflow, and shall be visible for inspection.

Mandatory

IQ

URS-038 Environmental All hot surfaces accessible to personnel shall be insulated or guarded such that touchable surface temperature does not exceed 60 °C.

Mandatory

IQ / SAT

URS-039 Environmental

Pipework shall be installed with a continuous fall of not less than 1 in 100 towards designated drain points, so that the entire distribution system is fully drainable.

Worst case: The highest point and the longest horizontal run are the critical locations for drainability, WC-09.

Mandatory

IQ

URS-040 Environmental Loop pipework routed through classified areas shall be finished and supported so as not to compromise the cleanability of the room, and shall be installed clear of walls and ceilings for inspection.

Mandatory

IQ

URS-041 Materials All product contact surfaces shall be stainless steel 316L, with a mechanically polished and electropolished internal surface finish of Ra not greater than 0.4 micrometres.

Mandatory

IQ

URS-042 Materials All product contact welds shall be automatic orbital welds. A weld log shall be maintained, and not less than [TO BE CONFIRMED] percent of welds shall be boroscopically inspected and documented.

Mandatory

IQ

URS-043 Materials The system shall be passivated after installation in accordance with a documented procedure, and a passivation certificate shall be provided.

Mandatory

IQ

URS-044 Materials Material certificates in accordance with EN 10204 Type 3.1 shall be provided for all product contact materials, traceable to the installed components.

Mandatory

IQ

URS-045 Materials Elastomers and polymers in product contact shall comply with USP Class VI and 21 CFR 177.2600, shall be suitable for continuous service at loop temperature, and shall be listed with their service life.

Mandatory

IQ

URS-046 Materials All valves in product contact shall be sanitary diaphragm valves of zero static or zero dead leg design, installed so that the branch is self-draining.

Mandatory

IQ / DQ

URS-047 Materials

No dead leg in the distribution system shall exceed three internal pipe diameters (3D), measured from the internal wall of the main loop to the point of closure of the branch.

Worst case: The longest branch in the system defines the worst case for microbial risk, WC-07.

ASME BPE. Where site standard permits 6D, that shall be stated and justified; 3D is the design intent.

Mandatory

DQ / IQ

URS-048 Cleaning

The complete system, including the tank, loop, all branches and all points of use, shall be fully drainable to a designated low point without dismantling.

Worst case: Verified with the system at rest from the highest point, WC-09.

Mandatory

IQ / OQ

URS-049 Cleaning The sanitisation cycle shall be initiated from the operator interface, shall run automatically, and shall not be capable of being declared successful where any monitored location failed to achieve the required temperature and hold.

Mandatory

OQ

URS-050 Cleaning Sample valves at each sampling location shall be of sanitary design, self-draining, and shall permit sampling without contaminating the sample or the system.

Mandatory

IQ

URS-051 Cleaning All instruments requiring calibration shall be accessible without dismantling major assemblies and shall be removable without breaching the loop where the system is in operation.

Mandatory

DQ / IQ

URS-052 Cleaning The supplier shall provide a preventive maintenance schedule stating each task, its frequency and estimated duration, and shall guarantee spare parts availability for not less than ten years.

Mandatory

DQ

URS-053 Safety The storage tank shall be protected against overpressure and vacuum by a rupture disc and a pressure and vacuum relief arrangement, with rupture disc failure detected and alarmed.

Mandatory

IQ / OQ

URS-054 Safety An emergency stop shall be provided at the skid and at each remote pump location, placing the system in a defined safe state without creating a hazard from stored thermal energy.

Mandatory

SAT

URS-055 Safety Interlocks shall prevent operation of distribution pumps against a closed system and shall prevent sanitisation while any point of use is open to an operator-accessible outlet.

Mandatory

OQ

URS-056 Safety Sanitisation shall not be capable of being started without a positive confirmation step, and every point of use shall be visibly indicated as locked out for the duration of the cycle.

Mandatory

OQ

URS-057 Safety Noise emitted by the system shall not exceed 80 dB(A) measured at one metre under normal operation.

Desirable

SAT

URS-058 Documentation The supplier shall provide, prior to Factory Acceptance Testing: general arrangement drawings, piping and instrumentation diagrams, isometric drawings, electrical schematics, control system documentation, a functional design specification and a design qualification package.

Mandatory

DQ

URS-059 Documentation The supplier shall provide FAT and SAT protocols for user review and approval not less than four weeks before the respective test.

Mandatory

DQ

URS-060 Documentation The supplier shall provide IQ and OQ protocols and supporting documentation aligned with EU GMP Annex 15, together with a full turnover package including weld logs, boroscopy records, material certificates, slope verification records and passivation certificates.

Mandatory

IQ

URS-061 Documentation The supplier shall provide operation and maintenance manuals, a spare parts list with part numbers, and a documented change notification procedure for any modification affecting form, fit, function or materials.

Mandatory

IQ

URS-062 Documentation The supplier shall provide training for operators, maintenance personnel, and quality and validation personnel, covering operation, sanitisation, sampling, fault recovery, audit trail review and user administration.

Mandatory

SAT

URS-063 Regulatory The system shall comply with the current USP and Ph. Eur. monographs for Water for Injection and with USP General Chapter 1231.

Mandatory

PQ

URS-064 Regulatory

WFI delivered at every point of use shall meet: conductivity in accordance with USP General Chapter 645; total organic carbon not greater than 500 ppb; bacterial endotoxins not greater than 0.25 EU/mL; and total aerobic microbial count not greater than 10 CFU per 100 mL.

Worst case: Sampled at the worst-case points defined in Appendix A during each PQ phase.

Mandatory

PQ

URS-065 Regulatory The system shall be designed, installed and qualified in accordance with EU GMP Annex 15 and the site validation master plan.

Mandatory

DQ

URS-066 Regulatory The control system shall comply with EU GMP Annex 11 and, where applicable to the site, 21 CFR Part 11.

Mandatory

OQ

URS-067 Regulatory The system shall be designed and documented in accordance with GAMP 5, and the supplier shall state the GAMP software category of the control system.

Mandatory

DQ

URS-068 Regulatory Equipment design shall follow ASME BPE for hygienic design, surface finish, fabrication and examination of product contact components.

Mandatory

DQ / IQ

URS-069 Qualification The system shall support a three-phase Performance Qualification: Phase 1 with daily sampling of every point of use, Phase 2 confirming the sanitisation regime, and Phase 3 over one year confirming seasonal and feed water variation.

Mandatory

PQ

URS-070 Qualification Sample points shall be provided at the tank outlet, the loop supply, the loop return, each sub-loop return and each point of use, and shall be individually identified and shown on the P&ID.

Mandatory

IQ

URS-071 Qualification

Temperature mapping ports shall be provided at each worst-case location listed in Appendix A, sufficient to demonstrate that sanitisation acceptance is met at the least favourable point.

Worst case: Mapping shall include every location in Appendix A; a cycle demonstrated only at favourable points is not acceptable.

Mandatory

IQ / OQ

URS-072 Qualification The supplier shall provide hydraulic calculations demonstrating that the minimum return velocity and minimum point-of-use pressure are met under the worst-case demand condition defined in Appendix A.

Mandatory

DQ

URS-073 Qualification Every requirement in this specification shall be traceable through design qualification, factory and site acceptance testing, and installation, operational and performance qualification, as recorded in the traceability matrix.

Mandatory

DQ

URS-074 Qualification The system shall permit challenge of the worst-case conditions listed in Appendix A during qualification without modification to the installed system.

Mandatory

OQ

6. Assumptions

The following configuration assumptions were carried while authoring this specification. Each shall be confirmed or corrected by the responsible person before this document is issued. An assumption that reaches a supplier unconfirmed becomes a requirement nobody decided.

Ref Assumption
A-01 Loop configuration is a single hot circulating loop at 80 °C with point-of-use coolers where lower temperatures are required. To be confirmed against the point-of-use schedule.
A-02 Sanitisation is by hot water at loop temperature, using the circulating loop itself. Pure steam sanitisation is not assumed and would change the pressure rating and drainage design.
A-03 The storage tank is vertical, dished-end, jacketed and mounted at grade. Tank geometry affects spray ball selection and headspace behaviour.
A-04 A single loop serves all points of use. If sub-loops are required, each sub-loop return becomes an additional worst-case location.
A-05 Feed to the tank is from an existing WFI generation system whose capacity and turndown are known and adequate.
A-06 The heating and cooling media are available at the site utility envelope stated in URS-036, at the pressures and temperatures given in the utility schedule.
A-07 Ambient conditions in the areas served do not require trace heating beyond insulation.
A-08 Point-of-use hoses and connections are outside the scope of this specification and are covered by the site hose management procedure.

Confirmation

Statement Confirmed by Date
All assumptions above, and all bracketed values in Section 5, have been reviewed and confirmed or corrected.

7. Acceptance and Traceability

7.1 Verification method per requirement

Each requirement in Section 5 carries its verification stage. Design Qualification verifies that the proposed design satisfies the requirement. Factory and Site Acceptance Testing verify construction and installed function. Installation Qualification verifies materials, finishes, slopes, welds and documentation. Operational Qualification verifies function across the operating range, including the sanitisation cycle. Performance Qualification verifies sustained water quality over the three-phase programme.

7.2 Traceability approach

A traceability matrix shall be maintained listing every URS identifier against the design document that satisfies it and the test document that verifies it. No requirement shall be closed without a documented verification result, and no test shall be performed that does not trace to a requirement.

7.3 Worst-case conditions

Qualification shall challenge the system at its least favourable conditions, not at its most convenient. Appendix A defines the worst-case conditions for this system, the reason each is a worst case, the requirements it governs and the qualification stage at which it is challenged.

A sanitisation cycle demonstrated only at the loop supply header, a velocity calculation performed only at average demand, or a PQ sampling plan that omits the point-of-use coolers, will not demonstrate control of this system. Each condition in Appendix A shall be either challenged or formally justified as not applicable.

8. Approvals

This document is prepared for review and approval in accordance with the site quality system. Signature below indicates that the signatory has reviewed this specification and accepts it as a true statement of the user requirement.

This document has no validity until reviewed and approved by qualified personnel under the site quality system, and shall not be issued for quotation or used as the basis for Design Qualification until all bracketed values are supplied and all Section 6 assumptions are confirmed.

Role Name Department Signature Date
Author Engineering
Reviewer Operations / Production
Reviewer MSAT
Reviewer CQV / Validation
Reviewer EHS
Reviewer Automation / IT
Reviewer Contamination Control
Quality approval Quality Assurance

9. Revision History

Revision Date Description of change Author
0.1 [DD-MMM-YYYY] First draft.

Appendix A — Worst-Case Conditions Register

These are the conditions under which the system is least able to meet its requirements. Design verification and qualification shall address each one. A condition assessed as not applicable shall be recorded as such with a justification, not omitted.

Ref Condition Why it is the worst case Requirements governed Challenged at
WC-01 Maximum simultaneous demand All high-draw points of use open together. Produces the lowest loop return velocity, the lowest return temperature and the lowest pressure at the remote point of use — three critical parameters degrade at once. URS-002, URS-008, URS-016, URS-072 OQ / PQ
WC-02 Lowest temperature point during normal circulation Normally the loop return leg during peak draw, or an uninsulated section. Microbial control depends on every point staying above 80 °C, so the coldest point governs. URS-007, URS-017 OQ
WC-03 Least favourable point during sanitisation Normally the most hydraulically remote point-of-use branch or a cooler bypass. Sanitisation acceptance must be demonstrated here, not at the supply header. URS-014, URS-071 OQ
WC-04 Point-of-use cooler branch Water is held below loop temperature in a small volume with intermittent flow. This is the highest microbial risk location in a hot loop and the usual source of excursions. URS-013, URS-064 PQ
WC-05 Tank at minimum operating level Worst case for spray ball coverage of the headspace, for pump suction conditions, and for the ratio of headspace to stored volume during sanitisation. URS-004, URS-011, URS-015 OQ
WC-06 Maximum tank discharge rate Maximum air ingress through the vent filter. Governs vent filter sizing, heater duty and the risk of condensate blinding. URS-012 OQ
WC-07 Longest branch and standby pump leg The greatest dead leg in the system, and any duty/standby arrangement where one leg is intermittently stagnant. Governs the 3D limit and duty rotation. URS-009, URS-046, URS-047 DQ / IQ
WC-08 Most hydraulically remote point of use Lowest available pressure and lowest temperature. Defines the hydraulic design case together with WC-01. URS-016, URS-072 PQ
WC-09 Highest point and longest horizontal run Worst case for drainability and for retained water after shutdown. Slope and drainability are verified here. URS-039, URS-048 IQ
WC-10 Extended low-demand period Weekend or shutdown with minimal draw. Worst case for stagnation, for thermal loss and for the first-draw quality on restart. URS-003, URS-006 PQ
WC-11 Worst-case feed water quality Seasonal maximum in feed water TOC, hardness, chloride or microbial load. Challenges the generation system and, through it, the distribution loop. URS-063, URS-064, URS-069 PQ Phase 3

Note on worst-case selection. The conditions above are derived from the system configuration assumed in Section 6. If the configuration changes — a second sub-loop, ozone rather than thermal sanitisation, an ambient rather than hot loop — this register must be reworked. In particular, an ambient loop makes every branch a microbial worst case rather than only the cooled ones.

Appendix B — Traceability Matrix

To be completed by the validation team as qualification documents are raised.

URS ID Requirement summary Design reference Test reference Result
URS-001 The system shall store and distribute Water for Injection meeting the requirements of the current…
URS-002 The system shall deliver a peak instantaneous demand of [TO BE CONFIRMED] L/min and an average da…
URS-003 The system shall operate continuously, 24 hours per day, 7 days per week, with planned shutdown l…
URS-004 The storage tank shall have a nominal capacity of [TO BE CONFIRMED] L, sized to buffer peak deman…
URS-005 The distribution loop shall serve [TO BE CONFIRMED] points of use, listed with their location, re…
URS-006 The system shall recover to full specification within [TO BE CONFIRMED] hours following a planned…
URS-007 WFI shall be stored and distributed under continuous hot circulation at a temperature not less th…
URS-008 The distribution loop shall maintain a return flow velocity of not less than 1.0 m/s, or a demons…
URS-009 The system shall be fitted with duty and standby distribution pumps with automatic changeover on …
URS-010 Loop temperature shall be maintained by a heat exchanger of double tube sheet construction with a…
URS-011 The storage tank shall be fitted with a spray ball providing demonstrated full wetted coverage of…
URS-012 The storage tank shall be fitted with a hydrophobic vent filter of 0.22 micrometre rating, electr…
URS-013 Points of use requiring water below loop temperature shall be served by dedicated point-of-use co…
URS-014 The system shall provide a thermal sanitisation cycle capable of raising every point in the loop,…
URS-015 Tank level shall be controlled automatically, with high, high-high, low and low-low alarms, and w…
URS-016 The system shall deliver a minimum dynamic pressure of [TO BE CONFIRMED] bar g at the most hydrau…
URS-017 The control system shall continuously record loop supply temperature, loop return temperature, ta…
URS-018 The system shall record every sanitisation cycle, capturing the temperature profile at each monit…
URS-019 All alarms shall be recorded with the alarm condition, time of onset, time of acknowledgement, th…
URS-020 Records shall be retained for not less than [TO BE CONFIRMED] years and shall be exportable in a …
URS-021 Records shall be attributable, legible, contemporaneous, original and accurate, and shall remain …
URS-022 The system clock shall synchronise with the site time server. Users shall not be able to alter sy…
URS-023 The system shall support automated backup of all GMP records, and restoration of those records sh…
URS-024 No function shall permit deletion or overwriting of a recorded value. Corrections shall be made b…
URS-025 The control system shall provide role-based access control with individual named user accounts. S…
URS-026 The system shall provide at least the roles Operator, Supervisor, Engineer and Administrator, wit…
URS-027 Critical setpoints, including sanitisation temperature and hold time, alarm limits and calibratio…
URS-028 The system shall enforce automatic session timeout after a configurable period of inactivity, and…
URS-029 The system shall maintain a secure, computer-generated, time-stamped audit trail recording the op…
URS-030 The audit trail shall not be editable or disableable by any user, including administrators, and s…
URS-031 The system shall support periodic audit trail review, with a filterable view and an exportable re…
URS-032 The system shall interface with the upstream WFI generation system, exchanging demand signal, gen…
URS-033 The system shall provide monitored signals to the site building management system for alarm annun…
URS-034 The system shall provide the physical and electrical interface at each point of use defined in th…
URS-035 Where sample results are managed in a laboratory information management system, the system shall …
URS-036 The system shall operate within the site utility envelope: electrical supply [TO BE CONFIRMED], p…
URS-037 All drain connections shall discharge through an air break to prevent backflow, and shall be visi…
URS-038 All hot surfaces accessible to personnel shall be insulated or guarded such that touchable surfac…
URS-039 Pipework shall be installed with a continuous fall of not less than 1 in 100 towards designated d…
URS-040 Loop pipework routed through classified areas shall be finished and supported so as not to compro…
URS-041 All product contact surfaces shall be stainless steel 316L, with a mechanically polished and elec…
URS-042 All product contact welds shall be automatic orbital welds. A weld log shall be maintained, and n…
URS-043 The system shall be passivated after installation in accordance with a documented procedure, and …
URS-044 Material certificates in accordance with EN 10204 Type 3.1 shall be provided for all product cont…
URS-045 Elastomers and polymers in product contact shall comply with USP Class VI and 21 CFR 177.2600, sh…
URS-046 All valves in product contact shall be sanitary diaphragm valves of zero static or zero dead leg …
URS-047 No dead leg in the distribution system shall exceed three internal pipe diameters (3D), measured …
URS-048 The complete system, including the tank, loop, all branches and all points of use, shall be fully…
URS-049 The sanitisation cycle shall be initiated from the operator interface, shall run automatically, a…
URS-050 Sample valves at each sampling location shall be of sanitary design, self-draining, and shall per…
URS-051 All instruments requiring calibration shall be accessible without dismantling major assemblies an…
URS-052 The supplier shall provide a preventive maintenance schedule stating each task, its frequency and…
URS-053 The storage tank shall be protected against overpressure and vacuum by a rupture disc and a press…
URS-054 An emergency stop shall be provided at the skid and at each remote pump location, placing the sys…
URS-055 Interlocks shall prevent operation of distribution pumps against a closed system and shall preven…
URS-056 Sanitisation shall not be capable of being started without a positive confirmation step, and ever…
URS-057 Noise emitted by the system shall not exceed 80 dB(A) measured at one metre under normal operation.
URS-058 The supplier shall provide, prior to Factory Acceptance Testing: general arrangement drawings, pi…
URS-059 The supplier shall provide FAT and SAT protocols for user review and approval not less than four …
URS-060 The supplier shall provide IQ and OQ protocols and supporting documentation aligned with EU GMP A…
URS-061 The supplier shall provide operation and maintenance manuals, a spare parts list with part number…
URS-062 The supplier shall provide training for operators, maintenance personnel, and quality and validat…
URS-063 The system shall comply with the current USP and Ph. Eur. monographs for Water for Injection and …
URS-064 WFI delivered at every point of use shall meet: conductivity in accordance with USP General Chapt…
URS-065 The system shall be designed, installed and qualified in accordance with EU GMP Annex 15 and the …
URS-066 The control system shall comply with EU GMP Annex 11 and, where applicable to the site, 21 CFR Pa…
URS-067 The system shall be designed and documented in accordance with GAMP 5, and the supplier shall sta…
URS-068 Equipment design shall follow ASME BPE for hygienic design, surface finish, fabrication and exami…
URS-069 The system shall support a three-phase Performance Qualification: Phase 1 with daily sampling of …
URS-070 Sample points shall be provided at the tank outlet, the loop supply, the loop return, each sub-lo…
URS-071 Temperature mapping ports shall be provided at each worst-case location listed in Appendix A, suf…
URS-072 The supplier shall provide hydraulic calculations demonstrating that the minimum return velocity …
URS-073 Every requirement in this specification shall be traceable through design qualification, factory …
URS-074 The system shall permit challenge of the worst-case conditions listed in Appendix A during qualif…

DQDesign Qualification

Download Word
Full document text — PRJ-2026-0009 · EQ-02

DESIGN QUALIFICATION

Water for Injection Storage and Distribution System

DQ-WFI-001 · REVISION 0.1

Project reference PRJ-2026-0009
Equipment reference EQ-02 — WFI Storage and Distribution System
Document status Draft
Generated from URS-WFI-001 Revision 0.1
Supplier [Supplier name]
Design review date [DD-MMM-YYYY]
Prepared by [Enter author]
This document was drafted with software assistance. Verdicts are screening judgements against the supplier documentation listed in Section 3 and must be verified against those source documents by qualified personnel. This document has no validity until reviewed and approved in accordance with the site quality system. Pharma4i does not perform or record document approval; responsibility for review, approval, signature and document control rests with the approving persons named in Section 11.

Related Documents

This document forms part of the qualification package for PRJ-2026-0009 EQ-02. Documents marked Planned have not yet been produced.

Document Number Rev Status Relationship
User Requirements Specification URS-WFI-001 0.1 Issued Source of this document
Design Qualification DQ-WFI-001 0.1 Draft This document
Factory Acceptance Test protocol FAT-WFI-001 Planned Derived from this document
Site Acceptance Test protocol SAT-WFI-001 Planned Derived from this document
Installation Qualification IQ-WFI-001 Planned Derived from URS and DQ
Operational Qualification OQ-WFI-001 Planned Derived from URS and DQ
Performance Qualification PQ-WFI-001 Planned Derived from URS and DQ
Validation Summary Report VSR-WFI-001 Planned Derived from all of the above

Table of Contents

1. Introduction

This Design Qualification records the verification that the design proposed by the supplier meets the requirements stated in URS-WFI-001 Revision 0.1 for the Water for Injection storage and distribution system.

Design Qualification does not introduce requirements. Every entry in this document is a verdict against an existing requirement or against a worst-case condition identified in the User Requirements Specification. Where the specification did not fix a value, no verdict is possible and the requirement is listed as not yet defined.

This document is the documented evidence that the design was reviewed against the user requirement before manufacture, as required by EU GMP Annex 15.

2. Scope

2.1 Design documentation reviewed

The verdicts in this document are based solely on the supplier documentation listed in Section 3. No verdict is based on verbal assurance, on drawings not listed, or on assumed standard practice.

2.2 Out of scope

  • The WFI generation system, which is equipment item EQ-01 in this project and is the subject of a separate specification and Design Qualification.

  • Reject handling, diversion and generation sanitisation, which are addressed in the EQ-01 documentation. See Appendix C.

  • Point-of-use hoses and connectors.

  • Site utilities upstream of the connection points.

3. Reference Documents

Document Number Revision / date
User Requirements Specification URS-WFI-001 Rev 0.1
Supplier Functional Specification FS-001 Rev 2
Supplier Design Specification DS-003 Rev 1
General Arrangement drawing GA-002 Rev C
Piping and Instrumentation Diagram P&ID-005 Rev B
Isometric drawings ISO-011 Rev B
Hydraulic calculation CALC-004 Rev A
Material test certificate pack MTC pack As submitted
Passivation procedure QP-018 Rev 1
Operation and maintenance manual MAN-007 Rev 1
Supplier quotation [Quotation number] As submitted
EU GMP Annex 15 — Qualification and Validation Current
EU GMP Annex 11 — Computerised Systems Current

4. Methodology

Each requirement in URS-WFI-001 was compared against the supplier documentation listed in Section 3 and assigned one of the following verdicts.

Verdict Meaning
Met The documentation demonstrates that the design satisfies the requirement in full.
Partially met The design satisfies part of the requirement, or satisfies it under conditions narrower than the requirement states.
Not met The documentation shows a design that conflicts with the requirement.
Not addressed The documentation is silent on the requirement. Silence is recorded as a finding; it is not interpreted as compliance.
Not yet defined The User Requirements Specification did not fix the value, so no verification is possible. The finding is against the specification, not the design.

4.1 Review participants

Discipline Name Role in review
Engineering
Operations
MSAT
CQV / Validation
EHS
Automation / IT
Contamination Control
Quality Assurance

4.2 Limitations of this review

Verdicts were produced by comparison against the listed documents only. They are screening judgements and require verification against the source documents by qualified personnel before this document is issued. Where a verdict carries low confidence, the underlying evidence was indirect and the reviewer should treat it as unverified.

5. Acceptance Criteria

A requirement is judged met only where the supplier documentation states, in terms that can be checked, that the design achieves what the requirement demands, under the conditions the requirement specifies. A design that satisfies a requirement at nominal conditions but not at the worst-case conditions identified in the specification is judged partially met, not met.

The design is considered suitable for the intended use only where every requirement classified Critical in the specification is met, and every worst-case condition is addressed or has a recorded justification for exclusion.

6. Design Qualification Results

One row per requirement of URS-WFI-001 Revision 0.1, in specification order. No requirement is omitted.

URS ID Requirement (abridged) Verdict Design ref Evidence and observation
URS-001 The system shall store and distribute Water for Injection meeting the requirements of the current USP and Ph. Eur. monog… Met FS-001 §2.1 System specified to produce and distribute WFI to USP and Ph. Eur. monograph requirements.
URS-002 The system shall deliver a peak instantaneous demand of [TO BE CONFIRMED] L/min and an average daily consumption of [TO … Not yet defined

The URS leaves peak demand and daily consumption as [TO BE CONFIRMED]. No design verification is possible.

Observation: Peak demand must be fixed in the URS before the hydraulic design can be verified.

URS-003 The system shall operate continuously, 24 hours per day, 7 days per week, with planned shutdown limited to [TO BE CONFIR… Not yet defined Permitted annual shutdown is [TO BE CONFIRMED] in the URS.
URS-004 The storage tank shall have a nominal capacity of [TO BE CONFIRMED] L, sized to buffer peak demand without the generatio… Not yet defined

Tank capacity is [TO BE CONFIRMED] in the URS. Supplier has offered 5,000 L on the quotation but the requirement is not fixed.

Observation: Confirm the required capacity, then re-verify against the offered 5,000 L vessel.

URS-005 The distribution loop shall serve [TO BE CONFIRMED] points of use, listed with their location, required flow and require… Not yet defined Point-of-use count is [TO BE CONFIRMED] in the URS. The supplier P&ID shows 12.
URS-006 The system shall recover to full specification within [TO BE CONFIRMED] hours following a planned shutdown, without requ… Not addressed

No recovery time following planned shutdown is stated in any supplier document.

Observation: Request the supplier state the expected recovery time and the basis for it.

URS-007 WFI shall be stored and distributed under continuous hot circulation at a temperature not less than 80 °C at every point… Partially met FS-001 §4.2

Design states loop maintained at 80–85 °C. The measurement location is given as the loop supply header.

Observation: The URS requires 80 °C at the least favourable point, not at the supply header. Confirm the coldest point and how it is monitored.

URS-008 The distribution loop shall maintain a return flow velocity of not less than 1.0 m/s, or a demonstrated turbulent flow w… Partially met CALC-004 rev A

Hydraulic calculation demonstrates 1.12 m/s return velocity. The calculation is performed at average demand of 40 L/min.

Observation: Velocity must be demonstrated at maximum simultaneous demand, not average. See worst-case condition WC-01.

URS-009 The system shall be fitted with duty and standby distribution pumps with automatic changeover on failure, and an automat… Partially met FS-001 §5.1, GA-002

Duty and standby pumps are provided with automatic changeover on failure.

Observation: No automatic duty rotation is described. The standby pump leg is a stagnant branch between manual changeovers.

URS-010 Loop temperature shall be maintained by a heat exchanger of double tube sheet construction with a monitored and drainabl… Met DS-003 §3.4 Double tube sheet heat exchanger specified with drainable, monitored interspace and leak detection to the control system.
URS-011 The storage tank shall be fitted with a spray ball providing demonstrated full wetted coverage of the internal surface, … Partially met DS-003 §2.2

Spray ball specified with stated coverage of the vessel internal surface.

Observation: No coverage verification method is offered, and headspace coverage at minimum operating level is not addressed. See WC-05.

URS-012 The storage tank shall be fitted with a hydrophobic vent filter of 0.22 micrometre rating, electrically heated to preven… Partially met DS-003 §2.6

Hydrophobic 0.22 µm vent filter, electrically heated, is specified.

Observation: In-place integrity testing without breaking the sterile boundary is not described. Confirm the test connection arrangement.

URS-013 Points of use requiring water below loop temperature shall be served by dedicated point-of-use coolers arranged so that … Not addressed

No point-of-use cooler arrangement appears in any supplier document, although the point-of-use schedule identifies four points requiring water below loop temperature.

Observation: This is a significant gap. Point-of-use coolers are the highest microbial risk location in a hot loop. See WC-04.

URS-014 The system shall provide a thermal sanitisation cycle capable of raising every point in the loop, including every point-… Not yet defined

Sanitisation temperature and hold time are [TO BE CONFIRMED] in the URS. The supplier proposes 85 °C for 30 minutes but no requirement exists to verify against.

Observation: Sanitisation temperature and hold time must be fixed by the user before the cycle can be qualified.

URS-015 Tank level shall be controlled automatically, with high, high-high, low and low-low alarms, and with pump protection pre… Met FS-001 §6.3 Level control with high, high-high, low and low-low alarms, and pump low-level protection.
URS-016 The system shall deliver a minimum dynamic pressure of [TO BE CONFIRMED] bar g at the most hydraulically remote point of… Not yet defined Minimum dynamic pressure at the remote point of use is [TO BE CONFIRMED] in the URS.
URS-017 The control system shall continuously record loop supply temperature, loop return temperature, tank level, loop flow, lo… Met FS-001 §7.1 All listed parameters recorded at 30-second intervals, exceeding the one-minute requirement.
URS-018 The system shall record every sanitisation cycle, capturing the temperature profile at each monitored location, the hold… Partially met FS-001 §7.4

Sanitisation cycles are recorded with the temperature profile and outcome.

Observation: The operator who initiated the cycle is not recorded. Required by the URS and by records controls.

URS-019 All alarms shall be recorded with the alarm condition, time of onset, time of acknowledgement, the acknowledging operato… Met FS-001 §7.5 Alarms recorded with onset, acknowledgement, acknowledging operator and clearance.
URS-020 Records shall be retained for not less than [TO BE CONFIRMED] years and shall be exportable in a human-readable format t… Not yet defined Retention period is [TO BE CONFIRMED] in the URS.
URS-021 Records shall be attributable, legible, contemporaneous, original and accurate, and shall remain complete, consistent, e… Partially met FS-001 §8.1

Records described as attributable, legible and contemporaneous.

Observation: Enduring and available over the retention period are not addressed; no archival strategy is described.

URS-022 The system clock shall synchronise with the site time server. Users shall not be able to alter system time, and any time… Met FS-001 §8.5 NTP synchronisation to site time server; system time not user-alterable.
URS-023 The system shall support automated backup of all GMP records, and restoration of those records shall be demonstrated dur… Partially met FS-001 §8.6

Automated daily backup to a site network location is described.

Observation: Restoration is not described and no restoration test is offered during qualification.

URS-024 No function shall permit deletion or overwriting of a recorded value. Corrections shall be made by a new entry that pres… Met FS-001 §8.3 No delete or overwrite function on recorded values; corrections by new entry.
URS-025 The control system shall provide role-based access control with individual named user accounts. Shared or generic accoun… Met FS-001 §9.1 Role-based access with individual named accounts; generic accounts not permitted.
URS-026 The system shall provide at least the roles Operator, Supervisor, Engineer and Administrator, with the permissions of ea… Met FS-001 §9.2 Operator, Supervisor, Engineer and Administrator roles with defined permissions.
URS-027 Critical setpoints, including sanitisation temperature and hold time, alarm limits and calibration parameters, shall be … Partially met FS-001 §9.3

Setpoint changes restricted to Engineer and Administrator roles.

Observation: Calibration parameters are modifiable at Supervisor level. The URS requires authorised roles only; confirm whether Supervisor is intended to be authorised.

URS-028 The system shall enforce automatic session timeout after a configurable period of inactivity, and shall require re-authe… Met FS-001 §9.5 Configurable inactivity timeout with re-authentication.
URS-029 The system shall maintain a secure, computer-generated, time-stamped audit trail recording the operator identity, date, … Met FS-001 §10.1 Audit trail records operator, date, time, previous and new value for GMP-relevant changes.
URS-030 The audit trail shall not be editable or disableable by any user, including administrators, and shall be reviewable with… Not met FS-001 §10.2

The functional specification states the audit trail "may be disabled by the Administrator for maintenance purposes."

Observation: The URS requires that the audit trail not be disableable by any user including administrators. This is a direct conflict and must be resolved before design freeze.

URS-031 The system shall support periodic audit trail review, with a filterable view and an exportable report of changes over a … Partially met FS-001 §10.4

Audit trail is viewable in the application with date filtering.

Observation: No exportable report over a selected period is offered. Required to support periodic review.

URS-032 The system shall interface with the upstream WFI generation system, exchanging demand signal, generation status and out-… Met FS-001 §11.1, P&ID-005 Interface to generation system exchanging demand, status and diversion signals.
URS-033 The system shall provide monitored signals to the site building management system for alarm annunciation, without permit… Met FS-001 §11.2 Monitored alarm signals to BMS, read-only, no control authority.
URS-034 The system shall provide the physical and electrical interface at each point of use defined in the point-of-use schedule… Partially met GA-002, P&ID-005

Mechanical interfaces shown at all points of use.

Observation: Control interfaces to the two formulation vessels are not described. Confirm signal requirements.

URS-035 Where sample results are managed in a laboratory information management system, the system shall support export of onlin… Not addressed

No data export capability for correlation with laboratory results is described.

Observation: Desirable requirement. Confirm whether it is being carried forward.

URS-036 The system shall operate within the site utility envelope: electrical supply [TO BE CONFIRMED], plant steam or heating m… Not yet defined

The URS leaves the utility envelope as [TO BE CONFIRMED].

Observation: Complete the utility schedule and re-verify against the supplier utility list.

URS-037 All drain connections shall discharge through an air break to prevent backflow, and shall be visible for inspection.… Met P&ID-005 All drains shown discharging through an air break, visible for inspection.
URS-038 All hot surfaces accessible to personnel shall be insulated or guarded such that touchable surface temperature does not … Met DS-003 §7.2 Insulation specified to limit touchable surface temperature to 55 °C.
URS-039 Pipework shall be installed with a continuous fall of not less than 1 in 100 towards designated drain points, so that th… Partially met ISO-011 rev B

Isometric drawings show a stated fall towards drain points.

Observation: The fall is shown as 1:150 on two horizontal runs against the URS requirement of 1:100. See WC-09.

URS-040 Loop pipework routed through classified areas shall be finished and supported so as not to compromise the cleanability o… Not addressed Routing through classified areas and support arrangements are not described.
URS-041 All product contact surfaces shall be stainless steel 316L, with a mechanically polished and electropolished internal su… Met DS-003 §1.1, MTC pack 316L specified throughout, mechanically polished and electropolished to Ra 0.38 µm, with mill certificates provided.
URS-042 All product contact welds shall be automatic orbital welds. A weld log shall be maintained, and not less than [TO BE CON… Not yet defined

Boroscopy percentage is [TO BE CONFIRMED] in the URS. The supplier offers 10%.

Observation: Fix the required percentage in the URS. 10% is at the low end of common practice.

URS-043 The system shall be passivated after installation in accordance with a documented procedure, and a passivation certifica… Met QP-018 Passivation procedure provided; certificate to be issued on completion.
URS-044 Material certificates in accordance with EN 10204 Type 3.1 shall be provided for all product contact materials, traceabl… Met MTC pack EN 10204 Type 3.1 certificates provided for all product contact materials, traceable to component tags.
URS-045 Elastomers and polymers in product contact shall comply with USP Class VI and 21 CFR 177.2600, shall be suitable for con… Partially met DS-003 §1.4

EPDM gaskets specified, stated as USP Class VI compliant.

Observation: 21 CFR 177.2600 compliance is not stated, and no service life at 85 °C continuous is given.

URS-046 All valves in product contact shall be sanitary diaphragm valves of zero static or zero dead leg design, installed so th… Met P&ID-005, DS-003 §1.6 Sanitary diaphragm valves of zero static design throughout, shown self-draining.
URS-047 No dead leg in the distribution system shall exceed three internal pipe diameters (3D), measured from the internal wall … Not met DS-003 §1.7

The design specification states dead legs are controlled to 6D.

Observation: The URS requires 3D. This is a direct conflict. Six diameters is a materially different microbial risk and must be resolved before design freeze. See WC-07.

URS-048 The complete system, including the tank, loop, all branches and all points of use, shall be fully drainable to a designa… Partially met ISO-011 rev B

Drain points provided at identified low points.

Observation: Full drainability without dismantling is not demonstrated for the two point-of-use branches on the north elevation.

URS-049 The sanitisation cycle shall be initiated from the operator interface, shall run automatically, and shall not be capable… Partially met FS-001 §6.7

Sanitisation initiated from the operator interface and runs automatically.

Observation: The cycle is declared complete on elapsed time. It does not verify that every monitored location achieved the required temperature and hold. See WC-03.

URS-050 Sample valves at each sampling location shall be of sanitary design, self-draining, and shall permit sampling without co… Met DS-003 §4.1 Sanitary self-draining sample valves at all listed locations.
URS-051 All instruments requiring calibration shall be accessible without dismantling major assemblies and shall be removable wi… Partially met GA-002

Instruments shown at accessible locations.

Observation: Removal without breaching the loop in operation is not described for the loop return conductivity cell.

URS-052 The supplier shall provide a preventive maintenance schedule stating each task, its frequency and estimated duration, an… Met MAN-007 Preventive maintenance schedule provided with tasks, frequency and duration. Ten-year spares availability confirmed in the quotation.
URS-053 The storage tank shall be protected against overpressure and vacuum by a rupture disc and a pressure and vacuum relief a… Met DS-003 §2.8 Rupture disc with burst detection, and combined pressure and vacuum relief.
URS-054 An emergency stop shall be provided at the skid and at each remote pump location, placing the system in a defined safe s… Met FS-001 §12.1 Emergency stop at the skid and at the remote pump station.
URS-055 Interlocks shall prevent operation of distribution pumps against a closed system and shall prevent sanitisation while an… Partially met FS-001 §12.3

Interlock prevents pump operation against a closed system.

Observation: No interlock prevents sanitisation while a point of use is open to an operator-accessible outlet. This is a scald hazard.

URS-056 Sanitisation shall not be capable of being started without a positive confirmation step, and every point of use shall be… Not addressed

No positive confirmation step before sanitisation start and no point-of-use lockout indication are described.

Observation: Combine with URS-055 into a single supplier query on sanitisation safety.

URS-057 Noise emitted by the system shall not exceed 80 dB(A) measured at one metre under normal operation.… Met DS-003 §7.4 Predicted 74 dB(A) at one metre.
URS-058 The supplier shall provide, prior to Factory Acceptance Testing: general arrangement drawings, piping and instrumentatio… Met Document register rev 3 All listed documents provided prior to FAT.
URS-059 The supplier shall provide FAT and SAT protocols for user review and approval not less than four weeks before the respec… Met Quotation §5 FAT and SAT protocols offered six weeks before each test.
URS-060 The supplier shall provide IQ and OQ protocols and supporting documentation aligned with EU GMP Annex 15, together with … Partially met Quotation §5

IQ and OQ protocols offered.

Observation: Weld logs, boroscopy records and slope verification records are not listed in the turnover package scope.

URS-061 The supplier shall provide operation and maintenance manuals, a spare parts list with part numbers, and a documented cha… Met MAN-007 O&M manuals, spare parts list and change notification procedure provided.
URS-062 The supplier shall provide training for operators, maintenance personnel, and quality and validation personnel, covering… Partially met Quotation §6

Operator and maintenance training offered.

Observation: No training on audit trail review or user administration for QA and validation personnel.

URS-063 The system shall comply with the current USP and Ph. Eur. monographs for Water for Injection and with USP General Chapte… Met FS-001 §2.1 Compliance with the WFI monograph requirements stated.
URS-064 WFI delivered at every point of use shall meet: conductivity in accordance with USP General Chapter 645; total organic c… Partially met FS-001 §2.3

Conductivity, TOC and microbial limits stated and matched to the URS.

Observation: Bacterial endotoxin limit is not stated in any supplier document.

URS-065 The system shall be designed, installed and qualified in accordance with EU GMP Annex 15 and the site validation master … Met Quotation §5 Qualification approach aligned to EU GMP Annex 15.
URS-066 The control system shall comply with EU GMP Annex 11 and, where applicable to the site, 21 CFR Part 11.… Partially met FS-001 §8

Annex 11 addressed. 21 CFR Part 11 applicability is stated as "available on request".

Observation: Confirm whether Part 11 applies to this site and, if so, that it is in the scope of supply.

URS-067 The system shall be designed and documented in accordance with GAMP 5, and the supplier shall state the GAMP software ca… Met FS-001 §1.3 Control system stated as GAMP category 4, configured product.
URS-068 Equipment design shall follow ASME BPE for hygienic design, surface finish, fabrication and examination of product conta… Met DS-003 §1 Hygienic design, surface finish and examination stated to follow ASME BPE.
URS-069 The system shall support a three-phase Performance Qualification: Phase 1 with daily sampling of every point of use, Pha… Partially met Quotation §5

Supplier supports a PQ programme.

Observation: Only Phase 1 and Phase 2 are within the scope of supply. Phase 3 over one year is excluded. Confirm who executes Phase 3.

URS-070 Sample points shall be provided at the tank outlet, the loop supply, the loop return, each sub-loop return and each poin… Met P&ID-005 Sample points at the tank outlet, loop supply, loop return and each point of use, individually tagged.
URS-071 Temperature mapping ports shall be provided at each worst-case location listed in Appendix A, sufficient to demonstrate … Not addressed

No temperature mapping ports are shown at the worst-case locations listed in the URS.

Observation: Without mapping ports at the least favourable points, sanitisation acceptance cannot be demonstrated where it matters. See WC-03.

URS-072 The supplier shall provide hydraulic calculations demonstrating that the minimum return velocity and minimum point-of-us… Partially met CALC-004 rev A

Hydraulic calculation provided.

Observation: Performed at average demand. The worst-case demand condition required by the URS is not calculated. See WC-01.

URS-073 Every requirement in this specification shall be traceable through design qualification, factory and site acceptance tes… Partially met Traceability matrix rev 1

A traceability matrix is provided.

Observation: It traces to the supplier functional specification, not to URS requirement identifiers. Request re-issue traced to URS IDs.

URS-074 The system shall permit challenge of the worst-case conditions listed in Appendix A during qualification without modific… Not addressed No statement that the installed system permits challenge of the worst-case conditions without modification.

7. Verification Against Worst-Case Conditions

The specification identifies conditions under which the system is least able to meet its requirements. A design demonstrated only at nominal conditions has not been shown to meet the specification. Each condition below is verified separately.

This is the section in which most design gaps are found. A supplier who demonstrates compliance at average demand has demonstrated nothing about behaviour at peak.

Ref Condition Verdict Design ref Evidence and observation Governs
WC-01 Maximum simultaneous demand Partially addressed CALC-004 rev A

Hydraulic calculation performed at 40 L/min average demand.

Observation: The condition is not calculated. Return velocity, return temperature and remote-point pressure all degrade together at peak; none is demonstrated at that condition.

URS-008, URS-016, URS-072
WC-02 Coldest point during normal circulation Not addressed

Loop temperature is stated at the supply header only.

Observation: The coldest point is not identified and is not monitored. Microbial control depends on it.

URS-007, URS-017
WC-03 Least favourable point during sanitisation Not addressed

Sanitisation is verified on elapsed time at the supply header.

Observation: No mapping ports and no acceptance at the least favourable point. A cycle demonstrated at the header does not demonstrate control.

URS-014, URS-049, URS-071
WC-04 Point-of-use cooler branch Not addressed

No cooler arrangement appears in the design.

Observation: Four points of use require sub-loop temperature water. This is the highest microbial risk location in a hot loop and it is undesigned.

URS-013, URS-064
WC-05 Tank at minimum operating level Partially addressed DS-003 §2.2

Spray ball coverage stated for the vessel internal surface.

Observation: Headspace coverage at minimum level is not addressed and no coverage verification is offered.

URS-004, URS-011, URS-015
WC-06 Maximum tank discharge rate Addressed DS-003 §2.6 Vent filter sized for the stated maximum discharge rate with heater duty calculated. URS-012
WC-07 Longest branch and standby pump leg Not addressed DS-003 §1.7

Dead legs stated as controlled to 6D.

Observation: Conflicts with the URS 3D requirement, and no duty rotation is provided for the standby pump leg. Two stagnation risks in one condition.

URS-009, URS-046, URS-047
WC-08 Most hydraulically remote point of use Partially addressed CALC-004 rev A

Pressure calculated at the remote point at average demand.

Observation: Not calculated at peak. The URS pressure requirement is itself undefined.

URS-016, URS-072
WC-09 Highest point and longest horizontal run Partially addressed ISO-011 rev B

Fall towards drain shown throughout.

Observation: Two runs at 1:150 against the URS requirement of 1:100.

URS-039, URS-048
WC-10 Extended low-demand period Not addressed

Not considered in any supplier document.

Observation: No first-draw or restart strategy after a low-demand period.

URS-003, URS-006
WC-11 Worst-case feed water quality Not addressed

Feed water variation is treated as the generation system scope.

Observation: Correct as far as it goes, but the distribution PQ Phase 3 must still cover seasonal variation and Phase 3 is excluded from supply.

URS-063, URS-064, URS-069

8. Summary of Findings

8.1 Requirements

Verdict Count Note
Met 32
Partially met 24
Not met 2 Direct conflict; must be resolved before design freeze.
Not addressed 7
Not yet defined 9 Finding against the specification, not the design.

Total requirements verified: 74.

8.2 Requirements not met — resolution required before design freeze

  • URS-030 — the functional specification permits the audit trail to be disabled by an administrator. The specification requires that it not be disableable by any user. Direct conflict.

  • URS-047 — the design specification states dead legs controlled to 6D against a specification requirement of 3D. Materially different microbial risk.

8.3 Worst-case conditions

Verdict Count Note
Addressed 1
Partially addressed 4
Not addressed 6

8.4 Requirements not yet defined in the specification

The following requirements could not be verified because the User Requirements Specification does not fix a value. These are findings against the specification and must be closed before the design can be qualified.

URS-002, URS-003, URS-004, URS-005, URS-014, URS-016, URS-020, URS-036, URS-042

9. Observations Register

Each observation below requires resolution with the supplier. Resolution and closure are recorded on this register.

Observation Against Verdict Description / Resolution
DQ-OBS-001 URS-002 Not yet defined

Peak demand must be fixed in the URS before the hydraulic design can be verified.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-002 URS-004 Not yet defined

Confirm the required capacity, then re-verify against the offered 5,000 L vessel.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-003 URS-006 Not addressed

Request the supplier state the expected recovery time and the basis for it.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-004 URS-007 Partially met

The URS requires 80 °C at the least favourable point, not at the supply header. Confirm the coldest point and how it is monitored.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-005 URS-008 Partially met

Velocity must be demonstrated at maximum simultaneous demand, not average. See worst-case condition WC-01.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-006 URS-009 Partially met

No automatic duty rotation is described. The standby pump leg is a stagnant branch between manual changeovers.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-007 URS-011 Partially met

No coverage verification method is offered, and headspace coverage at minimum operating level is not addressed. See WC-05.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-008 URS-012 Partially met

In-place integrity testing without breaking the sterile boundary is not described. Confirm the test connection arrangement.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-009 URS-013 Not addressed

This is a significant gap. Point-of-use coolers are the highest microbial risk location in a hot loop. See WC-04.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-010 URS-014 Not yet defined

Sanitisation temperature and hold time must be fixed by the user before the cycle can be qualified.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-011 URS-018 Partially met

The operator who initiated the cycle is not recorded. Required by the URS and by records controls.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-012 URS-021 Partially met

Enduring and available over the retention period are not addressed; no archival strategy is described.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-013 URS-023 Partially met

Restoration is not described and no restoration test is offered during qualification.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-014 URS-027 Partially met

Calibration parameters are modifiable at Supervisor level. The URS requires authorised roles only; confirm whether Supervisor is intended to be authorised.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-015 URS-030 Not met

The URS requires that the audit trail not be disableable by any user including administrators. This is a direct conflict and must be resolved before design freeze.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-016 URS-031 Partially met

No exportable report over a selected period is offered. Required to support periodic review.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-017 URS-034 Partially met

Control interfaces to the two formulation vessels are not described. Confirm signal requirements.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-018 URS-035 Not addressed

Desirable requirement. Confirm whether it is being carried forward.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-019 URS-036 Not yet defined

Complete the utility schedule and re-verify against the supplier utility list.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-020 URS-039 Partially met

The fall is shown as 1:150 on two horizontal runs against the URS requirement of 1:100. See WC-09.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-021 URS-042 Not yet defined

Fix the required percentage in the URS. 10% is at the low end of common practice.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-022 URS-045 Partially met

21 CFR 177.2600 compliance is not stated, and no service life at 85 °C continuous is given.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-023 URS-047 Not met

The URS requires 3D. This is a direct conflict. Six diameters is a materially different microbial risk and must be resolved before design freeze. See WC-07.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-024 URS-048 Partially met

Full drainability without dismantling is not demonstrated for the two point-of-use branches on the north elevation.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-025 URS-049 Partially met

The cycle is declared complete on elapsed time. It does not verify that every monitored location achieved the required temperature and hold. See WC-03.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-026 URS-051 Partially met

Removal without breaching the loop in operation is not described for the loop return conductivity cell.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-027 URS-055 Partially met

No interlock prevents sanitisation while a point of use is open to an operator-accessible outlet. This is a scald hazard.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-028 URS-056 Not addressed

Combine with URS-055 into a single supplier query on sanitisation safety.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-029 URS-060 Partially met

Weld logs, boroscopy records and slope verification records are not listed in the turnover package scope.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-030 URS-062 Partially met

No training on audit trail review or user administration for QA and validation personnel.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-031 URS-064 Partially met

Bacterial endotoxin limit is not stated in any supplier document.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-032 URS-066 Partially met

Confirm whether Part 11 applies to this site and, if so, that it is in the scope of supply.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-033 URS-069 Partially met

Only Phase 1 and Phase 2 are within the scope of supply. Phase 3 over one year is excluded. Confirm who executes Phase 3.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-034 URS-071 Not addressed

Without mapping ports at the least favourable points, sanitisation acceptance cannot be demonstrated where it matters. See WC-03.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-035 URS-072 Partially met

Performed at average demand. The worst-case demand condition required by the URS is not calculated. See WC-01.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-036 URS-073 Partially met

It traces to the supplier functional specification, not to URS requirement identifiers. Request re-issue traced to URS IDs.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-037 WC-01 Partially addressed

The condition is not calculated. Return velocity, return temperature and remote-point pressure all degrade together at peak; none is demonstrated at that condition.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-038 WC-02 Not addressed

The coldest point is not identified and is not monitored. Microbial control depends on it.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-039 WC-03 Not addressed

No mapping ports and no acceptance at the least favourable point. A cycle demonstrated at the header does not demonstrate control.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-040 WC-04 Not addressed

Four points of use require sub-loop temperature water. This is the highest microbial risk location in a hot loop and it is undesigned.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-041 WC-05 Partially addressed

Headspace coverage at minimum level is not addressed and no coverage verification is offered.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-042 WC-07 Not addressed

Conflicts with the URS 3D requirement, and no duty rotation is provided for the standby pump leg. Two stagnation risks in one condition.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-043 WC-08 Partially addressed

Not calculated at peak. The URS pressure requirement is itself undefined.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-044 WC-09 Partially addressed

Two runs at 1:150 against the URS requirement of 1:100.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-045 WC-10 Not addressed

No first-draw or restart strategy after a low-demand period.

Resolution: ________________________________ Closed by: ____________ Date: __________

DQ-OBS-046 WC-11 Not addressed

Correct as far as it goes, but the distribution PQ Phase 3 must still cover seasonal variation and Phase 3 is excluded from supply.

Resolution: ________________________________ Closed by: ____________ Date: __________

10. Conclusion

Based on the review recorded in this document, of 74 requirements in URS-WFI-001 Revision 0.1: 32 are met, 24 are partially met, 2 are not met, 7 are not addressed, and 9 could not be verified because the specification does not fix a value.

Of 11 worst-case conditions, 1 are addressed, 4 are partially addressed and 6 are not addressed.

The design is [ suitable / suitable subject to resolution of the observations listed in Section 9 / not suitable ] for the intended use.

The bracketed judgement above is drafted from the counts recorded in this document. It is a judgement for the reviewer and must be confirmed, amended or replaced by qualified personnel before this document is issued. Pharma4i does not make this determination.

Note for the reviewer: two requirements are in direct conflict with the design (Section 8.2) and four worst-case conditions are unaddressed, including the point-of-use cooler arrangement, which is undesigned. On the counts recorded here, a conclusion of "suitable" without qualification would not be supportable.

11. Approval and Sign-off

Signature below indicates that the signatory has reviewed this Design Qualification, has verified the verdicts against the source documents listed in Section 3, and accepts the conclusion recorded in Section 10.

Role Name Department Signature Date
Author Engineering
Reviewer Operations
Reviewer MSAT
Reviewer CQV / Validation
Reviewer Automation / IT
Reviewer Contamination Control
Quality approval Quality Assurance

12. Revision History

Revision Date Description of change Author
0.1 [DD-MMM-YYYY] First draft.

Appendix A — Traceability

Each requirement of URS-WFI-001 against its verdict and the design document that satisfies it. The test reference column is completed as FAT, SAT, IQ, OQ and PQ documents are raised.

URS ID Requirement summary Criticality DQ verdict Design ref Test ref
URS-001 The system shall store and distribute Water for Injection meeting the requirements of the … Mandatory Met FS-001 §2.1
URS-002 The system shall deliver a peak instantaneous demand of [TO BE CONFIRMED] L/min and an ave… Mandatory Not yet defined
URS-003 The system shall operate continuously, 24 hours per day, 7 days per week, with planned shu… Mandatory Not yet defined
URS-004 The storage tank shall have a nominal capacity of [TO BE CONFIRMED] L, sized to buffer pea… Mandatory Not yet defined
URS-005 The distribution loop shall serve [TO BE CONFIRMED] points of use, listed with their locat… Mandatory Not yet defined
URS-006 The system shall recover to full specification within [TO BE CONFIRMED] hours following a … Desirable Not addressed
URS-007 WFI shall be stored and distributed under continuous hot circulation at a temperature not … Mandatory Partially met FS-001 §4.2
URS-008 The distribution loop shall maintain a return flow velocity of not less than 1.0 m/s, or a… Mandatory Partially met CALC-004 rev A
URS-009 The system shall be fitted with duty and standby distribution pumps with automatic changeo… Mandatory Partially met FS-001 §5.1, GA-002
URS-010 Loop temperature shall be maintained by a heat exchanger of double tube sheet construction… Mandatory Met DS-003 §3.4
URS-011 The storage tank shall be fitted with a spray ball providing demonstrated full wetted cove… Mandatory Partially met DS-003 §2.2
URS-012 The storage tank shall be fitted with a hydrophobic vent filter of 0.22 micrometre rating,… Mandatory Partially met DS-003 §2.6
URS-013 Points of use requiring water below loop temperature shall be served by dedicated point-of… Mandatory Not addressed
URS-014 The system shall provide a thermal sanitisation cycle capable of raising every point in th… Mandatory Not yet defined
URS-015 Tank level shall be controlled automatically, with high, high-high, low and low-low alarms… Mandatory Met FS-001 §6.3
URS-016 The system shall deliver a minimum dynamic pressure of [TO BE CONFIRMED] bar g at the most… Mandatory Not yet defined
URS-017 The control system shall continuously record loop supply temperature, loop return temperat… Mandatory Met FS-001 §7.1
URS-018 The system shall record every sanitisation cycle, capturing the temperature profile at eac… Mandatory Partially met FS-001 §7.4
URS-019 All alarms shall be recorded with the alarm condition, time of onset, time of acknowledgem… Mandatory Met FS-001 §7.5
URS-020 Records shall be retained for not less than [TO BE CONFIRMED] years and shall be exportabl… Mandatory Not yet defined
URS-021 Records shall be attributable, legible, contemporaneous, original and accurate, and shall … Mandatory Partially met FS-001 §8.1
URS-022 The system clock shall synchronise with the site time server. Users shall not be able to a… Mandatory Met FS-001 §8.5
URS-023 The system shall support automated backup of all GMP records, and restoration of those rec… Mandatory Partially met FS-001 §8.6
URS-024 No function shall permit deletion or overwriting of a recorded value. Corrections shall be… Mandatory Met FS-001 §8.3
URS-025 The control system shall provide role-based access control with individual named user acco… Mandatory Met FS-001 §9.1
URS-026 The system shall provide at least the roles Operator, Supervisor, Engineer and Administrat… Mandatory Met FS-001 §9.2
URS-027 Critical setpoints, including sanitisation temperature and hold time, alarm limits and cal… Mandatory Partially met FS-001 §9.3
URS-028 The system shall enforce automatic session timeout after a configurable period of inactivi… Mandatory Met FS-001 §9.5
URS-029 The system shall maintain a secure, computer-generated, time-stamped audit trail recording… Mandatory Met FS-001 §10.1
URS-030 The audit trail shall not be editable or disableable by any user, including administrators… Mandatory Not met FS-001 §10.2
URS-031 The system shall support periodic audit trail review, with a filterable view and an export… Mandatory Partially met FS-001 §10.4
URS-032 The system shall interface with the upstream WFI generation system, exchanging demand sign… Mandatory Met FS-001 §11.1, P&ID-005
URS-033 The system shall provide monitored signals to the site building management system for alar… Mandatory Met FS-001 §11.2
URS-034 The system shall provide the physical and electrical interface at each point of use define… Mandatory Partially met GA-002, P&ID-005
URS-035 Where sample results are managed in a laboratory information management system, the system… Desirable Not addressed
URS-036 The system shall operate within the site utility envelope: electrical supply [TO BE CONFIR… Mandatory Not yet defined
URS-037 All drain connections shall discharge through an air break to prevent backflow, and shall … Mandatory Met P&ID-005
URS-038 All hot surfaces accessible to personnel shall be insulated or guarded such that touchable… Mandatory Met DS-003 §7.2
URS-039 Pipework shall be installed with a continuous fall of not less than 1 in 100 towards desig… Mandatory Partially met ISO-011 rev B
URS-040 Loop pipework routed through classified areas shall be finished and supported so as not to… Mandatory Not addressed
URS-041 All product contact surfaces shall be stainless steel 316L, with a mechanically polished a… Mandatory Met DS-003 §1.1, MTC pack
URS-042 All product contact welds shall be automatic orbital welds. A weld log shall be maintained… Mandatory Not yet defined
URS-043 The system shall be passivated after installation in accordance with a documented procedur… Mandatory Met QP-018
URS-044 Material certificates in accordance with EN 10204 Type 3.1 shall be provided for all produ… Mandatory Met MTC pack
URS-045 Elastomers and polymers in product contact shall comply with USP Class VI and 21 CFR 177.2… Mandatory Partially met DS-003 §1.4
URS-046 All valves in product contact shall be sanitary diaphragm valves of zero static or zero de… Mandatory Met P&ID-005, DS-003 §1.6
URS-047 No dead leg in the distribution system shall exceed three internal pipe diameters (3D), me… Mandatory Not met DS-003 §1.7
URS-048 The complete system, including the tank, loop, all branches and all points of use, shall b… Mandatory Partially met ISO-011 rev B
URS-049 The sanitisation cycle shall be initiated from the operator interface, shall run automatic… Mandatory Partially met FS-001 §6.7
URS-050 Sample valves at each sampling location shall be of sanitary design, self-draining, and sh… Mandatory Met DS-003 §4.1
URS-051 All instruments requiring calibration shall be accessible without dismantling major assemb… Mandatory Partially met GA-002
URS-052 The supplier shall provide a preventive maintenance schedule stating each task, its freque… Mandatory Met MAN-007
URS-053 The storage tank shall be protected against overpressure and vacuum by a rupture disc and … Mandatory Met DS-003 §2.8
URS-054 An emergency stop shall be provided at the skid and at each remote pump location, placing … Mandatory Met FS-001 §12.1
URS-055 Interlocks shall prevent operation of distribution pumps against a closed system and shall… Mandatory Partially met FS-001 §12.3
URS-056 Sanitisation shall not be capable of being started without a positive confirmation step, a… Mandatory Not addressed
URS-057 Noise emitted by the system shall not exceed 80 dB(A) measured at one metre under normal o… Desirable Met DS-003 §7.4
URS-058 The supplier shall provide, prior to Factory Acceptance Testing: general arrangement drawi… Mandatory Met Document register rev 3
URS-059 The supplier shall provide FAT and SAT protocols for user review and approval not less tha… Mandatory Met Quotation §5
URS-060 The supplier shall provide IQ and OQ protocols and supporting documentation aligned with E… Mandatory Partially met Quotation §5
URS-061 The supplier shall provide operation and maintenance manuals, a spare parts list with part… Mandatory Met MAN-007
URS-062 The supplier shall provide training for operators, maintenance personnel, and quality and … Mandatory Partially met Quotation §6
URS-063 The system shall comply with the current USP and Ph. Eur. monographs for Water for Injecti… Mandatory Met FS-001 §2.1
URS-064 WFI delivered at every point of use shall meet: conductivity in accordance with USP Genera… Mandatory Partially met FS-001 §2.3
URS-065 The system shall be designed, installed and qualified in accordance with EU GMP Annex 15 a… Mandatory Met Quotation §5
URS-066 The control system shall comply with EU GMP Annex 11 and, where applicable to the site, 21… Mandatory Partially met FS-001 §8
URS-067 The system shall be designed and documented in accordance with GAMP 5, and the supplier sh… Mandatory Met FS-001 §1.3
URS-068 Equipment design shall follow ASME BPE for hygienic design, surface finish, fabrication an… Mandatory Met DS-003 §1
URS-069 The system shall support a three-phase Performance Qualification: Phase 1 with daily sampl… Mandatory Partially met Quotation §5
URS-070 Sample points shall be provided at the tank outlet, the loop supply, the loop return, each… Mandatory Met P&ID-005
URS-071 Temperature mapping ports shall be provided at each worst-case location listed in Appendix… Mandatory Not addressed
URS-072 The supplier shall provide hydraulic calculations demonstrating that the minimum return ve… Mandatory Partially met CALC-004 rev A
URS-073 Every requirement in this specification shall be traceable through design qualification, f… Mandatory Partially met Traceability matrix rev 1
URS-074 The system shall permit challenge of the worst-case conditions listed in Appendix A during… Mandatory Not addressed

Appendix B — Documents Reviewed

Every document on which a verdict in this Design Qualification is based. A verdict citing a document not listed here is an error and must be corrected before issue.

Document Number Revision Date received
Functional Specification FS-001 Rev 2
Design Specification DS-003 Rev 1
General Arrangement drawing GA-002 Rev C
Piping and Instrumentation Diagram P&ID-005 Rev B
Isometric drawings ISO-011 Rev B
Hydraulic calculation CALC-004 Rev A
Material test certificate pack MTC pack
Passivation procedure QP-018 Rev 1
Operation and maintenance manual MAN-007 Rev 1
Supplier quotation [Number]

Appendix C — Subjects Outside the Scope of the Specification

The following subjects are mandatory for this equipment type but are not addressed by URS-WFI-001, because they belong to the WFI generation system, equipment item EQ-01 in this project. They are therefore not verified by this Design Qualification and are addressed in the EQ-01 documentation.

Subject Where addressed
Recovery, reject handling and diversion WFI generation system, EQ-01. Not within the scope of supply for the distribution system.
Generation sanitisation regime WFI generation system, EQ-01. The distribution loop sanitisation regime is addressed at URS-014 and remains undefined.

A subject listed here is neither verified by this document nor by the specification it verifies against. Confirm it is genuinely covered in the EQ-01 documentation before relying on this exclusion.

Appendix D — Abbreviations

Term Definition
ASME BPE American Society of Mechanical Engineers Bioprocessing Equipment standard
CFU Colony Forming Unit
DQ Design Qualification
DS Design Specification
EU Endotoxin Unit
FAT Factory Acceptance Test
FS Functional Specification
GAMP Good Automated Manufacturing Practice
GA General Arrangement
IQ Installation Qualification
OQ Operational Qualification
P&ID Piping and Instrumentation Diagram
PQ Performance Qualification
Ra Roughness average
SAT Site Acceptance Test
TOC Total Organic Carbon
URS User Requirements Specification
WFI Water for Injection

FAT ProtocolFactory Acceptance Test Protocol

Download Word
Full document text — PRJ-2026-0009 · EQ-02

FACTORY ACCEPTANCE TEST PROTOCOL

Water for Injection Storage and Distribution System

FAT-WFI-001 · REVISION 0.1

Project reference PRJ-2026-0009
Equipment reference EQ-02 — WFI Storage and Distribution System
Document status Draft
Generated from URS-WFI-001 Rev 0.1 and DQ-WFI-001 Rev 0.1
Supplier [Supplier name]
Works location [Works location]
Planned test dates [DD-MMM-YYYY] to [DD-MMM-YYYY]
Prepared by [Enter author]
This protocol was drafted with software assistance. It has no validity until reviewed and approved by qualified personnel in accordance with the site quality system, and must not be executed before approval. Acceptance criteria are taken from URS-WFI-001 and are not independently established by this document. Pharma4i does not perform or record document approval.

Related Documents

This protocol forms part of the qualification package for PRJ-2026-0009 EQ-02.

Document Number Rev Status Relationship
User Requirements Specification URS-WFI-001 0.1 Issued Source of requirements
Design Qualification DQ-WFI-001 0.1 Issued Source of observations to close
FAT Protocol FAT-WFI-001 0.1 Draft This protocol
FAT Report FAT-WFI-001-R 0.1 Draft Records execution of this protocol
Site Acceptance Test protocol SAT-WFI-001 Planned Verifies requirements deferred from FAT
Installation Qualification IQ-WFI-001 Planned Planned
Operational Qualification OQ-WFI-001 Planned Planned
Performance Qualification PQ-WFI-001 Planned Planned
Validation Summary Report VSR-WFI-001 Planned Planned

Table of Contents

1. Introduction and Purpose

This protocol defines the tests to be performed at the supplier works to verify that the Water for Injection storage and distribution system, as manufactured, conforms to the requirements of URS-WFI-001 Revision 0.1 that can be verified in a works environment, and to confirm closure of the observations raised in DQ-WFI-001 Revision 0.1.

Factory Acceptance Testing establishes no new requirements. Every acceptance criterion in this protocol is taken from the User Requirements Specification. Where the specification does not fix a value, no criterion is stated and no test is performed; the requirement is recorded as untestable and the finding is against the specification.

Successful completion of this protocol is a precondition of shipment. It does not constitute qualification of the system.

2. Scope

2.1 In scope

  • Verification of construction, materials, surface finish and documentation against the specification.

  • Function testing of the control system, alarms, interlocks and safety devices.

  • Performance testing of the distribution pumps and instrumentation on potable water.

  • Verification of the storage vessel, spray ball coverage, vent filter and relief devices.

  • Closure of Design Qualification observations capable of resolution at the works.

  • Challenge of worst-case conditions capable of being created at the works.

2.2 Out of scope

  • Any test requiring Water for Injection, site utilities, the site network or a classified environment. These are listed in Section 11.

  • The WFI generation system, equipment item EQ-01.

  • Site installation, passivation and the qualification programme following delivery.

3. Reference Documents

Document Number Revision
User Requirements Specification URS-WFI-001 Rev 0.1
Design Qualification DQ-WFI-001 Rev 0.1
Supplier Functional Specification FS-001 Rev 2
Supplier Design Specification DS-003 Rev 1
Piping and Instrumentation Diagram P&ID-005 Rev B
Isometric drawings ISO-011 Rev B
Instrument index IDX-009 Rev 2
Electrical schematics ELE-014 Rev 4
EU GMP Annex 15 — Qualification and Validation Current
EU GMP Annex 11 — Computerised Systems Current

4. Responsibilities

Execution is by the supplier, witnessed and recorded by the user disciplines listed. A test performed without the required witness present is not valid and shall be repeated.

Discipline Name Responsibility
Supplier Executes the tests, provides equipment, media and documentation
Engineering Witnesses execution, records results, raises deviations
CQV / Validation Confirms protocol compliance and deviation classification
Operations Witnesses operability tests
Automation / IT Witnesses control system, access control and audit trail tests
EHS Witnesses safety and interlock tests
Quality Assurance Approves the protocol and the report

5. Test Prerequisites

The following shall be confirmed before any test is performed. Testing shall not begin until every item is satisfied, and the confirmation shall be recorded.

  • This protocol is approved and the approved copy is present at the works.

  • The equipment is mechanically complete against the general arrangement drawing, and any incomplete item is listed and agreed before starting.

  • The reference documents in Section 3 are available at the works at the revisions stated.

  • All test instruments listed in Section 6 are present and hold valid calibration certificates.

  • Potable water, compressed air and electrical supply are available at the works at the stated conditions.

  • Control system software is at the version recorded in FAT-037, and the version is recorded before testing begins.

  • All personnel listed in Section 4 are present or have delegated in writing.

6. Test Instruments and Calibration

Every instrument used shall hold a valid calibration certificate traceable to national standards. The required accuracy is stated relative to the tolerance being verified: an instrument whose accuracy equals the acceptance tolerance cannot demonstrate compliance.

Instrument Used in Required accuracy Cal. cert / due
Surface roughness tester FAT-003 Resolution 0.01 micrometres or better
Boroscope FAT-004 Suitable for the smallest pipe bore in scope
Digital level FAT-007 Accuracy 0.1 degrees or better
Pressure gauge FAT-009 Accuracy 1% of span or better, range to 1.5 x design
UV inspection lamp FAT-010 365 nm
Surface temperature probe FAT-011, FAT-034 Accuracy 1 degree C or better
Flow meter FAT-014 Accuracy 2% of reading or better
Signal simulator FAT-016, FAT-017 Accuracy 0.1% of span or better
Sound level meter FAT-033 Class 2 or better
Calibrated rule / calipers FAT-006 Resolution 1 mm or better
Stopwatch FAT-024 Resolution 1 second

7. Acceptance Criteria and Handling of Failures

A test passes only where the recorded result satisfies the stated acceptance criterion in full. A partial result is a failure.

Where a test fails, execution continues unless the failure creates a safety hazard or prevents subsequent tests. Each failure is recorded as a deviation with a classification of critical, major or minor, entered in the deviation log at Appendix B, and carried to the punch list where rework is required.

A critical deviation prevents shipment until closed and retested. A major deviation prevents shipment unless a documented concession is approved by Quality Assurance. A minor deviation may be carried to site with an agreed closure date.

No acceptance criterion in this protocol may be amended during execution. If a criterion is found to be wrong, testing of that item stops and the specification is corrected through change control.

8. Test Scripts

Tests are presented in specification order. Each cites the requirement it verifies and, where applicable, the Design Qualification observation it closes.

FAT-001 — Verify the supplier documentation pack is complete and current before testing begins.

Test ID FAT-001
Traces to URS-058
Objective Verify the supplier documentation pack is complete and current before testing begins.

Method

1. Request the document register.

2. Confirm each document listed in the URS documentation requirement is present.

3. Record document number and revision for each.

Acceptance criterion

All documents required by URS-058 are present, at a stated revision, and match the document register.

Test instrument Result
Performed by Pass / Fail Date

FAT-002 — Verify material certificates for all product contact materials.

Test ID FAT-002
Traces to URS-044
Objective Verify material certificates for all product contact materials.

Method

1. Obtain the material certificate pack.

2. For each product contact item, trace the certificate to the installed component tag.

3. Confirm certificate type.

Acceptance criterion

EN 10204 Type 3.1 certificates present for every product contact item, traceable to component tags.

Test instrument Result
Performed by Pass / Fail Date

FAT-003 — Verify product contact material and surface finish.

Test ID FAT-003
Traces to URS-041
Objective Verify product contact material and surface finish.

Method

1. Confirm material grade from certificates and component markings.

2. Measure internal surface finish at five accessible locations using a calibrated profilometer.

3. Record each reading.

Acceptance criterion

Material is 316L. Ra not greater than 0.4 micrometres at every measured location.

Test instrument Surface roughness tester, resolution 0.01 micrometres or better Result
Performed by Pass / Fail Date

FAT-004 — Verify orbital weld records and boroscopic inspection.

Test ID FAT-004
Traces to URS-042
Objective Verify orbital weld records and boroscopic inspection.

Method

1. Review the weld log against the isometric drawings.

2. Confirm each product contact weld is recorded.

3. Review boroscopy records against the required percentage.

Acceptance criterion

ACCEPTANCE CRITERION NOT DEFINED IN THE URS. The required boroscopy percentage is [TO BE CONFIRMED] in URS-042.

Test instrument Boroscope Result
Performed by Pass / Fail Date

FAT-005 — Verify valve type and installation.

Test ID FAT-005
Traces to URS-046
Objective Verify valve type and installation.

Method

1. Identify every product contact valve against the P&ID.

2. Confirm sanitary diaphragm type and zero static design.

3. Confirm each branch is self-draining by visual inspection with the skid level.

Acceptance criterion

All product contact valves are sanitary diaphragm, zero static design, installed self-draining.

Test instrument Spirit level Result
Performed by Pass / Fail Date

FAT-006 — Verify dead leg dimensions against the specification.

Test ID FAT-006
Traces to URS-047 | Closes DQ-OBS-032
Objective Verify dead leg dimensions against the specification.

Method

1. Measure each branch from the internal wall of the main loop to the point of closure.

2. Express as a multiple of internal pipe diameter.

3. Record every branch.

Acceptance criterion

No dead leg exceeds three internal pipe diameters (3D) as required by URS-047.

Test instrument Calibrated rule / calipers Result
Performed by Pass / Fail Date

FAT-007 — Verify slope of skid-mounted pipework.

Test ID FAT-007
Traces to URS-039
Objective Verify slope of skid-mounted pipework.

Method

1. Level the skid to its installed datum.

2. Measure fall on each horizontal run using a calibrated level.

3. Record fall as a ratio.

Acceptance criterion

Continuous fall of not less than 1 in 100 towards designated drain points, on all skid pipework.

Test instrument Digital level, accuracy 0.1 degrees or better Result
Performed by Pass / Fail Date

FAT-008 — Verify drainability of the skid.

Test ID FAT-008
Traces to URS-048
Objective Verify drainability of the skid.

Method

1. Fill the skid pipework with water.

2. Open all drain points.

3. After 15 minutes inspect all low points and branches for retained water.

Acceptance criterion

No retained water in any accessible section of skid pipework after draining.

Test instrument Result
Performed by Pass / Fail Date

FAT-009 — Hydrostatic pressure test of the assembled skid.

Test ID FAT-009
Traces to General construction and safety verification
Objective Hydrostatic pressure test of the assembled skid.

Method

1. Blank off the skid at its battery limits.

2. Fill with potable water and pressurise to 1.5 times design pressure.

3. Hold for 30 minutes and inspect all joints.

Acceptance criterion

No pressure drop and no visible leakage over the hold period.

Test instrument Calibrated pressure gauge, accuracy 1% of span or better Result
Performed by Pass / Fail Date

FAT-010 — Verify spray ball coverage of the storage vessel.

Test ID FAT-010
Traces to URS-011 | Closes DQ-OBS-006
Objective Verify spray ball coverage of the storage vessel.

Method

1. Coat the internal surface of the vessel, including the headspace, with riboflavin solution.

2. Operate the spray ball at design flow and pressure for the design duration.

3. Inspect all internal surfaces under ultraviolet light.

4. Photograph any area showing residual fluorescence.

Acceptance criterion

No residual fluorescence on any internal surface, including the headspace and all internal fittings.

Test instrument UV inspection lamp, riboflavin solution Result
Performed by Pass / Fail Date

FAT-011 — Verify vent filter installation and heater function.

Test ID FAT-011
Traces to URS-012 | Closes DQ-OBS-007
Objective Verify vent filter installation and heater function.

Method

1. Confirm filter rating and hydrophobic construction from the certificate.

2. Energise the heater and record surface temperature after 30 minutes.

3. Confirm the integrity test connection is present and accessible.

Acceptance criterion

Filter is 0.22 micrometre hydrophobic. Heater raises housing above dew point. Integrity test connection permits testing without breaking the sterile boundary.

Test instrument Surface temperature probe Result
Performed by Pass / Fail Date

FAT-012 — Verify overpressure and vacuum protection.

Test ID FAT-012
Traces to URS-053
Objective Verify overpressure and vacuum protection.

Method

1. Confirm rupture disc rating and burst detection installation.

2. Verify the pressure and vacuum relief device rating against the design.

3. Function test the rupture disc burst detection signal.

Acceptance criterion

Rupture disc rated to design, burst detection signal reaches the control system and raises an alarm.

Test instrument Result
Performed by Pass / Fail Date

FAT-013 — Verify the heat exchanger construction and interspace leak detection.

Test ID FAT-013
Traces to URS-010
Objective Verify the heat exchanger construction and interspace leak detection.

Method

1. Confirm double tube sheet construction from the certificate and by visual inspection.

2. Confirm the interspace is drainable.

3. Introduce water into the interspace and confirm detection and alarm.

Acceptance criterion

Double tube sheet with drainable, monitored interspace. Leak detection raises an alarm at the control system.

Test instrument Result
Performed by Pass / Fail Date

FAT-014 — Verify distribution pump performance and automatic changeover.

Test ID FAT-014
Traces to URS-009 | Closes DQ-OBS-004
Objective Verify distribution pump performance and automatic changeover.

Method

1. Run the duty pump on potable water and record flow and head at three points on the curve.

2. Simulate duty pump failure.

3. Record time to standby pump start and flow restoration.

Acceptance criterion

Pump performance within the supplier curve tolerance. Standby starts automatically on duty failure and restores flow.

Test instrument Calibrated flow meter and pressure gauges Result
Performed by Pass / Fail Date

FAT-015 — Verify automatic duty rotation between distribution pumps.

Test ID FAT-015
Traces to URS-009 | Closes DQ-OBS-004
Objective Verify automatic duty rotation between distribution pumps.

Method

1. Review the control system configuration for a duty rotation function.

2. If present, force the rotation interval and observe changeover.

Acceptance criterion

The control system rotates duty between pumps automatically at a configurable interval, so that neither leg remains stagnant.

Test instrument Result
Performed by Pass / Fail Date

FAT-016 — Verify instrument loop checks and recording interval.

Test ID FAT-016
Traces to URS-017
Objective Verify instrument loop checks and recording interval.

Method

1. For each instrument, apply a simulated input at 0, 50 and 100 percent of span.

2. Confirm the value displayed at the HMI and the value recorded.

3. Confirm the recording interval.

Acceptance criterion

Every loop reads correctly at all three points within instrument accuracy. Recording interval does not exceed one minute.

Test instrument Calibrated signal simulator Result
Performed by Pass / Fail Date

FAT-017 — Verify tank level control and alarms.

Test ID FAT-017
Traces to URS-015
Objective Verify tank level control and alarms.

Method

1. Simulate level at each alarm setpoint in turn.

2. Confirm alarm annunciation and recording.

3. Confirm pump protection operates at low-low level.

Acceptance criterion

High, high-high, low and low-low alarms annunciate and are recorded. Pumps stop at low-low level.

Test instrument Signal simulator Result
Performed by Pass / Fail Date

FAT-018 — Verify alarm recording content.

Test ID FAT-018
Traces to URS-019
Objective Verify alarm recording content.

Method

1. Raise three alarms of different types.

2. Acknowledge each under a named user account.

3. Clear each and review the alarm record.

Acceptance criterion

Each alarm record contains the condition, onset time, acknowledgement time, acknowledging operator and clearance time.

Test instrument Result
Performed by Pass / Fail Date

FAT-019 — Verify emergency stop function.

Test ID FAT-019
Traces to URS-054
Objective Verify emergency stop function.

Method

1. Operate the emergency stop at the skid.

2. Confirm the system enters the defined safe state.

3. Repeat at the remote pump station.

Acceptance criterion

Both emergency stops place the system in the defined safe state without creating a hazard from stored thermal energy.

Test instrument Result
Performed by Pass / Fail Date

FAT-020 — Verify interlocks.

Test ID FAT-020
Traces to URS-055 | Closes DQ-OBS-038
Objective Verify interlocks.

Method

1. Attempt pump start against a closed system.

2. Attempt to initiate sanitisation with a point of use simulated open.

Acceptance criterion

Pump start is prevented against a closed system. Sanitisation cannot be initiated while a point of use is open to an operator-accessible outlet.

Test instrument Result
Performed by Pass / Fail Date

FAT-021 — Verify access control and user accounts.

Test ID FAT-021
Traces to URS-025
Objective Verify access control and user accounts.

Method

1. Attempt login with a generic account.

2. Create a named account and log in.

3. Attempt an action outside the assigned role.

Acceptance criterion

Only named individual accounts permitted. Role permissions enforced. Generic accounts cannot be created.

Test instrument Result
Performed by Pass / Fail Date

FAT-022 — Verify configured user roles.

Test ID FAT-022
Traces to URS-026
Objective Verify configured user roles.

Method

1. Log in as each of the four roles in turn.

2. Confirm the permissions available match the functional specification.

Acceptance criterion

Operator, Supervisor, Engineer and Administrator roles present with permissions as specified.

Test instrument Result
Performed by Pass / Fail Date

FAT-023 — Verify restriction of critical setpoint changes.

Test ID FAT-023
Traces to URS-027 | Closes DQ-OBS-025
Objective Verify restriction of critical setpoint changes.

Method

1. Attempt to change sanitisation setpoints, alarm limits and calibration parameters at each role level.

2. Record which roles can change which parameters.

Acceptance criterion

Critical setpoints modifiable only by authorised roles, and every change recorded.

Test instrument Result
Performed by Pass / Fail Date

FAT-024 — Verify session timeout.

Test ID FAT-024
Traces to URS-028
Objective Verify session timeout.

Method

1. Log in and leave the session idle for the configured period.

2. Confirm the session locks and requires re-authentication.

Acceptance criterion

Session times out after the configured period and requires re-authentication to resume.

Test instrument Stopwatch Result
Performed by Pass / Fail Date

FAT-025 — Verify audit trail content.

Test ID FAT-025
Traces to URS-029
Objective Verify audit trail content.

Method

1. Make a setpoint change under a named account.

2. Review the audit trail entry.

Acceptance criterion

Audit trail records operator, date, time, previous value and new value.

Test instrument Result
Performed by Pass / Fail Date

FAT-026 — Verify that the audit trail cannot be disabled.

Test ID FAT-026
Traces to URS-030 | Closes DQ-OBS-027
Objective Verify that the audit trail cannot be disabled.

Method

1. Log in as Administrator.

2. Attempt to disable the audit trail.

3. Attempt to edit or delete an audit trail entry.

Acceptance criterion

The audit trail cannot be disabled, edited or deleted by any user, including Administrator.

Test instrument Result
Performed by Pass / Fail Date

FAT-027 — Verify audit trail review and export.

Test ID FAT-027
Traces to URS-031
Objective Verify audit trail review and export.

Method

1. Filter the audit trail by date range and by user.

2. Attempt to export the filtered record.

Acceptance criterion

Audit trail is reviewable in the application with filtering, and exportable as a report over a selected period.

Test instrument Result
Performed by Pass / Fail Date

FAT-028 — Verify that recorded values cannot be deleted or overwritten.

Test ID FAT-028
Traces to URS-024
Objective Verify that recorded values cannot be deleted or overwritten.

Method

1. Attempt to delete a recorded value at each role level.

2. Make a correction and confirm the original is preserved.

Acceptance criterion

No function permits deletion or overwriting. Corrections create a new entry preserving the original.

Test instrument Result
Performed by Pass / Fail Date

FAT-029 — Verify backup and restoration.

Test ID FAT-029
Traces to URS-023
Objective Verify backup and restoration.

Method

1. Trigger a backup.

2. Restore the backup to a test instance.

3. Confirm records and audit trail are intact after restoration.

Acceptance criterion

Backup completes and restoration reproduces all GMP records and the associated audit trail.

Test instrument Result
Performed by Pass / Fail Date

FAT-030 — Verify the sanitisation cycle sequence and completion logic.

Test ID FAT-030
Traces to URS-049 | Closes DQ-OBS-036
Objective Verify the sanitisation cycle sequence and completion logic.

Method

1. Initiate a sanitisation cycle in simulation mode.

2. Observe the sequence of steps.

3. Force a simulated temperature failure at one monitored location and observe the cycle outcome.

Acceptance criterion

The cycle runs automatically and cannot be declared successful where any monitored location failed to achieve the required temperature and hold.

Test instrument Result
Performed by Pass / Fail Date

FAT-031 — Verify sample valve type and installation.

Test ID FAT-031
Traces to URS-050
Objective Verify sample valve type and installation.

Method

1. Identify every sample valve against the P&ID.

2. Confirm sanitary design and self-draining installation.

Acceptance criterion

Sanitary, self-draining sample valves at every location shown on the P&ID.

Test instrument Result
Performed by Pass / Fail Date

FAT-032 — Verify instrument accessibility for calibration.

Test ID FAT-032
Traces to URS-051 | Closes DQ-OBS-041
Objective Verify instrument accessibility for calibration.

Method

1. For each instrument requiring calibration, confirm access without dismantling major assemblies.

2. Confirm removability without breaching the loop where the system is in operation.

Acceptance criterion

All instruments accessible without dismantling. Removable without breaching the loop in operation.

Test instrument Result
Performed by Pass / Fail Date

FAT-033 — Measure noise emission.

Test ID FAT-033
Traces to URS-057
Objective Measure noise emission.

Method

1. Operate the skid at full duty.

2. Measure sound pressure level at one metre from the skid at four positions.

Acceptance criterion

Noise does not exceed 80 dB(A) at one metre.

Test instrument Calibrated sound level meter, class 2 or better Result
Performed by Pass / Fail Date

FAT-034 — Verify insulation and hot surface protection.

Test ID FAT-034
Traces to URS-038
Objective Verify insulation and hot surface protection.

Method

1. Confirm insulation is fitted to all specified surfaces.

2. Where the skid is operated hot at the works, measure touchable surface temperature.

Acceptance criterion

No accessible surface exceeds 60 degrees C.

Test instrument Surface temperature probe Result
Performed by Pass / Fail Date

FAT-035 — Verify spare parts list and maintenance schedule.

Test ID FAT-035
Traces to URS-052
Objective Verify spare parts list and maintenance schedule.

Method

1. Review the preventive maintenance schedule for task, frequency and duration.

2. Review the spare parts list for part numbers and availability statement.

Acceptance criterion

Maintenance schedule states task, frequency and duration. Spare parts list complete with part numbers and a ten-year availability statement.

Test instrument Result
Performed by Pass / Fail Date

FAT-036 — Verify equipment tagging and nameplates.

Test ID FAT-036
Traces to General construction and safety verification
Objective Verify equipment tagging and nameplates.

Method

1. Compare every tag on the skid against the P&ID and instrument index.

2. Confirm nameplate data on major items.

Acceptance criterion

All tags match the P&ID and instrument index. Nameplates present and legible on all major items.

Test instrument Result
Performed by Pass / Fail Date

FAT-037 — Verify control panel construction and software version.

Test ID FAT-037
Traces to General construction and safety verification
Objective Verify control panel construction and software version.

Method

1. Inspect the panel against the electrical schematics.

2. Record the PLC and HMI software versions and checksums.

Acceptance criterion

Panel built to schematic. Software versions and checksums recorded for configuration management.

Test instrument Result
Performed by Pass / Fail Date

FAT-038 — Verify sanitisation record content.

Test ID FAT-038
Traces to URS-018 | Closes DQ-OBS-014
Objective Verify sanitisation record content.

Method

1. Run a simulated sanitisation cycle under a named account.

2. Review the cycle record.

Acceptance criterion

The record contains the temperature profile at each monitored location, the hold achieved, the initiating operator and the outcome.

Test instrument Result
Performed by Pass / Fail Date

FAT-039 — Verify sanitisation start confirmation and point-of-use lockout indication.

Test ID FAT-039
Traces to URS-056 | Closes DQ-OBS-039
Objective Verify sanitisation start confirmation and point-of-use lockout indication.

Method

1. Initiate a sanitisation cycle.

2. Observe whether a positive confirmation step is required.

3. Observe point-of-use indication during the cycle.

Acceptance criterion

A positive confirmation step is required before start, and every point of use is visibly indicated as locked out for the duration.

Test instrument Result
Performed by Pass / Fail Date

FAT-040 — Verify elastomer specification and compliance.

Test ID FAT-040
Traces to URS-045 | Closes DQ-OBS-030
Objective Verify elastomer specification and compliance.

Method

1. Review the elastomer schedule and certificates.

2. Confirm compliance statements and stated service life.

Acceptance criterion

Elastomers comply with USP Class VI and 21 CFR 177.2600, suitable for continuous service at loop temperature, with stated service life.

Test instrument Result
Performed by Pass / Fail Date

9. Worst-Case Condition Challenges

The specification identifies conditions under which the system is least able to meet its requirements. Four can be created at a works environment. The remainder require the installed system and are deferred with a stated reason; a deferral is a record, not an omission.

Ref Condition At FAT Basis Outcome / deferral
WC-05 Tank at minimum operating level Challenged FAT-010 verified spray ball coverage. Coverage was tested at the design flow and pressure with the vessel empty, which is the condition that exposes the full headspace. Two shadowed areas found. See DEV-004.
WC-06 Maximum tank discharge rate Challenged Vent filter sizing and heater duty reviewed against the stated maximum discharge rate at FAT-011. Filter and heater adequate. Integrity test access is the finding, not the sizing.
WC-07 Longest branch and standby pump leg Challenged FAT-006 measured every branch. FAT-015 tested for duty rotation. Both elements failed. Nine branches exceed 3D and no duty rotation exists. DEV-001 and DEV-006.
WC-09 Highest point and longest horizontal run Partially challenged FAT-007 measured slope on skid pipework only. Site-installed pipework slope is verified at IQ. Two skid runs already fail at 1:150.
WC-01 Maximum simultaneous demand Not challengeable at works The loop is not installed and the points of use do not exist at the supplier works. Loop hydraulics cannot be created. Deferred to OQ. The supplier hydraulic calculation at this condition remains outstanding at DQ-OBS-045.
WC-02 Coldest point during normal circulation Not challengeable at works Requires the installed loop at operating temperature with site heating medium. Deferred to OQ. The coldest point is not yet identified in the design.
WC-03 Least favourable point during sanitisation Not challengeable at works Requires the installed loop, site utilities and mapping ports which are not in the design. Deferred to OQ. Mapping ports outstanding at DQ-OBS-044.
WC-04 Point-of-use cooler branch Not challengeable No cooler arrangement exists in the design. Design resolution required before any stage can challenge this condition.
WC-08 Most hydraulically remote point of use Not challengeable at works Requires the installed loop. Deferred to OQ.
WC-10 Extended low-demand period Not challengeable at works Requires extended operation in service. Deferred to PQ.
WC-11 Worst-case feed water quality Not challengeable at works Requires the generation system and seasonal variation in service. Deferred to PQ Phase 3.

10. Design Qualification Observation Closure

The following observations from DQ-WFI-001 are addressed by this protocol. Closure is recorded in the FAT report and the Design Qualification observation register is updated; no parallel register is created.

Observation Test Subject Closed / Not closed
DQ-OBS-032 FAT-006 Verify dead leg dimensions against the specification.
DQ-OBS-006 FAT-010 Verify spray ball coverage of the storage vessel.
DQ-OBS-007 FAT-011 Verify vent filter installation and heater function.
DQ-OBS-004 FAT-014 Verify distribution pump performance and automatic changeover.
DQ-OBS-004 FAT-015 Verify automatic duty rotation between distribution pumps.
DQ-OBS-038 FAT-020 Verify interlocks.
DQ-OBS-025 FAT-023 Verify restriction of critical setpoint changes.
DQ-OBS-027 FAT-026 Verify that the audit trail cannot be disabled.
DQ-OBS-036 FAT-030 Verify the sanitisation cycle sequence and completion logic.
DQ-OBS-041 FAT-032 Verify instrument accessibility for calibration.
DQ-OBS-014 FAT-038 Verify sanitisation record content.
DQ-OBS-039 FAT-039 Verify sanitisation start confirmation and point-of-use lockout indication.
DQ-OBS-030 FAT-040 Verify elastomer specification and compliance.

11. Requirements Not Testable at Factory Acceptance

A supplier works cannot produce Water for Injection, cannot supply site utilities, and is not connected to the site network. The following requirements therefore cannot be verified here. Each is deferred to a named later stage and carried in the traceability matrix.

This section exists because a weakened test is worse than a deferred one. A water quality test performed on potable water, or a sanitisation test performed on plant steam, would produce a passing result that demonstrates nothing.

URS ID Why it cannot be verified at the supplier works Verified instead at
URS-001 WFI cannot be produced or supplied at the supplier works. Testing on potable water would not demonstrate the requirement. PQ
URS-002 Peak demand is [TO BE CONFIRMED] in the URS, and true demand can only be created by the installed points of use. OQ
URS-003 Requires extended operation in service. PQ
URS-004 Tank capacity requirement is [TO BE CONFIRMED] in the URS. IQ
URS-005 Point-of-use count is [TO BE CONFIRMED] in the URS. Points of use are installed at site. IQ
URS-006 Requires operation in service following a planned shutdown. PQ
URS-007 Loop temperature at the least favourable point requires the installed loop and site heating medium. OQ
URS-008 Return velocity at operating conditions requires the installed loop with all points of use connected. OQ
URS-013 No point-of-use cooler arrangement exists in the design. Nothing to test. See DQ-OBS-011. Design resolution required
URS-014 Sanitisation temperature and hold time are [TO BE CONFIRMED] in the URS, and the cycle requires site utilities at temperature. OQ
URS-016 Minimum dynamic pressure requirement is [TO BE CONFIRMED] in the URS. Pressure at the remote point requires the installed loop. OQ
URS-020 Retention period is [TO BE CONFIRMED] in the URS. OQ
URS-021 Enduring and available over the retention period cannot be demonstrated at a works test. OQ
URS-022 Time synchronisation requires connection to the site time server. SAT
URS-032 Interface to the WFI generation system requires the installed system. SAT
URS-033 Interface to the site building management system requires the site network. SAT
URS-034 Point-of-use interfaces require the installed points of use and connected equipment. SAT
URS-035 Export to the laboratory information management system requires the site system. Not currently in the design. See DQ-OBS-033. SAT
URS-036 Site utility envelope is [TO BE CONFIRMED] in the URS and the connections are made at site. IQ
URS-037 Drain connections and air breaks are made at site. IQ
URS-039 Slope of site-installed pipework. Skid pipework is tested at FAT-007. IQ
URS-040 Routing through classified areas is a site installation matter. IQ
URS-043 Passivation is performed after installation at site. IQ
URS-063 Water quality against the monograph requires WFI in service. PQ
URS-064 Conductivity, TOC, endotoxin and microbial limits require WFI in service and laboratory testing. PQ
URS-069 The three-phase PQ programme runs in service over one year. PQ
URS-070 Sample point installation is verified at site. Sample point type is verified at FAT-031. IQ
URS-071 Temperature mapping ports at worst-case locations are a site installation matter. Ports are not shown in the design. See DQ-OBS-044. IQ
URS-072 Hydraulic calculation at the worst-case demand condition is a design deliverable, not a works test. Outstanding at DQ-OBS-045. DQ closure
URS-073 Traceability across the qualification programme cannot be closed at FAT. VSR
URS-074 Ability to challenge worst-case conditions is confirmed once installed. OQ
URS-059 FAT and SAT protocol provision is verified by this protocol existing; SAT protocol review is confirmed before SAT. SAT
URS-060 IQ and OQ protocol and turnover package completeness is verified at delivery. IQ
URS-062 Training delivery occurs at site. SAT
URS-065 Qualification approach compliance is assessed across the programme. VSR
URS-066 Part 11 applicability is unresolved at DQ-OBS-047 and requires site scope confirmation. SAT

Total requirements deferred: 36. Requirements tested at FAT: 37.

12. Deviation Handling

Each failure is recorded at the point of occurrence with the test identifier, a factual description of what was observed, and the classification. Classification is agreed between the user witness and Quality Assurance at the time, not retrospectively.

The deviation log at Appendix B is completed during execution and reproduced in the FAT report. A deviation is closed only by a retest against the original acceptance criterion, or by a documented concession approved by Quality Assurance.

13. Punch List

Items requiring action before shipment or before Site Acceptance Testing are recorded here during execution.

Item Description Raised by Owner Due

14. Approval and Sign-off

Approval below authorises execution of this protocol. It does not constitute acceptance of the equipment.

Role Name Department Signature Date
Author Engineering
Reviewer CQV / Validation
Reviewer Operations
Reviewer Automation / IT
Reviewer EHS
Quality approval Quality Assurance

15. Revision History

Revision Date Description of change Author
0.1 [DD-MMM-YYYY] First draft.

Appendix A — Traceability

Every requirement of URS-WFI-001 against its FAT disposition. A requirement not tested here shows the stage at which it is verified instead.

URS ID Requirement summary FAT test Disposition Result
URS-001 The system shall store and distribute Water for Injection meeting the requirements of the curre… Deferred to PQ
URS-002 The system shall deliver a peak instantaneous demand of [TO BE CONFIRMED] L/min and an average … Deferred to OQ
URS-003 The system shall operate continuously, 24 hours per day, 7 days per week, with planned shutdown… Deferred to PQ
URS-004 The storage tank shall have a nominal capacity of [TO BE CONFIRMED] L, sized to buffer peak dem… Deferred to IQ
URS-005 The distribution loop shall serve [TO BE CONFIRMED] points of use, listed with their location, … Deferred to IQ
URS-006 The system shall recover to full specification within [TO BE CONFIRMED] hours following a plann… Deferred to PQ
URS-007 WFI shall be stored and distributed under continuous hot circulation at a temperature not less … Deferred to OQ
URS-008 The distribution loop shall maintain a return flow velocity of not less than 1.0 m/s, or a demo… Deferred to OQ
URS-009 The system shall be fitted with duty and standby distribution pumps with automatic changeover o… FAT-014 Tested at FAT
URS-010 Loop temperature shall be maintained by a heat exchanger of double tube sheet construction with… FAT-013 Tested at FAT
URS-011 The storage tank shall be fitted with a spray ball providing demonstrated full wetted coverage … FAT-010 Tested at FAT
URS-012 The storage tank shall be fitted with a hydrophobic vent filter of 0.22 micrometre rating, elec… FAT-011 Tested at FAT
URS-013 Points of use requiring water below loop temperature shall be served by dedicated point-of-use … Deferred to Design resolution required
URS-014 The system shall provide a thermal sanitisation cycle capable of raising every point in the loo… Deferred to OQ
URS-015 Tank level shall be controlled automatically, with high, high-high, low and low-low alarms, and… FAT-017 Tested at FAT
URS-016 The system shall deliver a minimum dynamic pressure of [TO BE CONFIRMED] bar g at the most hydr… Deferred to OQ
URS-017 The control system shall continuously record loop supply temperature, loop return temperature, … FAT-016 Tested at FAT
URS-018 The system shall record every sanitisation cycle, capturing the temperature profile at each mon… FAT-038 Tested at FAT
URS-019 All alarms shall be recorded with the alarm condition, time of onset, time of acknowledgement, … FAT-018 Tested at FAT
URS-020 Records shall be retained for not less than [TO BE CONFIRMED] years and shall be exportable in … Deferred to OQ
URS-021 Records shall be attributable, legible, contemporaneous, original and accurate, and shall remai… Deferred to OQ
URS-022 The system clock shall synchronise with the site time server. Users shall not be able to alter … Deferred to SAT
URS-023 The system shall support automated backup of all GMP records, and restoration of those records … FAT-029 Tested at FAT
URS-024 No function shall permit deletion or overwriting of a recorded value. Corrections shall be made… FAT-028 Tested at FAT
URS-025 The control system shall provide role-based access control with individual named user accounts.… FAT-021 Tested at FAT
URS-026 The system shall provide at least the roles Operator, Supervisor, Engineer and Administrator, w… FAT-022 Tested at FAT
URS-027 Critical setpoints, including sanitisation temperature and hold time, alarm limits and calibrat… FAT-023 Tested at FAT
URS-028 The system shall enforce automatic session timeout after a configurable period of inactivity, a… FAT-024 Tested at FAT
URS-029 The system shall maintain a secure, computer-generated, time-stamped audit trail recording the … FAT-025 Tested at FAT
URS-030 The audit trail shall not be editable or disableable by any user, including administrators, and… FAT-026 Tested at FAT
URS-031 The system shall support periodic audit trail review, with a filterable view and an exportable … FAT-027 Tested at FAT
URS-032 The system shall interface with the upstream WFI generation system, exchanging demand signal, g… Deferred to SAT
URS-033 The system shall provide monitored signals to the site building management system for alarm ann… Deferred to SAT
URS-034 The system shall provide the physical and electrical interface at each point of use defined in … Deferred to SAT
URS-035 Where sample results are managed in a laboratory information management system, the system shal… Deferred to SAT
URS-036 The system shall operate within the site utility envelope: electrical supply [TO BE CONFIRMED],… Deferred to IQ
URS-037 All drain connections shall discharge through an air break to prevent backflow, and shall be vi… Deferred to IQ
URS-038 All hot surfaces accessible to personnel shall be insulated or guarded such that touchable surf… FAT-034 Tested at FAT
URS-039 Pipework shall be installed with a continuous fall of not less than 1 in 100 towards designated… FAT-007 Tested at FAT
URS-040 Loop pipework routed through classified areas shall be finished and supported so as not to comp… Deferred to IQ
URS-041 All product contact surfaces shall be stainless steel 316L, with a mechanically polished and el… FAT-003 Tested at FAT
URS-042 All product contact welds shall be automatic orbital welds. A weld log shall be maintained, and… FAT-004 Tested at FAT
URS-043 The system shall be passivated after installation in accordance with a documented procedure, an… Deferred to IQ
URS-044 Material certificates in accordance with EN 10204 Type 3.1 shall be provided for all product co… FAT-002 Tested at FAT
URS-045 Elastomers and polymers in product contact shall comply with USP Class VI and 21 CFR 177.2600, … FAT-040 Tested at FAT
URS-046 All valves in product contact shall be sanitary diaphragm valves of zero static or zero dead le… FAT-005 Tested at FAT
URS-047 No dead leg in the distribution system shall exceed three internal pipe diameters (3D), measure… FAT-006 Tested at FAT
URS-048 The complete system, including the tank, loop, all branches and all points of use, shall be ful… FAT-008 Tested at FAT
URS-049 The sanitisation cycle shall be initiated from the operator interface, shall run automatically,… FAT-030 Tested at FAT
URS-050 Sample valves at each sampling location shall be of sanitary design, self-draining, and shall p… FAT-031 Tested at FAT
URS-051 All instruments requiring calibration shall be accessible without dismantling major assemblies … FAT-032 Tested at FAT
URS-052 The supplier shall provide a preventive maintenance schedule stating each task, its frequency a… FAT-035 Tested at FAT
URS-053 The storage tank shall be protected against overpressure and vacuum by a rupture disc and a pre… FAT-012 Tested at FAT
URS-054 An emergency stop shall be provided at the skid and at each remote pump location, placing the s… FAT-019 Tested at FAT
URS-055 Interlocks shall prevent operation of distribution pumps against a closed system and shall prev… FAT-020 Tested at FAT
URS-056 Sanitisation shall not be capable of being started without a positive confirmation step, and ev… FAT-039 Tested at FAT
URS-057 Noise emitted by the system shall not exceed 80 dB(A) measured at one metre under normal operat… FAT-033 Tested at FAT
URS-058 The supplier shall provide, prior to Factory Acceptance Testing: general arrangement drawings, … FAT-001 Tested at FAT
URS-059 The supplier shall provide FAT and SAT protocols for user review and approval not less than fou… Deferred to SAT
URS-060 The supplier shall provide IQ and OQ protocols and supporting documentation aligned with EU GMP… Deferred to IQ
URS-061 The supplier shall provide operation and maintenance manuals, a spare parts list with part numb… Not in FAT scope
URS-062 The supplier shall provide training for operators, maintenance personnel, and quality and valid… Deferred to SAT
URS-063 The system shall comply with the current USP and Ph. Eur. monographs for Water for Injection an… Deferred to PQ
URS-064 WFI delivered at every point of use shall meet: conductivity in accordance with USP General Cha… Deferred to PQ
URS-065 The system shall be designed, installed and qualified in accordance with EU GMP Annex 15 and th… Deferred to VSR
URS-066 The control system shall comply with EU GMP Annex 11 and, where applicable to the site, 21 CFR … Deferred to SAT
URS-067 The system shall be designed and documented in accordance with GAMP 5, and the supplier shall s… Not in FAT scope
URS-068 Equipment design shall follow ASME BPE for hygienic design, surface finish, fabrication and exa… Not in FAT scope
URS-069 The system shall support a three-phase Performance Qualification: Phase 1 with daily sampling o… Deferred to PQ
URS-070 Sample points shall be provided at the tank outlet, the loop supply, the loop return, each sub-… Deferred to IQ
URS-071 Temperature mapping ports shall be provided at each worst-case location listed in Appendix A, s… Deferred to IQ
URS-072 The supplier shall provide hydraulic calculations demonstrating that the minimum return velocit… Deferred to DQ closure
URS-073 Every requirement in this specification shall be traceable through design qualification, factor… Deferred to VSR
URS-074 The system shall permit challenge of the worst-case conditions listed in Appendix A during qual… Deferred to OQ

Appendix B — Deviation Log

Completed during execution.

Deviation Test Description Classification Status

Appendix C — Abbreviations

Term Definition
DQ Design Qualification
DEV Deviation
FAT Factory Acceptance Test
HMI Human Machine Interface
IQ Installation Qualification
OQ Operational Qualification
P&ID Piping and Instrumentation Diagram
PL Punch list item
PQ Performance Qualification
PLC Programmable Logic Controller
Ra Roughness average
SAT Site Acceptance Test
URS User Requirements Specification
VSR Validation Summary Report
WFI Water for Injection

FAT ReportFactory Acceptance Test Report

Download Word
Full document text — PRJ-2026-0009 · EQ-02

FACTORY ACCEPTANCE TEST REPORT

Water for Injection Storage and Distribution System

FAT-WFI-001-R · REVISION 0.1

Project reference PRJ-2026-0009
Equipment reference EQ-02 — WFI Storage and Distribution System
Document status Draft
Records execution of FAT-WFI-001 Rev 0.1
Supplier [Supplier name]
Works location [Works location]
Test dates [DD-MMM-YYYY] to [DD-MMM-YYYY]
Prepared by [Enter author]
This report records the results of the tests defined in FAT-WFI-001 as observed at the supplier works. Results were recorded by the persons named against each test and are reproduced here without alteration. This report has no validity until reviewed and approved in accordance with the site quality system. Pharma4i does not perform or record document approval.

Related Documents

Document Number Rev Status Relationship
User Requirements Specification URS-WFI-001 0.1 Issued Source of requirements
Design Qualification DQ-WFI-001 0.1 Issued Source of observations to close
FAT Protocol FAT-WFI-001 0.1 Draft This protocol
FAT Report FAT-WFI-001-R 0.1 Draft Records execution of this protocol
Site Acceptance Test protocol SAT-WFI-001 Planned Verifies requirements deferred from FAT
Installation Qualification IQ-WFI-001 Planned Planned
Operational Qualification OQ-WFI-001 Planned Planned
Performance Qualification PQ-WFI-001 Planned Planned
Validation Summary Report VSR-WFI-001 Planned Planned

Table of Contents

1. Introduction

This report records the execution of FAT-WFI-001 Revision 0.1 at the supplier works. It reproduces the acceptance criteria from the approved protocol without amendment, records the result observed against each, and lists every deviation raised.

No acceptance criterion was amended during execution. Where a criterion could not be applied because the specification does not fix a value, the test is recorded as not executed and the finding is against the specification.

2. Summary of Results

Outcome Count Note
Pass 21
Fail 17 Each raised as a deviation; see Section 4.
Partial 1 Element verified at works; remainder deferred.
Not executed 1 Acceptance criterion not defined in the specification.

Tests defined in the protocol: 40. Requirements deferred to later stages: 36.

2.1 Deviations by classification

Classification Count Effect on shipment
Critical 4 Prevents shipment until closed and retested.
Major 7 Prevents shipment unless a concession is approved by Quality Assurance.
Minor 3 May be carried to site with an agreed closure date.

2.2 Critical deviations

The following prevent shipment until closed and retested.

  • DEV-001 (FAT-006) — Nine of fourteen branches exceed the 3D dead leg limit required by URS-047, measured up to 5.8D. The skid was built to the 6D stated in DS-003.

  • DEV-007 (FAT-020) — Sanitisation can be initiated with a point of use open to an operator-accessible outlet. Scald hazard.

  • DEV-009 (FAT-026) — The Administrator account can disable audit trail recording from the maintenance menu, contrary to URS-030 and to records controls.

  • DEV-011 (FAT-030) — The sanitisation cycle reports Complete on elapsed time even where a monitored location failed to achieve temperature.

3. Test Results

Results as recorded at the works, against the acceptance criteria of the approved protocol.

FAT-001 — Verify the supplier documentation pack is complete and current before testing begins.

Test ID FAT-001
Traces to URS-058
Objective Verify the supplier documentation pack is complete and current before testing begins.

Method

1. Request the document register.

2. Confirm each document listed in the URS documentation requirement is present.

3. Record document number and revision for each.

Acceptance criterion

All documents required by URS-058 are present, at a stated revision, and match the document register.

Test instrument Result All 11 documents present at stated revisions. Register rev 3.
Performed by Pass / Fail Pass Date

FAT-002 — Verify material certificates for all product contact materials.

Test ID FAT-002
Traces to URS-044
Objective Verify material certificates for all product contact materials.

Method

1. Obtain the material certificate pack.

2. For each product contact item, trace the certificate to the installed component tag.

3. Confirm certificate type.

Acceptance criterion

EN 10204 Type 3.1 certificates present for every product contact item, traceable to component tags.

Test instrument Result All 3.1 certificates present and traceable. 34 items checked.
Performed by Pass / Fail Pass Date

FAT-003 — Verify product contact material and surface finish.

Test ID FAT-003
Traces to URS-041
Objective Verify product contact material and surface finish.

Method

1. Confirm material grade from certificates and component markings.

2. Measure internal surface finish at five accessible locations using a calibrated profilometer.

3. Record each reading.

Acceptance criterion

Material is 316L. Ra not greater than 0.4 micrometres at every measured location.

Test instrument Surface roughness tester, resolution 0.01 micrometres or better Result 316L confirmed. Ra readings 0.31, 0.34, 0.29, 0.36, 0.33 micrometres.
Performed by Pass / Fail Pass Date

FAT-004 — Verify orbital weld records and boroscopic inspection.

Test ID FAT-004
Traces to URS-042
Objective Verify orbital weld records and boroscopic inspection.

Method

1. Review the weld log against the isometric drawings.

2. Confirm each product contact weld is recorded.

3. Review boroscopy records against the required percentage.

Acceptance criterion

ACCEPTANCE CRITERION NOT DEFINED IN THE URS. The required boroscopy percentage is [TO BE CONFIRMED] in URS-042.

Test instrument Boroscope Result Weld log complete, 214 welds. Boroscopy performed on 10% (22 welds), all acceptable.
Performed by Pass / Fail Not executed Date

Comment: The URS does not fix the required percentage, so no pass or fail is possible. Recorded as an observation against the specification.

FAT-005 — Verify valve type and installation.

Test ID FAT-005
Traces to URS-046
Objective Verify valve type and installation.

Method

1. Identify every product contact valve against the P&ID.

2. Confirm sanitary diaphragm type and zero static design.

3. Confirm each branch is self-draining by visual inspection with the skid level.

Acceptance criterion

All product contact valves are sanitary diaphragm, zero static design, installed self-draining.

Test instrument Spirit level Result All 18 valves correct type. Two branches on the north face do not fall to drain.
Performed by Pass / Fail Fail Date

Comment: Two point-of-use branches do not self-drain. Raised as deviation DEV-002 and punch list item PL-003.

FAT-006 — Verify dead leg dimensions against the specification.

Test ID FAT-006
Traces to URS-047 | Closes DQ-OBS-032
Objective Verify dead leg dimensions against the specification.

Method

1. Measure each branch from the internal wall of the main loop to the point of closure.

2. Express as a multiple of internal pipe diameter.

3. Record every branch.

Acceptance criterion

No dead leg exceeds three internal pipe diameters (3D) as required by URS-047.

Test instrument Calibrated rule / calipers Result Measured 14 branches. Range 2.1D to 5.8D. Nine branches exceed 3D.
Performed by Pass / Fail Fail Date

Comment: Design was built to the 6D stated in DS-003, which conflicts with URS-047. This confirms DQ-OBS-032 at the works. Deviation DEV-001, critical.

FAT-007 — Verify slope of skid-mounted pipework.

Test ID FAT-007
Traces to URS-039
Objective Verify slope of skid-mounted pipework.

Method

1. Level the skid to its installed datum.

2. Measure fall on each horizontal run using a calibrated level.

3. Record fall as a ratio.

Acceptance criterion

Continuous fall of not less than 1 in 100 towards designated drain points, on all skid pipework.

Test instrument Digital level, accuracy 0.1 degrees or better Result Seven runs measured. Five at 1:90 or better. Two at 1:150.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ finding on ISO-011. Site pipework slope is verified at IQ. Deviation DEV-003.

FAT-008 — Verify drainability of the skid.

Test ID FAT-008
Traces to URS-048
Objective Verify drainability of the skid.

Method

1. Fill the skid pipework with water.

2. Open all drain points.

3. After 15 minutes inspect all low points and branches for retained water.

Acceptance criterion

No retained water in any accessible section of skid pipework after draining.

Test instrument Result Retained water found in the two branches identified at FAT-005.
Performed by Pass / Fail Fail Date

Comment: Same root cause as FAT-005. Covered by DEV-002.

FAT-009 — Hydrostatic pressure test of the assembled skid.

Test ID FAT-009
Traces to General construction and safety verification
Objective Hydrostatic pressure test of the assembled skid.

Method

1. Blank off the skid at its battery limits.

2. Fill with potable water and pressurise to 1.5 times design pressure.

3. Hold for 30 minutes and inspect all joints.

Acceptance criterion

No pressure drop and no visible leakage over the hold period.

Test instrument Calibrated pressure gauge, accuracy 1% of span or better Result Held 9.0 barg for 30 minutes. No drop, no leakage.
Performed by Pass / Fail Pass Date

FAT-010 — Verify spray ball coverage of the storage vessel.

Test ID FAT-010
Traces to URS-011 | Closes DQ-OBS-006
Objective Verify spray ball coverage of the storage vessel.

Method

1. Coat the internal surface of the vessel, including the headspace, with riboflavin solution.

2. Operate the spray ball at design flow and pressure for the design duration.

3. Inspect all internal surfaces under ultraviolet light.

4. Photograph any area showing residual fluorescence.

Acceptance criterion

No residual fluorescence on any internal surface, including the headspace and all internal fittings.

Test instrument UV inspection lamp, riboflavin solution Result Coverage complete on shell and dish ends. Residual fluorescence around the level probe boss and the vent nozzle.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-006. Two shadowed areas in the headspace. Deviation DEV-004.

FAT-011 — Verify vent filter installation and heater function.

Test ID FAT-011
Traces to URS-012 | Closes DQ-OBS-007
Objective Verify vent filter installation and heater function.

Method

1. Confirm filter rating and hydrophobic construction from the certificate.

2. Energise the heater and record surface temperature after 30 minutes.

3. Confirm the integrity test connection is present and accessible.

Acceptance criterion

Filter is 0.22 micrometre hydrophobic. Heater raises housing above dew point. Integrity test connection permits testing without breaking the sterile boundary.

Test instrument Surface temperature probe Result Filter correct. Heater reached 62 degrees C. Integrity test connection present but requires removal of the housing clamp.
Performed by Pass / Fail Fail Date

Comment: In-place integrity testing is not possible without breaking the sterile boundary, as identified in DQ-OBS-007. Deviation DEV-005.

FAT-012 — Verify overpressure and vacuum protection.

Test ID FAT-012
Traces to URS-053
Objective Verify overpressure and vacuum protection.

Method

1. Confirm rupture disc rating and burst detection installation.

2. Verify the pressure and vacuum relief device rating against the design.

3. Function test the rupture disc burst detection signal.

Acceptance criterion

Rupture disc rated to design, burst detection signal reaches the control system and raises an alarm.

Test instrument Result Disc rated 3.5 barg. Burst detection signal verified, alarm raised at the HMI.
Performed by Pass / Fail Pass Date

FAT-013 — Verify the heat exchanger construction and interspace leak detection.

Test ID FAT-013
Traces to URS-010
Objective Verify the heat exchanger construction and interspace leak detection.

Method

1. Confirm double tube sheet construction from the certificate and by visual inspection.

2. Confirm the interspace is drainable.

3. Introduce water into the interspace and confirm detection and alarm.

Acceptance criterion

Double tube sheet with drainable, monitored interspace. Leak detection raises an alarm at the control system.

Test instrument Result Construction confirmed. Interspace drains freely. Leak simulated, alarm raised within 4 seconds.
Performed by Pass / Fail Pass Date

FAT-014 — Verify distribution pump performance and automatic changeover.

Test ID FAT-014
Traces to URS-009 | Closes DQ-OBS-004
Objective Verify distribution pump performance and automatic changeover.

Method

1. Run the duty pump on potable water and record flow and head at three points on the curve.

2. Simulate duty pump failure.

3. Record time to standby pump start and flow restoration.

Acceptance criterion

Pump performance within the supplier curve tolerance. Standby starts automatically on duty failure and restores flow.

Test instrument Calibrated flow meter and pressure gauges Result Duty curve within tolerance at all three points. Changeover in 6 seconds, flow restored.
Performed by Pass / Fail Pass Date

Comment: Note: automatic duty rotation is not provided. See FAT-015.

FAT-015 — Verify automatic duty rotation between distribution pumps.

Test ID FAT-015
Traces to URS-009 | Closes DQ-OBS-004
Objective Verify automatic duty rotation between distribution pumps.

Method

1. Review the control system configuration for a duty rotation function.

2. If present, force the rotation interval and observe changeover.

Acceptance criterion

The control system rotates duty between pumps automatically at a configurable interval, so that neither leg remains stagnant.

Test instrument Result No duty rotation function exists in the control software.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-004. The standby pump leg remains stagnant between manual changeovers. Deviation DEV-006.

FAT-016 — Verify instrument loop checks and recording interval.

Test ID FAT-016
Traces to URS-017
Objective Verify instrument loop checks and recording interval.

Method

1. For each instrument, apply a simulated input at 0, 50 and 100 percent of span.

2. Confirm the value displayed at the HMI and the value recorded.

3. Confirm the recording interval.

Acceptance criterion

Every loop reads correctly at all three points within instrument accuracy. Recording interval does not exceed one minute.

Test instrument Calibrated signal simulator Result All 14 loops verified at three points. Recording interval 30 seconds.
Performed by Pass / Fail Pass Date

FAT-017 — Verify tank level control and alarms.

Test ID FAT-017
Traces to URS-015
Objective Verify tank level control and alarms.

Method

1. Simulate level at each alarm setpoint in turn.

2. Confirm alarm annunciation and recording.

3. Confirm pump protection operates at low-low level.

Acceptance criterion

High, high-high, low and low-low alarms annunciate and are recorded. Pumps stop at low-low level.

Test instrument Signal simulator Result All four alarms verified and recorded. Pumps stopped at low-low.
Performed by Pass / Fail Pass Date

FAT-018 — Verify alarm recording content.

Test ID FAT-018
Traces to URS-019
Objective Verify alarm recording content.

Method

1. Raise three alarms of different types.

2. Acknowledge each under a named user account.

3. Clear each and review the alarm record.

Acceptance criterion

Each alarm record contains the condition, onset time, acknowledgement time, acknowledging operator and clearance time.

Test instrument Result All five fields present for all three alarms.
Performed by Pass / Fail Pass Date

FAT-019 — Verify emergency stop function.

Test ID FAT-019
Traces to URS-054
Objective Verify emergency stop function.

Method

1. Operate the emergency stop at the skid.

2. Confirm the system enters the defined safe state.

3. Repeat at the remote pump station.

Acceptance criterion

Both emergency stops place the system in the defined safe state without creating a hazard from stored thermal energy.

Test instrument Result Both stops verified. Safe state entered, no residual hazard.
Performed by Pass / Fail Pass Date

FAT-020 — Verify interlocks.

Test ID FAT-020
Traces to URS-055 | Closes DQ-OBS-038
Objective Verify interlocks.

Method

1. Attempt pump start against a closed system.

2. Attempt to initiate sanitisation with a point of use simulated open.

Acceptance criterion

Pump start is prevented against a closed system. Sanitisation cannot be initiated while a point of use is open to an operator-accessible outlet.

Test instrument Result Pump start correctly prevented. Sanitisation started with a point of use simulated open.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-038. This is a scald hazard. Deviation DEV-007, critical.

FAT-021 — Verify access control and user accounts.

Test ID FAT-021
Traces to URS-025
Objective Verify access control and user accounts.

Method

1. Attempt login with a generic account.

2. Create a named account and log in.

3. Attempt an action outside the assigned role.

Acceptance criterion

Only named individual accounts permitted. Role permissions enforced. Generic accounts cannot be created.

Test instrument Result Generic account creation blocked. Named accounts function. Role restrictions enforced.
Performed by Pass / Fail Pass Date

FAT-022 — Verify configured user roles.

Test ID FAT-022
Traces to URS-026
Objective Verify configured user roles.

Method

1. Log in as each of the four roles in turn.

2. Confirm the permissions available match the functional specification.

Acceptance criterion

Operator, Supervisor, Engineer and Administrator roles present with permissions as specified.

Test instrument Result All four roles verified against FS-001 section 9.2.
Performed by Pass / Fail Pass Date

FAT-023 — Verify restriction of critical setpoint changes.

Test ID FAT-023
Traces to URS-027 | Closes DQ-OBS-025
Objective Verify restriction of critical setpoint changes.

Method

1. Attempt to change sanitisation setpoints, alarm limits and calibration parameters at each role level.

2. Record which roles can change which parameters.

Acceptance criterion

Critical setpoints modifiable only by authorised roles, and every change recorded.

Test instrument Result Sanitisation setpoints and alarm limits restricted correctly. Calibration parameters modifiable at Supervisor level.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-025. Deviation DEV-008. Requires a decision on whether Supervisor is an authorised role.

FAT-024 — Verify session timeout.

Test ID FAT-024
Traces to URS-028
Objective Verify session timeout.

Method

1. Log in and leave the session idle for the configured period.

2. Confirm the session locks and requires re-authentication.

Acceptance criterion

Session times out after the configured period and requires re-authentication to resume.

Test instrument Stopwatch Result Timeout at 15 minutes as configured. Re-authentication required.
Performed by Pass / Fail Pass Date

FAT-025 — Verify audit trail content.

Test ID FAT-025
Traces to URS-029
Objective Verify audit trail content.

Method

1. Make a setpoint change under a named account.

2. Review the audit trail entry.

Acceptance criterion

Audit trail records operator, date, time, previous value and new value.

Test instrument Result All five fields recorded correctly.
Performed by Pass / Fail Pass Date

FAT-026 — Verify that the audit trail cannot be disabled.

Test ID FAT-026
Traces to URS-030 | Closes DQ-OBS-027
Objective Verify that the audit trail cannot be disabled.

Method

1. Log in as Administrator.

2. Attempt to disable the audit trail.

3. Attempt to edit or delete an audit trail entry.

Acceptance criterion

The audit trail cannot be disabled, edited or deleted by any user, including Administrator.

Test instrument Result The Administrator account was able to disable audit trail recording from the maintenance menu.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-027. This is a direct conflict with URS-030 and with records controls. Deviation DEV-009, critical. Must be resolved before shipment.

FAT-027 — Verify audit trail review and export.

Test ID FAT-027
Traces to URS-031
Objective Verify audit trail review and export.

Method

1. Filter the audit trail by date range and by user.

2. Attempt to export the filtered record.

Acceptance criterion

Audit trail is reviewable in the application with filtering, and exportable as a report over a selected period.

Test instrument Result Filtering by date and user works. No export function available.
Performed by Pass / Fail Fail Date

Comment: Deviation DEV-010. Required to support periodic review.

FAT-028 — Verify that recorded values cannot be deleted or overwritten.

Test ID FAT-028
Traces to URS-024
Objective Verify that recorded values cannot be deleted or overwritten.

Method

1. Attempt to delete a recorded value at each role level.

2. Make a correction and confirm the original is preserved.

Acceptance criterion

No function permits deletion or overwriting. Corrections create a new entry preserving the original.

Test instrument Result No delete function at any role. Correction created a new entry, original preserved.
Performed by Pass / Fail Pass Date

FAT-029 — Verify backup and restoration.

Test ID FAT-029
Traces to URS-023
Objective Verify backup and restoration.

Method

1. Trigger a backup.

2. Restore the backup to a test instance.

3. Confirm records and audit trail are intact after restoration.

Acceptance criterion

Backup completes and restoration reproduces all GMP records and the associated audit trail.

Test instrument Result Backup completed. Restoration performed to a test instance; records and audit trail intact.
Performed by Pass / Fail Pass Date

Comment: Site network backup destination is verified at SAT.

FAT-030 — Verify the sanitisation cycle sequence and completion logic.

Test ID FAT-030
Traces to URS-049 | Closes DQ-OBS-036
Objective Verify the sanitisation cycle sequence and completion logic.

Method

1. Initiate a sanitisation cycle in simulation mode.

2. Observe the sequence of steps.

3. Force a simulated temperature failure at one monitored location and observe the cycle outcome.

Acceptance criterion

The cycle runs automatically and cannot be declared successful where any monitored location failed to achieve the required temperature and hold.

Test instrument Result Cycle sequence correct. With a forced low temperature at one location, the cycle still reported Complete.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-036. The cycle completes on elapsed time and does not verify temperature at each location. Deviation DEV-011, critical. Note that the acceptance temperature and hold time are themselves undefined in URS-014.

FAT-031 — Verify sample valve type and installation.

Test ID FAT-031
Traces to URS-050
Objective Verify sample valve type and installation.

Method

1. Identify every sample valve against the P&ID.

2. Confirm sanitary design and self-draining installation.

Acceptance criterion

Sanitary, self-draining sample valves at every location shown on the P&ID.

Test instrument Result All 9 sample valves correct type and self-draining.
Performed by Pass / Fail Pass Date

FAT-032 — Verify instrument accessibility for calibration.

Test ID FAT-032
Traces to URS-051 | Closes DQ-OBS-041
Objective Verify instrument accessibility for calibration.

Method

1. For each instrument requiring calibration, confirm access without dismantling major assemblies.

2. Confirm removability without breaching the loop where the system is in operation.

Acceptance criterion

All instruments accessible without dismantling. Removable without breaching the loop in operation.

Test instrument Result All accessible. The loop return conductivity cell cannot be removed without breaking the loop.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-041. Deviation DEV-012.

FAT-033 — Measure noise emission.

Test ID FAT-033
Traces to URS-057
Objective Measure noise emission.

Method

1. Operate the skid at full duty.

2. Measure sound pressure level at one metre from the skid at four positions.

Acceptance criterion

Noise does not exceed 80 dB(A) at one metre.

Test instrument Calibrated sound level meter, class 2 or better Result Readings 71, 73, 72, 74 dB(A).
Performed by Pass / Fail Pass Date

FAT-034 — Verify insulation and hot surface protection.

Test ID FAT-034
Traces to URS-038
Objective Verify insulation and hot surface protection.

Method

1. Confirm insulation is fitted to all specified surfaces.

2. Where the skid is operated hot at the works, measure touchable surface temperature.

Acceptance criterion

No accessible surface exceeds 60 degrees C.

Test instrument Surface temperature probe Result Insulation fitted as specified. Skid not operated at temperature at the works; measurement deferred.
Performed by Pass / Fail Partial Date

Comment: Insulation fitment verified. Surface temperature at operating condition is verified at OQ.

FAT-035 — Verify spare parts list and maintenance schedule.

Test ID FAT-035
Traces to URS-052
Objective Verify spare parts list and maintenance schedule.

Method

1. Review the preventive maintenance schedule for task, frequency and duration.

2. Review the spare parts list for part numbers and availability statement.

Acceptance criterion

Maintenance schedule states task, frequency and duration. Spare parts list complete with part numbers and a ten-year availability statement.

Test instrument Result Schedule complete. Spare parts list complete with ten-year statement in the quotation.
Performed by Pass / Fail Pass Date

FAT-036 — Verify equipment tagging and nameplates.

Test ID FAT-036
Traces to General construction and safety verification
Objective Verify equipment tagging and nameplates.

Method

1. Compare every tag on the skid against the P&ID and instrument index.

2. Confirm nameplate data on major items.

Acceptance criterion

All tags match the P&ID and instrument index. Nameplates present and legible on all major items.

Test instrument Result All 47 tags verified. Two instrument tags transposed.
Performed by Pass / Fail Fail Date

Comment: Minor. Punch list PL-006.

FAT-037 — Verify control panel construction and software version.

Test ID FAT-037
Traces to General construction and safety verification
Objective Verify control panel construction and software version.

Method

1. Inspect the panel against the electrical schematics.

2. Record the PLC and HMI software versions and checksums.

Acceptance criterion

Panel built to schematic. Software versions and checksums recorded for configuration management.

Test instrument Result Panel matches schematic rev 4. Versions and checksums recorded in Appendix D.
Performed by Pass / Fail Pass Date

FAT-038 — Verify sanitisation record content.

Test ID FAT-038
Traces to URS-018 | Closes DQ-OBS-014
Objective Verify sanitisation record content.

Method

1. Run a simulated sanitisation cycle under a named account.

2. Review the cycle record.

Acceptance criterion

The record contains the temperature profile at each monitored location, the hold achieved, the initiating operator and the outcome.

Test instrument Result Temperature profile, hold and outcome recorded. Initiating operator not recorded.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-014. Deviation DEV-013.

FAT-039 — Verify sanitisation start confirmation and point-of-use lockout indication.

Test ID FAT-039
Traces to URS-056 | Closes DQ-OBS-039
Objective Verify sanitisation start confirmation and point-of-use lockout indication.

Method

1. Initiate a sanitisation cycle.

2. Observe whether a positive confirmation step is required.

3. Observe point-of-use indication during the cycle.

Acceptance criterion

A positive confirmation step is required before start, and every point of use is visibly indicated as locked out for the duration.

Test instrument Result No confirmation step. No point-of-use indication exists.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-039. Combined with DEV-007 as a single supplier query on sanitisation safety.

FAT-040 — Verify elastomer specification and compliance.

Test ID FAT-040
Traces to URS-045 | Closes DQ-OBS-030
Objective Verify elastomer specification and compliance.

Method

1. Review the elastomer schedule and certificates.

2. Confirm compliance statements and stated service life.

Acceptance criterion

Elastomers comply with USP Class VI and 21 CFR 177.2600, suitable for continuous service at loop temperature, with stated service life.

Test instrument Result EPDM, USP Class VI certificate present. No 21 CFR 177.2600 statement. No service life stated.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-030. Deviation DEV-014.

4. Deviation Register

Ref Class Test Description Disposition / status
DEV-001 Critical FAT-006 Nine of fourteen branches exceed the 3D dead leg limit required by URS-047, measured up to 5.8D. The skid was built to the 6D stated in DS-003.

Supplier to rework the nine branches to 3D, or the user to raise a formal specification change with a documented microbial risk assessment. Rework preferred.

Status: Open

DEV-002 Major FAT-005, FAT-008 Two point-of-use branches on the north face do not self-drain; retained water confirmed at FAT-008.

Supplier to modify the branch geometry to fall to drain. Retest at FAT before shipment.

Status: Open

DEV-003 Major FAT-007 Two horizontal runs on the skid have a fall of 1:150 against the 1:100 required by URS-039.

Supplier to re-support both runs to achieve 1:100. Retest before shipment.

Status: Open

DEV-004 Major FAT-010 Riboflavin coverage test showed residual fluorescence around the level probe boss and the vent nozzle.

Supplier to review spray ball position and pattern, modify, and repeat the coverage test.

Status: Open

DEV-005 Major FAT-011 Vent filter in-place integrity testing requires removal of the housing clamp, breaking the sterile boundary.

Supplier to provide an integrity test connection permitting testing in place, per URS-012.

Status: Open

DEV-006 Major FAT-015 No automatic duty rotation between distribution pumps. The standby leg remains stagnant between manual changeovers.

Supplier to add a configurable duty rotation function to the control software.

Status: Open

DEV-007 Critical FAT-020 Sanitisation can be initiated with a point of use open to an operator-accessible outlet. Scald hazard.

Supplier to add an interlock preventing sanitisation start with any point of use open. Retest before shipment.

Status: Open

DEV-008 Minor FAT-023 Calibration parameters are modifiable at Supervisor role level.

User to confirm whether Supervisor is an authorised role for calibration parameters. If not, supplier to restrict.

Status: Open

DEV-009 Critical FAT-026 The Administrator account can disable audit trail recording from the maintenance menu, contrary to URS-030 and to records controls.

Supplier to remove the disable function entirely. This is not a configuration change; the function must not exist. Retest before shipment.

Status: Open

DEV-010 Major FAT-027 No audit trail export function over a selected period.

Supplier to provide an exportable audit trail report to support periodic review.

Status: Open

DEV-011 Critical FAT-030 The sanitisation cycle reports Complete on elapsed time even where a monitored location failed to achieve temperature.

Supplier to modify the cycle completion logic to require every monitored location to achieve the acceptance temperature and hold. Note that the acceptance values are undefined in URS-014 and must be fixed by the user.

Status: Open

DEV-012 Minor FAT-032 The loop return conductivity cell cannot be removed without breaking the loop in operation.

Supplier to propose an isolation arrangement or the user to accept planned shutdown for this calibration.

Status: Open

DEV-013 Major FAT-038 The operator initiating a sanitisation cycle is not recorded.

Supplier to add the initiating operator to the cycle record.

Status: Open

DEV-014 Minor FAT-040 No 21 CFR 177.2600 compliance statement and no stated service life for the elastomers.

Supplier to provide the compliance statement and service life at loop temperature.

Status: Open

5. Punch List

Items requiring action before shipment or before Site Acceptance Testing.

Item Description Against Owner Due
PL-001 Rework nine branches to 3D dead leg limit DEV-001 Supplier Before shipment
PL-002 Modify vent filter housing for in-place integrity testing DEV-005 Supplier Before shipment
PL-003 Modify two north face branches to self-drain DEV-002 Supplier Before shipment
PL-004 Re-support two horizontal runs to 1:100 DEV-003 Supplier Before shipment
PL-005 Remove audit trail disable function; provide export function DEV-009, DEV-010 Supplier Before shipment
PL-006 Correct two transposed instrument tags FAT-036 Supplier Before shipment
PL-007 Add sanitisation start interlock and confirmation step DEV-007 Supplier Before shipment
PL-008 Modify sanitisation completion logic DEV-011 Supplier Before shipment
PL-009 Add duty rotation function DEV-006 Supplier Before shipment
PL-010 Repeat spray ball coverage test after modification DEV-004 Supplier Before shipment
PL-011 Provide elastomer compliance statement and service life DEV-014 Supplier Before shipment
PL-012 Add initiating operator to sanitisation record DEV-013 Supplier Before shipment
PL-013 Fix boroscopy percentage in the URS and confirm against 10% performed FAT-004 User Before SAT
PL-014 Confirm whether Supervisor is authorised for calibration parameters DEV-008 User Before SAT

6. Design Qualification Observation Closure

Status of the observations from DQ-WFI-001 addressed by this test.

Observation Test Outcome Status
DQ-OBS-032 FAT-006 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-006 FAT-010 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-007 FAT-011 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-004 FAT-014 Verified at the works; observation closed. Closed
DQ-OBS-004 FAT-015 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-038 FAT-020 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-025 FAT-023 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-027 FAT-026 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-036 FAT-030 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-041 FAT-032 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-014 FAT-038 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-039 FAT-039 Confirmed at the works; observation remains open pending rework. Not closed
DQ-OBS-030 FAT-040 Confirmed at the works; observation remains open pending rework. Not closed

7. Worst-Case Condition Outcomes

Ref Condition At FAT Basis Outcome / deferral
WC-05 Tank at minimum operating level Challenged FAT-010 verified spray ball coverage. Coverage was tested at the design flow and pressure with the vessel empty, which is the condition that exposes the full headspace. Two shadowed areas found. See DEV-004.
WC-06 Maximum tank discharge rate Challenged Vent filter sizing and heater duty reviewed against the stated maximum discharge rate at FAT-011. Filter and heater adequate. Integrity test access is the finding, not the sizing.
WC-07 Longest branch and standby pump leg Challenged FAT-006 measured every branch. FAT-015 tested for duty rotation. Both elements failed. Nine branches exceed 3D and no duty rotation exists. DEV-001 and DEV-006.
WC-09 Highest point and longest horizontal run Partially challenged FAT-007 measured slope on skid pipework only. Site-installed pipework slope is verified at IQ. Two skid runs already fail at 1:150.
WC-01 Maximum simultaneous demand Not challengeable at works The loop is not installed and the points of use do not exist at the supplier works. Loop hydraulics cannot be created. Deferred to OQ. The supplier hydraulic calculation at this condition remains outstanding at DQ-OBS-045.
WC-02 Coldest point during normal circulation Not challengeable at works Requires the installed loop at operating temperature with site heating medium. Deferred to OQ. The coldest point is not yet identified in the design.
WC-03 Least favourable point during sanitisation Not challengeable at works Requires the installed loop, site utilities and mapping ports which are not in the design. Deferred to OQ. Mapping ports outstanding at DQ-OBS-044.
WC-04 Point-of-use cooler branch Not challengeable No cooler arrangement exists in the design. Design resolution required before any stage can challenge this condition.
WC-08 Most hydraulically remote point of use Not challengeable at works Requires the installed loop. Deferred to OQ.
WC-10 Extended low-demand period Not challengeable at works Requires extended operation in service. Deferred to PQ.
WC-11 Worst-case feed water quality Not challengeable at works Requires the generation system and seasonal variation in service. Deferred to PQ Phase 3.

8. Requirements Remaining to be Verified

The following requirements were not verified at the works and remain to be verified at the stage stated. This list is carried into the Site Acceptance Test protocol and the project traceability matrix.

URS ID Why it cannot be verified at the supplier works Verified instead at
URS-001 WFI cannot be produced or supplied at the supplier works. Testing on potable water would not demonstrate the requirement. PQ
URS-002 Peak demand is [TO BE CONFIRMED] in the URS, and true demand can only be created by the installed points of use. OQ
URS-003 Requires extended operation in service. PQ
URS-004 Tank capacity requirement is [TO BE CONFIRMED] in the URS. IQ
URS-005 Point-of-use count is [TO BE CONFIRMED] in the URS. Points of use are installed at site. IQ
URS-006 Requires operation in service following a planned shutdown. PQ
URS-007 Loop temperature at the least favourable point requires the installed loop and site heating medium. OQ
URS-008 Return velocity at operating conditions requires the installed loop with all points of use connected. OQ
URS-013 No point-of-use cooler arrangement exists in the design. Nothing to test. See DQ-OBS-011. Design resolution required
URS-014 Sanitisation temperature and hold time are [TO BE CONFIRMED] in the URS, and the cycle requires site utilities at temperature. OQ
URS-016 Minimum dynamic pressure requirement is [TO BE CONFIRMED] in the URS. Pressure at the remote point requires the installed loop. OQ
URS-020 Retention period is [TO BE CONFIRMED] in the URS. OQ
URS-021 Enduring and available over the retention period cannot be demonstrated at a works test. OQ
URS-022 Time synchronisation requires connection to the site time server. SAT
URS-032 Interface to the WFI generation system requires the installed system. SAT
URS-033 Interface to the site building management system requires the site network. SAT
URS-034 Point-of-use interfaces require the installed points of use and connected equipment. SAT
URS-035 Export to the laboratory information management system requires the site system. Not currently in the design. See DQ-OBS-033. SAT
URS-036 Site utility envelope is [TO BE CONFIRMED] in the URS and the connections are made at site. IQ
URS-037 Drain connections and air breaks are made at site. IQ
URS-039 Slope of site-installed pipework. Skid pipework is tested at FAT-007. IQ
URS-040 Routing through classified areas is a site installation matter. IQ
URS-043 Passivation is performed after installation at site. IQ
URS-063 Water quality against the monograph requires WFI in service. PQ
URS-064 Conductivity, TOC, endotoxin and microbial limits require WFI in service and laboratory testing. PQ
URS-069 The three-phase PQ programme runs in service over one year. PQ
URS-070 Sample point installation is verified at site. Sample point type is verified at FAT-031. IQ
URS-071 Temperature mapping ports at worst-case locations are a site installation matter. Ports are not shown in the design. See DQ-OBS-044. IQ
URS-072 Hydraulic calculation at the worst-case demand condition is a design deliverable, not a works test. Outstanding at DQ-OBS-045. DQ closure
URS-073 Traceability across the qualification programme cannot be closed at FAT. VSR
URS-074 Ability to challenge worst-case conditions is confirmed once installed. OQ
URS-059 FAT and SAT protocol provision is verified by this protocol existing; SAT protocol review is confirmed before SAT. SAT
URS-060 IQ and OQ protocol and turnover package completeness is verified at delivery. IQ
URS-062 Training delivery occurs at site. SAT
URS-065 Qualification approach compliance is assessed across the programme. VSR
URS-066 Part 11 applicability is unresolved at DQ-OBS-047 and requires site scope confirmation. SAT

9. Conclusion

Of 40 tests defined in FAT-WFI-001 Revision 0.1: 21 passed, 17 failed, 1 were partially completed and 1 could not be executed because the acceptance criterion is not defined in URS-WFI-001.

14 deviations were raised: 4 critical, 7 major and 3 minor. All remain open at the time of this report. 14 punch list items are recorded, of which 12 are for supplier action before shipment.

Of the eleven worst-case conditions identified in URS-WFI-001, three were challenged at the works and one partially. The remaining seven require the installed system and are deferred.

The equipment is [ acceptable for shipment / acceptable for shipment subject to closure of the punch list / not acceptable for shipment ].

The bracketed judgement is drafted from the results recorded in this document. It is a judgement for the reviewer and must be confirmed, amended or replaced by qualified personnel before this report is issued. Pharma4i does not make this determination.

Note for the reviewer: four critical deviations are open, including a control system that permits the audit trail to be disabled and a sanitisation cycle that reports success without verifying temperature. On the results recorded here, a conclusion of acceptable for shipment would not be supportable until at least the critical deviations are closed and retested.

10. Attendance and Signatures

The persons below witnessed execution and confirm that the results recorded in this report are those observed at the works.

Role Name Department Signature Date
Author Engineering
Reviewer CQV / Validation
Reviewer Operations
Reviewer Automation / IT
Reviewer EHS
Quality approval Quality Assurance

11. Revision History

Revision Date Description of change Author
0.1 [DD-MMM-YYYY] First draft.

Appendix A — Traceability

URS ID Requirement summary FAT test Disposition Result
URS-001 The system shall store and distribute Water for Injection meeting the requirements of the curre… Deferred to PQ
URS-002 The system shall deliver a peak instantaneous demand of [TO BE CONFIRMED] L/min and an average … Deferred to OQ
URS-003 The system shall operate continuously, 24 hours per day, 7 days per week, with planned shutdown… Deferred to PQ
URS-004 The storage tank shall have a nominal capacity of [TO BE CONFIRMED] L, sized to buffer peak dem… Deferred to IQ
URS-005 The distribution loop shall serve [TO BE CONFIRMED] points of use, listed with their location, … Deferred to IQ
URS-006 The system shall recover to full specification within [TO BE CONFIRMED] hours following a plann… Deferred to PQ
URS-007 WFI shall be stored and distributed under continuous hot circulation at a temperature not less … Deferred to OQ
URS-008 The distribution loop shall maintain a return flow velocity of not less than 1.0 m/s, or a demo… Deferred to OQ
URS-009 The system shall be fitted with duty and standby distribution pumps with automatic changeover o… FAT-014 Tested at FAT Pass
URS-010 Loop temperature shall be maintained by a heat exchanger of double tube sheet construction with… FAT-013 Tested at FAT Pass
URS-011 The storage tank shall be fitted with a spray ball providing demonstrated full wetted coverage … FAT-010 Tested at FAT Fail
URS-012 The storage tank shall be fitted with a hydrophobic vent filter of 0.22 micrometre rating, elec… FAT-011 Tested at FAT Fail
URS-013 Points of use requiring water below loop temperature shall be served by dedicated point-of-use … Deferred to Design resolution required
URS-014 The system shall provide a thermal sanitisation cycle capable of raising every point in the loo… Deferred to OQ
URS-015 Tank level shall be controlled automatically, with high, high-high, low and low-low alarms, and… FAT-017 Tested at FAT Pass
URS-016 The system shall deliver a minimum dynamic pressure of [TO BE CONFIRMED] bar g at the most hydr… Deferred to OQ
URS-017 The control system shall continuously record loop supply temperature, loop return temperature, … FAT-016 Tested at FAT Pass
URS-018 The system shall record every sanitisation cycle, capturing the temperature profile at each mon… FAT-038 Tested at FAT Fail
URS-019 All alarms shall be recorded with the alarm condition, time of onset, time of acknowledgement, … FAT-018 Tested at FAT Pass
URS-020 Records shall be retained for not less than [TO BE CONFIRMED] years and shall be exportable in … Deferred to OQ
URS-021 Records shall be attributable, legible, contemporaneous, original and accurate, and shall remai… Deferred to OQ
URS-022 The system clock shall synchronise with the site time server. Users shall not be able to alter … Deferred to SAT
URS-023 The system shall support automated backup of all GMP records, and restoration of those records … FAT-029 Tested at FAT Pass
URS-024 No function shall permit deletion or overwriting of a recorded value. Corrections shall be made… FAT-028 Tested at FAT Pass
URS-025 The control system shall provide role-based access control with individual named user accounts.… FAT-021 Tested at FAT Pass
URS-026 The system shall provide at least the roles Operator, Supervisor, Engineer and Administrator, w… FAT-022 Tested at FAT Pass
URS-027 Critical setpoints, including sanitisation temperature and hold time, alarm limits and calibrat… FAT-023 Tested at FAT Fail
URS-028 The system shall enforce automatic session timeout after a configurable period of inactivity, a… FAT-024 Tested at FAT Pass
URS-029 The system shall maintain a secure, computer-generated, time-stamped audit trail recording the … FAT-025 Tested at FAT Pass
URS-030 The audit trail shall not be editable or disableable by any user, including administrators, and… FAT-026 Tested at FAT Fail
URS-031 The system shall support periodic audit trail review, with a filterable view and an exportable … FAT-027 Tested at FAT Fail
URS-032 The system shall interface with the upstream WFI generation system, exchanging demand signal, g… Deferred to SAT
URS-033 The system shall provide monitored signals to the site building management system for alarm ann… Deferred to SAT
URS-034 The system shall provide the physical and electrical interface at each point of use defined in … Deferred to SAT
URS-035 Where sample results are managed in a laboratory information management system, the system shal… Deferred to SAT
URS-036 The system shall operate within the site utility envelope: electrical supply [TO BE CONFIRMED],… Deferred to IQ
URS-037 All drain connections shall discharge through an air break to prevent backflow, and shall be vi… Deferred to IQ
URS-038 All hot surfaces accessible to personnel shall be insulated or guarded such that touchable surf… FAT-034 Tested at FAT Partial
URS-039 Pipework shall be installed with a continuous fall of not less than 1 in 100 towards designated… FAT-007 Tested at FAT Fail
URS-040 Loop pipework routed through classified areas shall be finished and supported so as not to comp… Deferred to IQ
URS-041 All product contact surfaces shall be stainless steel 316L, with a mechanically polished and el… FAT-003 Tested at FAT Pass
URS-042 All product contact welds shall be automatic orbital welds. A weld log shall be maintained, and… FAT-004 Tested at FAT Not executed
URS-043 The system shall be passivated after installation in accordance with a documented procedure, an… Deferred to IQ
URS-044 Material certificates in accordance with EN 10204 Type 3.1 shall be provided for all product co… FAT-002 Tested at FAT Pass
URS-045 Elastomers and polymers in product contact shall comply with USP Class VI and 21 CFR 177.2600, … FAT-040 Tested at FAT Fail
URS-046 All valves in product contact shall be sanitary diaphragm valves of zero static or zero dead le… FAT-005 Tested at FAT Fail
URS-047 No dead leg in the distribution system shall exceed three internal pipe diameters (3D), measure… FAT-006 Tested at FAT Fail
URS-048 The complete system, including the tank, loop, all branches and all points of use, shall be ful… FAT-008 Tested at FAT Fail
URS-049 The sanitisation cycle shall be initiated from the operator interface, shall run automatically,… FAT-030 Tested at FAT Fail
URS-050 Sample valves at each sampling location shall be of sanitary design, self-draining, and shall p… FAT-031 Tested at FAT Pass
URS-051 All instruments requiring calibration shall be accessible without dismantling major assemblies … FAT-032 Tested at FAT Fail
URS-052 The supplier shall provide a preventive maintenance schedule stating each task, its frequency a… FAT-035 Tested at FAT Pass
URS-053 The storage tank shall be protected against overpressure and vacuum by a rupture disc and a pre… FAT-012 Tested at FAT Pass
URS-054 An emergency stop shall be provided at the skid and at each remote pump location, placing the s… FAT-019 Tested at FAT Pass
URS-055 Interlocks shall prevent operation of distribution pumps against a closed system and shall prev… FAT-020 Tested at FAT Fail
URS-056 Sanitisation shall not be capable of being started without a positive confirmation step, and ev… FAT-039 Tested at FAT Fail
URS-057 Noise emitted by the system shall not exceed 80 dB(A) measured at one metre under normal operat… FAT-033 Tested at FAT Pass
URS-058 The supplier shall provide, prior to Factory Acceptance Testing: general arrangement drawings, … FAT-001 Tested at FAT Pass
URS-059 The supplier shall provide FAT and SAT protocols for user review and approval not less than fou… Deferred to SAT
URS-060 The supplier shall provide IQ and OQ protocols and supporting documentation aligned with EU GMP… Deferred to IQ
URS-061 The supplier shall provide operation and maintenance manuals, a spare parts list with part numb… Not in FAT scope
URS-062 The supplier shall provide training for operators, maintenance personnel, and quality and valid… Deferred to SAT
URS-063 The system shall comply with the current USP and Ph. Eur. monographs for Water for Injection an… Deferred to PQ
URS-064 WFI delivered at every point of use shall meet: conductivity in accordance with USP General Cha… Deferred to PQ
URS-065 The system shall be designed, installed and qualified in accordance with EU GMP Annex 15 and th… Deferred to VSR
URS-066 The control system shall comply with EU GMP Annex 11 and, where applicable to the site, 21 CFR … Deferred to SAT
URS-067 The system shall be designed and documented in accordance with GAMP 5, and the supplier shall s… Not in FAT scope
URS-068 Equipment design shall follow ASME BPE for hygienic design, surface finish, fabrication and exa… Not in FAT scope
URS-069 The system shall support a three-phase Performance Qualification: Phase 1 with daily sampling o… Deferred to PQ
URS-070 Sample points shall be provided at the tank outlet, the loop supply, the loop return, each sub-… Deferred to IQ
URS-071 Temperature mapping ports shall be provided at each worst-case location listed in Appendix A, s… Deferred to IQ
URS-072 The supplier shall provide hydraulic calculations demonstrating that the minimum return velocit… Deferred to DQ closure
URS-073 Every requirement in this specification shall be traceable through design qualification, factor… Deferred to VSR
URS-074 The system shall permit challenge of the worst-case conditions listed in Appendix A during qual… Deferred to OQ

Appendix B — Test Instruments Used

Instrument Used in Required accuracy Cal. cert / due
Surface roughness tester FAT-003 Resolution 0.01 micrometres or better
Boroscope FAT-004 Suitable for the smallest pipe bore in scope
Digital level FAT-007 Accuracy 0.1 degrees or better
Pressure gauge FAT-009 Accuracy 1% of span or better, range to 1.5 x design
UV inspection lamp FAT-010 365 nm
Surface temperature probe FAT-011, FAT-034 Accuracy 1 degree C or better
Flow meter FAT-014 Accuracy 2% of reading or better
Signal simulator FAT-016, FAT-017 Accuracy 0.1% of span or better
Sound level meter FAT-033 Class 2 or better
Calibrated rule / calipers FAT-006 Resolution 1 mm or better
Stopwatch FAT-024 Resolution 1 second

Appendix C — Software Configuration Recorded

Item Version Checksum
PLC application [Recorded at FAT-037]
HMI application [Recorded at FAT-037]
PLC firmware [Recorded at FAT-037]

Appendix D — Abbreviations

Term Definition
DQ Design Qualification
DEV Deviation
FAT Factory Acceptance Test
HMI Human Machine Interface
IQ Installation Qualification
OQ Operational Qualification
P&ID Piping and Instrumentation Diagram
PL Punch list item
PQ Performance Qualification
PLC Programmable Logic Controller
Ra Roughness average
SAT Site Acceptance Test
URS User Requirements Specification
VSR Validation Summary Report
WFI Water for Injection

SAT ProtocolSite Acceptance Test Protocol

Download Word
Full document text — PRJ-2026-0009 · EQ-02

SITE ACCEPTANCE TEST PROTOCOL

Water for Injection Storage and Distribution System

SAT-WFI-001 · REVISION 0.1

Project reference PRJ-2026-0009
Equipment reference EQ-02 — WFI Storage and Distribution System
Document status Draft
Generated from URS-WFI-001, DQ-WFI-001, FAT-WFI-001 and FAT-WFI-001-R
Site [Site name and location]
Supplier [Supplier name]
Planned test dates [DD-MMM-YYYY] to [DD-MMM-YYYY]
Prepared by [Enter author]
This protocol was drafted with software assistance. It has no validity until reviewed and approved by qualified personnel in accordance with the site quality system, and must not be executed before approval. Acceptance criteria are taken from URS-WFI-001 and are not independently established by this document. Pharma4i does not perform or record document approval; responsibility for review, approval, signature and document control rests with the approving persons named in Section 17.

Related Documents

This protocol forms part of the qualification package for PRJ-2026-0009 EQ-02.

Document Number Rev Status Relationship
User Requirements Specification URS-WFI-001 0.1 Issued Source of requirements
Design Qualification DQ-WFI-001 0.1 Issued Source of open observations
FAT Protocol FAT-WFI-001 0.1 Issued Preceding test
FAT Report FAT-WFI-001-R 0.1 Issued Source of deferrals, deviations and punch list
SAT Protocol SAT-WFI-001 0.1 Draft This protocol
SAT Report SAT-WFI-001-R 0.1 Draft Records execution of this protocol
Installation Qualification IQ-WFI-001 Planned Receives requirements outstanding after SAT
Operational Qualification OQ-WFI-001 Planned Planned
Performance Qualification PQ-WFI-001 Planned Planned
Validation Summary Report VSR-WFI-001 Planned Planned

Table of Contents

1. Introduction and Purpose

This protocol defines the tests to be performed at site to verify that the Water for Injection storage and distribution system, as installed, conforms to the requirements of URS-WFI-001 that could not be verified at the supplier works, and to confirm closure of the deviations and punch list items raised during Factory Acceptance Testing.

Site Acceptance Testing establishes no new requirements. Every acceptance criterion is taken from the User Requirements Specification. Where the specification does not fix a value, no criterion is stated, no test is performed, and the finding is recorded against the specification.

Thirty-six requirements were deferred from Factory Acceptance because a supplier works cannot produce Water for Injection, supply site utilities, or connect to the site network. Section 11 records the disposition of every one of them. A requirement deferred at FAT and deferred again here is visible as such; it does not disappear.

2. Scope

2.1 In scope

  • Verification of installation: location, levelling, anchoring, supports, utility connections, routing and as-built accuracy.

  • Verification of site-installed pipework: slope, drainability, dead legs and passivation.

  • Requirements deferred from Factory Acceptance that the installed system now makes testable.

  • Interfaces to the WFI generation system, the building management system, the site time server and the points of use.

  • Closure of Factory Acceptance deviations and punch list items by retest against the original acceptance criteria.

  • Challenge of worst-case conditions that the installed system makes testable.

2.2 Out of scope

  • Water quality against the monograph, which requires the system in service and is verified at Performance Qualification.

  • Operational challenge at maximum simultaneous demand, verified at Operational Qualification.

  • The three-phase Performance Qualification programme.

  • The WFI generation system, equipment item EQ-01.

3. Reference Documents

Document Number Revision
User Requirements Specification URS-WFI-001 Rev 0.1
Design Qualification DQ-WFI-001 Rev 0.1
FAT Protocol FAT-WFI-001 Rev 0.1
FAT Report FAT-WFI-001-R Rev 0.1
Supplier Functional Specification FS-001 Rev 3
Supplier Design Specification DS-003 Rev 2
Piping and Instrumentation Diagram P&ID-005 Rev C
As-built isometric drawings ISO-011 Rev C
Site layout drawing SL-003 Rev B
Utility schedule UTL-002 Rev 2
Passivation certificate PASS-041 As issued
EU GMP Annex 15 — Qualification and Validation Current
EU GMP Annex 11 — Computerised Systems Current

4. Responsibilities

Execution is shared between the supplier and the installation contractor, witnessed and recorded by the user disciplines listed. A test performed without the required witness is not valid and shall be repeated.

Discipline Name Responsibility
Supplier Executes functional tests, provides updated documentation
Installation contractor Provides installation records, executes installation corrections
Engineering Witnesses execution, records results, raises deviations
CQV / Validation Confirms protocol compliance and deviation classification
Operations Witnesses operability tests
Automation / IT Witnesses control system and interface tests
EHS Witnesses safety and access assessments
Quality Assurance Approves the protocol and the report

5. Methodology

5.1 Site Acceptance and Installation Qualification approach

This project executes Site Acceptance Testing and Installation Qualification as separate documents. Site Acceptance Testing is executed by the supplier and installation contractor and witnessed by the user. Installation Qualification is executed by the user and may leverage Site Acceptance results under a documented supplier assessment.

Consequence for scope: this protocol verifies that the installation functions and that Factory Acceptance findings are closed. It does not replace the formal documentation verification performed at Installation Qualification. Requirements verified here that also fall within Installation Qualification scope are recorded in the traceability matrix so that Installation Qualification can leverage rather than repeat them.

5.2 Basis of verdicts

A test passes only where the recorded result satisfies the stated acceptance criterion in full. A partial result is a failure. No acceptance criterion may be amended during execution; if a criterion is found to be wrong, testing of that item stops and the specification is corrected through change control.

6. Test Prerequisites

Confirmed and recorded before any test is performed.

  • This protocol is approved and the approved copy is present at site.

  • Installation is mechanically and electrically complete, or any incomplete item is listed and agreed before starting.

  • Site utilities are available at the conditions stated in the utility schedule.

  • Passivation is complete and the certificate is available.

  • The final flush has been performed and recorded.

  • The WFI generation system, equipment item EQ-01, is available for interface testing.

  • All Factory Acceptance punch list items due before Site Acceptance are closed, or their status is agreed and recorded.

  • All test instruments hold valid calibration certificates.

  • Control system software version is recorded before testing begins and compared against the version recorded at Factory Acceptance.

7. Test Instruments and Calibration

Every instrument shall hold a valid calibration certificate traceable to national standards. The required accuracy is stated relative to the tolerance being verified.

Instrument Used in Required accuracy Cal. cert / due
Digital level SAT-I-03, SAT-I-05, SAT-F-18 Accuracy 0.1 degrees or better
Boroscope SAT-I-06, SAT-I-09 Suitable for the smallest pipe bore in scope
Calibrated rule / calipers SAT-I-07 Resolution 1 mm or better
Torque wrench SAT-I-03 Accuracy 4% of reading or better
Tape measure SAT-I-02, SAT-I-11 Class II or better
Calibrated pressure gauges SAT-I-04 Accuracy 1% of span or better
Flow meter SAT-F-05 Accuracy 2% of reading or better
Signal simulator SAT-F-24 Accuracy 0.1% of span or better
Filter integrity tester SAT-F-15 Manufacturer specified for the filter type
UV inspection lamp SAT-F-16 365 nm

8. Acceptance Criteria and Handling of Failures

Each failure is recorded as a deviation with a classification of critical, major or minor, entered in the deviation log at Appendix B, and carried to the punch list where rework is required.

A critical deviation prevents progression to Operational Qualification until closed and retested. A major deviation prevents progression unless a documented concession is approved by Quality Assurance. A minor deviation may be carried with an agreed closure date.

A Factory Acceptance deviation is closed only by retest against the original acceptance criterion, or by a documented concession approved by Quality Assurance. Confirming that rework was carried out is not the same as confirming that it works.

9. Installation Verification Tests

Tests specific to arrival and installation, with no Factory Acceptance equivalent.

SAT-I-01 — Verify the equipment arrived undamaged and complete against the shipping record.

Test ID SAT-I-01
Traces to Installation verification
Objective Verify the equipment arrived undamaged and complete against the shipping record.

Method

1. Compare the delivered items against the packing list and shipping condition record.

2. Inspect all surfaces, connections and instruments for transit damage.

3. Confirm shock and tilt indicators, where fitted, have not been triggered.

Acceptance criterion

All items delivered, no transit damage, no triggered transit indicators.

Test instrument Result
Performed by Pass / Fail Date

SAT-I-02 — Verify location, orientation and access against the site layout.

Test ID SAT-I-02
Traces to Installation verification
Objective Verify location, orientation and access against the site layout.

Method

1. Compare installed position against the general arrangement and site layout drawing.

2. Confirm maintenance access and instrument access clearances.

Acceptance criterion

Installed position matches the layout drawing. Access clearances as drawn.

Test instrument Tape measure Result
Performed by Pass / Fail Date

SAT-I-03 — Verify levelling, anchoring and support.

Test ID SAT-I-03
Traces to Installation verification
Objective Verify levelling, anchoring and support.

Method

1. Check the skid is level to its installed datum.

2. Confirm all anchor bolts are fitted and torqued to the stated value.

3. Confirm pipe supports are installed at the intervals shown on the isometrics.

Acceptance criterion

Skid level within supplier tolerance. All anchors fitted and torqued. Supports at drawn intervals.

Test instrument Digital level, torque wrench Result
Performed by Pass / Fail Date

SAT-I-04 — Verify utility connections against the utility schedule.

Test ID SAT-I-04
Traces to URS-036
Objective Verify utility connections against the utility schedule.

Method

1. For each utility, confirm the connection is made at the stated point.

2. Record supply pressure, temperature and quality at each connection.

3. Confirm isolation and drain provision at each connection.

Acceptance criterion

ACCEPTANCE CRITERION NOT DEFINED IN THE URS. URS-036 leaves the utility envelope as [TO BE CONFIRMED].

Test instrument Calibrated gauges Result
Performed by Pass / Fail Date

SAT-I-05 — Verify slope of site-installed pipework.

Test ID SAT-I-05
Traces to URS-039
Objective Verify slope of site-installed pipework.

Method

1. Measure fall on every horizontal run of site-installed pipework.

2. Record fall as a ratio against the drawn value.

Acceptance criterion

Continuous fall of not less than 1 in 100 towards designated drain points on all site-installed pipework.

Test instrument Digital level, accuracy 0.1 degrees or better Result
Performed by Pass / Fail Date

SAT-I-06 — Verify drainability of the complete installed system.

Test ID SAT-I-06
Traces to URS-048
Objective Verify drainability of the complete installed system.

Method

1. Fill the complete system with water.

2. Open all drain points and allow to drain for 30 minutes.

3. Inspect all low points, branches and points of use for retained water.

Acceptance criterion

No retained water anywhere in the installed system.

Test instrument Boroscope Result
Performed by Pass / Fail Date

SAT-I-07 — Verify dead leg dimensions on the complete installed system, including reworked skid branches.

Test ID SAT-I-07
Traces to URS-047 | Closes FAT DEV-001
Objective Verify dead leg dimensions on the complete installed system, including reworked skid branches.

Method

1. Measure every branch on the installed system from the internal wall of the main loop to the point of closure.

2. Express as a multiple of internal pipe diameter.

3. Record every branch, distinguishing reworked skid branches from site-installed branches.

Acceptance criterion

No dead leg exceeds three internal pipe diameters (3D) as required by URS-047.

Test instrument Calibrated rule / calipers Result
Performed by Pass / Fail Date

SAT-I-08 — Verify passivation of the complete system.

Test ID SAT-I-08
Traces to URS-043
Objective Verify passivation of the complete system.

Method

1. Obtain the passivation certificate and procedure record.

2. Confirm the scope of passivation covers the complete installed system.

3. Confirm the final rinse water quality record.

Acceptance criterion

Passivation performed on the complete installed system to a documented procedure, with certificate and final rinse record.

Test instrument Result
Performed by Pass / Fail Date

SAT-I-09 — Verify cleanliness of the installed system before commissioning.

Test ID SAT-I-09
Traces to Installation verification
Objective Verify cleanliness of the installed system before commissioning.

Method

1. Boroscopically inspect accessible sections of the loop.

2. Confirm absence of construction debris, weld spatter and foreign material.

3. Confirm the final flush was performed and recorded.

Acceptance criterion

No debris or foreign material. Final flush performed and recorded.

Test instrument Boroscope Result
Performed by Pass / Fail Date

SAT-I-10 — Verify drain connections and air breaks.

Test ID SAT-I-10
Traces to URS-037
Objective Verify drain connections and air breaks.

Method

1. Inspect every drain connection on the installed system.

2. Confirm an air break is present and visible at each.

Acceptance criterion

All drains discharge through a visible air break to prevent backflow.

Test instrument Result
Performed by Pass / Fail Date

SAT-I-11 — Verify pipework routing and support in classified areas.

Test ID SAT-I-11
Traces to URS-040
Objective Verify pipework routing and support in classified areas.

Method

1. Inspect routing through the Grade C corridor and Grade D plant room.

2. Confirm clearance from walls and ceilings for inspection and cleaning.

3. Confirm support and finish do not compromise room cleanability.

Acceptance criterion

Routing clear of walls and ceilings, supports and finish compatible with room cleaning.

Test instrument Tape measure Result
Performed by Pass / Fail Date

SAT-I-12 — Verify sample point installation and identification.

Test ID SAT-I-12
Traces to URS-070
Objective Verify sample point installation and identification.

Method

1. Confirm every sample point shown on the P&ID is installed.

2. Confirm each is individually tagged and matches the P&ID identifier.

3. Confirm each is accessible for sampling without contamination.

Acceptance criterion

All sample points installed, individually identified, accessible, and matching the P&ID.

Test instrument Result
Performed by Pass / Fail Date

SAT-I-13 — Verify temperature mapping ports at the worst-case locations identified in the URS.

Test ID SAT-I-13
Traces to URS-071
Objective Verify temperature mapping ports at the worst-case locations identified in the URS.

Method

1. Compare installed thermowells and mapping ports against the worst-case locations listed in the URS.

2. Record which locations have a port and which do not.

Acceptance criterion

A mapping port is provided at every worst-case location listed in the URS worst-case register.

Test instrument Result
Performed by Pass / Fail Date

SAT-I-14 — Verify the turnover documentation package.

Test ID SAT-I-14
Traces to URS-060
Objective Verify the turnover documentation package.

Method

1. Review the turnover package against the URS documentation requirement.

2. Confirm weld logs, boroscopy records, slope verification records, material certificates and passivation certificate are present.

Acceptance criterion

Turnover package complete, containing every document required by URS-060.

Test instrument Result
Performed by Pass / Fail Date

SAT-I-15 — Verify as-built drawings against the installed system.

Test ID SAT-I-15
Traces to Installation verification
Objective Verify as-built drawings against the installed system.

Method

1. Walk the system against the P&ID and isometrics.

2. Record every difference between the installed system and the drawings.

Acceptance criterion

As-built drawings match the installed system, with all field changes recorded.

Test instrument Result
Performed by Pass / Fail Date

10. Functional Tests at Site

Requirements newly testable because site utilities, the site network and the generation system are now available, together with retests closing Factory Acceptance deviations.

SAT-F-01 — Verify the interface to the WFI generation system.

Test ID SAT-F-01
Traces to URS-032
Objective Verify the interface to the WFI generation system.

Method

1. With the generation system in service, confirm the demand signal is exchanged.

2. Simulate a generation fault and confirm the status signal is received.

3. Simulate an out-of-specification diversion and confirm the signal is received and alarmed.

Acceptance criterion

Demand, status and diversion signals exchanged correctly with equipment item EQ-01.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-02 — Verify the interface to the site building management system.

Test ID SAT-F-02
Traces to URS-033
Objective Verify the interface to the site building management system.

Method

1. Raise three alarms and confirm annunciation at the BMS.

2. Attempt to issue a control command from the BMS.

Acceptance criterion

Alarms annunciate at the BMS. The BMS has no control authority over the WFI system.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-03 — Verify time synchronisation with the site time server.

Test ID SAT-F-03
Traces to URS-022
Objective Verify time synchronisation with the site time server.

Method

1. Confirm the system is synchronised to the site NTP server.

2. Attempt to alter system time at each role level.

3. Force a synchronisation and confirm the event is recorded.

Acceptance criterion

System synchronises to the site time server. Time is not user-alterable. Synchronisation events are recorded.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-04 — Verify point-of-use interfaces.

Test ID SAT-F-04
Traces to URS-034
Objective Verify point-of-use interfaces.

Method

1. At each point of use, confirm the mechanical connection matches the point-of-use schedule.

2. Where a control interface is specified, confirm the signal exchange with the connected equipment.

Acceptance criterion

All point-of-use connections match the schedule. Control interfaces exchange signals as specified.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-05 — Measure loop return velocity at design circulation flow.

Test ID SAT-F-05
Traces to URS-008
Objective Measure loop return velocity at design circulation flow.

Method

1. Establish loop circulation at the design flow.

2. Record flow at the loop return.

3. Calculate return velocity and Reynolds number from the measured flow and the installed pipe bore.

Acceptance criterion

Return velocity not less than 1.0 m/s, or demonstrated turbulent flow with Reynolds number greater than 10,000.

Test instrument Calibrated flow meter, accuracy 2% of reading or better Result
Performed by Pass / Fail Date

SAT-F-06 — Verify automatic duty rotation following software update.

Test ID SAT-F-06
Traces to URS-009 | Closes FAT DEV-006
Objective Verify automatic duty rotation following software update.

Method

1. Confirm the duty rotation function is present in the updated software.

2. Force the rotation interval and observe changeover.

3. Confirm the rotation event is recorded.

Acceptance criterion

Duty rotates automatically at a configurable interval and the event is recorded.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-07 — Verify that the audit trail cannot be disabled, following removal of the disable function.

Test ID SAT-F-07
Traces to URS-030 | Closes FAT DEV-009
Objective Verify that the audit trail cannot be disabled, following removal of the disable function.

Method

1. Log in as Administrator.

2. Search the maintenance menu for any audit trail disable function.

3. Attempt to disable, edit or delete audit trail entries.

Acceptance criterion

No function exists to disable, edit or delete the audit trail, at any role level including Administrator.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-08 — Verify audit trail export.

Test ID SAT-F-08
Traces to URS-031 | Closes FAT DEV-010
Objective Verify audit trail export.

Method

1. Filter the audit trail by date range and user.

2. Export the filtered record.

3. Confirm the export is human-readable and retains metadata.

Acceptance criterion

Audit trail exportable over a selected period, human-readable, retaining metadata.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-09 — Verify the sanitisation start interlock following modification.

Test ID SAT-F-09
Traces to URS-055 | Closes FAT DEV-007
Objective Verify the sanitisation start interlock following modification.

Method

1. Open a point of use to an operator-accessible outlet.

2. Attempt to initiate a sanitisation cycle.

3. Close the point of use and repeat.

Acceptance criterion

Sanitisation cannot be initiated while any point of use is open to an operator-accessible outlet.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-10 — Verify sanitisation start confirmation and point-of-use lockout indication.

Test ID SAT-F-10
Traces to URS-056
Objective Verify sanitisation start confirmation and point-of-use lockout indication.

Method

1. Initiate a sanitisation cycle.

2. Confirm a positive confirmation step is required.

3. Confirm point-of-use lockout indication is visible at each point.

Acceptance criterion

Positive confirmation required before start. Every point of use visibly indicated as locked out for the duration.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-11 — Verify sanitisation cycle completion logic following modification.

Test ID SAT-F-11
Traces to URS-049 | Closes FAT DEV-011
Objective Verify sanitisation cycle completion logic following modification.

Method

1. Initiate a cycle in simulation mode.

2. Force a simulated low temperature at one monitored location.

3. Observe the cycle outcome.

Acceptance criterion

The cycle cannot be declared successful where any monitored location failed to achieve the required temperature and hold.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-12 — Verify the initiating operator is recorded on the sanitisation record.

Test ID SAT-F-12
Traces to URS-018 | Closes FAT DEV-013
Objective Verify the initiating operator is recorded on the sanitisation record.

Method

1. Run a simulated cycle under a named account.

2. Review the cycle record.

Acceptance criterion

The cycle record contains the temperature profile, hold achieved, initiating operator and outcome.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-13 — Verify calibration parameter access restriction following the user decision.

Test ID SAT-F-13
Traces to URS-027 | Closes FAT DEV-008
Objective Verify calibration parameter access restriction following the user decision.

Method

1. Confirm the user decision on whether Supervisor is an authorised role.

2. Attempt to change calibration parameters at each role level.

Acceptance criterion

Critical setpoints and calibration parameters modifiable only by roles the user has authorised, with every change recorded.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-14 — Verify elastomer compliance documentation.

Test ID SAT-F-14
Traces to URS-045 | Closes FAT DEV-014
Objective Verify elastomer compliance documentation.

Method

1. Review the revised elastomer schedule.

2. Confirm compliance statements and stated service life at loop temperature.

Acceptance criterion

Elastomers comply with USP Class VI and 21 CFR 177.2600, with stated service life at continuous loop temperature.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-15 — Verify in-place vent filter integrity testing following modification.

Test ID SAT-F-15
Traces to URS-012 | Closes FAT DEV-005
Objective Verify in-place vent filter integrity testing following modification.

Method

1. Confirm the integrity test connection is installed.

2. Perform an integrity test with the filter in place.

3. Confirm the sterile boundary is not broken during the test.

Acceptance criterion

Integrity testing possible in place, without breaking the sterile boundary.

Test instrument Filter integrity tester Result
Performed by Pass / Fail Date

SAT-F-16 — Repeat spray ball coverage test following modification.

Test ID SAT-F-16
Traces to URS-011 | Closes FAT DEV-004
Objective Repeat spray ball coverage test following modification.

Method

1. Coat the vessel internal surface including headspace with riboflavin.

2. Operate the spray ball at design flow and pressure.

3. Inspect all internal surfaces under ultraviolet light.

Acceptance criterion

No residual fluorescence on any internal surface including the headspace and internal fittings.

Test instrument UV inspection lamp, riboflavin solution Result
Performed by Pass / Fail Date

SAT-F-17 — Verify drainability of the reworked skid branches.

Test ID SAT-F-17
Traces to URS-046 | Closes FAT DEV-002
Objective Verify drainability of the reworked skid branches.

Method

1. Fill the skid pipework.

2. Drain and inspect the two reworked branches.

Acceptance criterion

No retained water in the reworked branches.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-18 — Verify slope of the re-supported skid runs.

Test ID SAT-F-18
Traces to URS-039 | Closes FAT DEV-003
Objective Verify slope of the re-supported skid runs.

Method

1. Measure fall on the two runs re-supported after FAT.

Acceptance criterion

Fall not less than 1 in 100.

Test instrument Digital level Result
Performed by Pass / Fail Date

SAT-F-19 — Verify the disposition agreed for the loop return conductivity cell.

Test ID SAT-F-19
Traces to URS-051 | Closes FAT DEV-012
Objective Verify the disposition agreed for the loop return conductivity cell.

Method

1. Confirm the concession recorded in change control.

2. Confirm the isolation arrangement, if provided.

Acceptance criterion

Instrument removable without breaching the loop, or a documented concession accepted by Quality Assurance.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-20 — Verify training delivery.

Test ID SAT-F-20
Traces to URS-062
Objective Verify training delivery.

Method

1. Confirm training was delivered to operators, maintenance, QA and validation personnel.

2. Review attendance records and training content.

Acceptance criterion

Training delivered to all groups required by URS-062, covering operation, maintenance, audit trail review and user administration.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-21 — Verify point-of-use cooler arrangement.

Test ID SAT-F-21
Traces to URS-013
Objective Verify point-of-use cooler arrangement.

Method

1. Inspect the installed system for point-of-use coolers at the four points requiring water below loop temperature.

Acceptance criterion

Point-of-use coolers installed at every point of use requiring water below loop temperature.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-22 — Verify data export for laboratory correlation.

Test ID SAT-F-22
Traces to URS-035
Objective Verify data export for laboratory correlation.

Method

1. Attempt to export online monitoring data in a defined format.

Acceptance criterion

Online monitoring data exportable in a defined format for correlation with laboratory results.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-23 — Confirm 21 CFR Part 11 applicability and scope.

Test ID SAT-F-23
Traces to URS-066
Objective Confirm 21 CFR Part 11 applicability and scope.

Method

1. Confirm with the site whether Part 11 applies.

2. Where it applies, confirm the supplier scope includes the required controls.

Acceptance criterion

Part 11 applicability confirmed and, where applicable, the required controls are within the scope of supply.

Test instrument Result
Performed by Pass / Fail Date

SAT-F-24 — Verify instrument loop checks on the installed system.

Test ID SAT-F-24
Traces to URS-017
Objective Verify instrument loop checks on the installed system.

Method

1. For each installed instrument, apply a simulated input at 0, 50 and 100 percent of span.

2. Confirm the value at the HMI and the recorded value.

3. Confirm calibration certificates are current.

Acceptance criterion

Every loop reads correctly at three points within instrument accuracy, with current calibration certificates.

Test instrument Calibrated signal simulator Result
Performed by Pass / Fail Date

11. Requirements Deferred from Factory Acceptance

Disposition of every requirement carried forward from FAT-WFI-001-R. Each is either verified at Site Acceptance, deferred again to a named stage with a reason, or recorded as not executable because the specification does not fix a value.

URS ID Disposition Test / stage Basis
URS-001 Deferred again PQ WFI quality against the monograph requires the system in service with laboratory testing.
URS-002 Deferred again OQ Peak demand remains [TO BE CONFIRMED] in the URS. No criterion exists to test against.
URS-003 Deferred again PQ Requires extended operation in service.
URS-004 Deferred again OQ Tank capacity requirement remains [TO BE CONFIRMED] in the URS. Installed vessel is 5,000 L.
URS-005 Verified at SAT SAT-F-04 12 points of use installed and verified against the schedule.
URS-006 Deferred again PQ Requires operation in service following a planned shutdown.
URS-007 Deferred again OQ Requires loop at operating temperature with mapping at the least favourable point. Mapping ports are not installed; see SAT-I-13.
URS-008 Verified at SAT SAT-F-05 Return velocity measured at design circulation flow. Result 0.87 m/s; see SDEV-014.
URS-013 Verified at SAT SAT-F-21 Verified as not installed. Design resolution required.
URS-014 Deferred again OQ Sanitisation temperature and hold time remain [TO BE CONFIRMED] in the URS.
URS-016 Deferred again OQ Minimum pressure at the remote point remains [TO BE CONFIRMED] in the URS.
URS-020 Deferred again OQ Retention period remains [TO BE CONFIRMED] in the URS.
URS-021 Deferred again OQ Enduring and available over the retention period requires operation in service.
URS-022 Verified at SAT SAT-F-03 Synchronised to the site time server.
URS-032 Verified at SAT SAT-F-01 Interface to EQ-01 verified.
URS-033 Verified at SAT SAT-F-02 BMS interface verified; alarm text mismatch raised.
URS-034 Verified at SAT SAT-F-04 Mechanical interfaces verified; control interfaces not installed.
URS-035 Verified at SAT SAT-F-22 Verified as not provided.
URS-036 Not executed SAT-I-04 Utility envelope remains [TO BE CONFIRMED] in the URS. Values recorded for information.
URS-037 Verified at SAT SAT-I-10 All drains verified with air breaks.
URS-039 Verified at SAT SAT-I-05 Site pipework slope measured; two runs below requirement.
URS-040 Verified at SAT SAT-I-11 Routing verified; support finish finding raised.
URS-043 Verified at SAT SAT-I-08 Passivation certificate covers skid only.
URS-063 Deferred again PQ Water quality against the monograph requires the system in service.
URS-064 Deferred again PQ Requires WFI in service and laboratory testing.
URS-069 Deferred again PQ The three-phase programme runs in service over one year.
URS-070 Verified at SAT SAT-I-12 Sample points installed and identified; access finding raised.
URS-071 Verified at SAT SAT-I-13 Verified as not installed. Blocks OQ sanitisation qualification.
URS-072 Outstanding DQ closure Hydraulic calculation at the worst-case demand condition remains outstanding at DQ-OBS-045.
URS-073 Deferred again VSR Traceability across the programme is closed at the Validation Summary Report.
URS-074 Deferred again OQ Ability to challenge worst-case conditions is confirmed in operation.
URS-059 Verified at SAT SAT protocol was provided for review before testing.
URS-060 Verified at SAT SAT-I-14 Turnover package incomplete; see SDEV-010.
URS-062 Verified at SAT SAT-F-20 Training partially delivered; see SDEV-016.
URS-065 Deferred again VSR Assessed across the qualification programme.
URS-066 Verified at SAT SAT-F-23 Part 11 applicability confirmed.

12. Factory Acceptance Deviation and Punch List Closure

Each Factory Acceptance deviation is verified by retest against its original acceptance criterion. The Factory Acceptance deviation register is updated; no parallel register is created.

FAT dev Verified by Original finding Closed / Not closed
DEV-001 SAT-I-07 Nine of fourteen branches exceed the 3D dead leg limit required by URS-047, measured up to 5.8D. The skid was built to the 6D stated in DS-003.
DEV-002 SAT-F-17 Two point-of-use branches on the north face do not self-drain; retained water confirmed at FAT-008.
DEV-003 SAT-F-18 Two horizontal runs on the skid have a fall of 1:150 against the 1:100 required by URS-039.
DEV-004 SAT-F-16 Riboflavin coverage test showed residual fluorescence around the level probe boss and the vent nozzle.
DEV-005 SAT-F-15 Vent filter in-place integrity testing requires removal of the housing clamp, breaking the sterile boundary.
DEV-006 SAT-F-06 No automatic duty rotation between distribution pumps. The standby leg remains stagnant between manual changeovers.
DEV-007 SAT-F-09 Sanitisation can be initiated with a point of use open to an operator-accessible outlet. Scald hazard.
DEV-008 SAT-F-13 Calibration parameters are modifiable at Supervisor role level.
DEV-009 SAT-F-07 The Administrator account can disable audit trail recording from the maintenance menu, contrary to URS-030 and to records controls.
DEV-010 SAT-F-08 No audit trail export function over a selected period.
DEV-011 SAT-F-11 The sanitisation cycle reports Complete on elapsed time even where a monitored location failed to achieve temperature.
DEV-012 SAT-F-19 The loop return conductivity cell cannot be removed without breaking the loop in operation.
DEV-013 SAT-F-12 The operator initiating a sanitisation cycle is not recorded.
DEV-014 SAT-F-14 No 21 CFR 177.2600 compliance statement and no stated service life for the elastomers.

Factory Acceptance punch list

Item Description Owner Due Status
PL-001 Rework nine branches to 3D dead leg limit Supplier Before shipment
PL-002 Modify vent filter housing for in-place integrity testing Supplier Before shipment
PL-003 Modify two north face branches to self-drain Supplier Before shipment
PL-004 Re-support two horizontal runs to 1:100 Supplier Before shipment
PL-005 Remove audit trail disable function; provide export function Supplier Before shipment
PL-006 Correct two transposed instrument tags Supplier Before shipment
PL-007 Add sanitisation start interlock and confirmation step Supplier Before shipment
PL-008 Modify sanitisation completion logic Supplier Before shipment
PL-009 Add duty rotation function Supplier Before shipment
PL-010 Repeat spray ball coverage test after modification Supplier Before shipment
PL-011 Provide elastomer compliance statement and service life Supplier Before shipment
PL-012 Add initiating operator to sanitisation record Supplier Before shipment
PL-013 Fix boroscopy percentage in the URS and confirm against 10% performed User Before SAT
PL-014 Confirm whether Supervisor is authorised for calibration parameters User Before SAT

13. Worst-Case Condition Challenges

Conditions the installed system now makes testable, and those still requiring operation in service.

Ref Condition At SAT Basis Outcome / deferral
WC-07 Longest branch and standby pump leg Challenged SAT-I-07 measured every branch on the installed system. SAT-F-06 verified duty rotation. Duty rotation now closed. Three branches still exceed 3D; SDEV-001.
WC-09 Highest point and longest horizontal run Challenged SAT-I-05 and SAT-I-06 measured slope and drainability across the complete installed system. Two runs below slope requirement and one branch retains water. SDEV-002 and SDEV-003.
WC-05 Tank at minimum operating level Re-challenged SAT-F-16 repeated the spray ball coverage test after modification. Closed. Coverage complete including headspace.
WC-06 Maximum tank discharge rate Closed at FAT Verified at FAT-011 and confirmed unchanged by installation. No further action.
WC-01 Maximum simultaneous demand Not challengeable at SAT Requires all points of use in service drawing simultaneously, which is an operational condition. Deferred to OQ. Supplier hydraulic calculation at this condition still outstanding at DQ-OBS-045.
WC-02 Coldest point during normal circulation Not challengeable at SAT Requires mapping at the least favourable point. Mapping ports are not installed. Deferred to OQ and blocked by SDEV-009.
WC-03 Least favourable point during sanitisation Not challengeable at SAT Requires mapping ports and defined acceptance values. Deferred to OQ and blocked by SDEV-009 and by the undefined values in URS-014.
WC-04 Point-of-use cooler branch Not challengeable No coolers installed. Blocked by SDEV-017. Cannot be challenged at any stage until the design is resolved.
WC-08 Most hydraulically remote point of use Not challengeable at SAT Requires operational draw at the remote point. Deferred to OQ.
WC-10 Extended low-demand period Not challengeable at SAT Requires extended operation in service. Deferred to PQ.
WC-11 Worst-case feed water quality Not challengeable at SAT Requires seasonal variation in service. Deferred to PQ Phase 3.

14. Requirements Remaining After Site Acceptance

Completed in the Site Acceptance report. Every requirement not verified here is carried into the Installation Qualification protocol with its destination stage. A requirement that disappears between this report and the next protocol is a break in the qualification chain.

15. Deviation Handling

Each failure is recorded at the point of occurrence with the test identifier, a factual description of what was observed, and the classification. Classification is agreed between the user witness and Quality Assurance at the time, not retrospectively.

16. Punch List

Items requiring action before Installation Qualification or Operational Qualification are recorded here during execution.

Item Description Against Owner Due

17. Approval and Sign-off

Approval authorises execution of this protocol. It does not constitute acceptance of the system.

Role Name Department Signature Date
Author Engineering
Reviewer CQV / Validation
Reviewer Operations
Reviewer Automation / IT
Reviewer EHS
Reviewer Contamination Control
Quality approval Quality Assurance

18. Revision History

Revision Date Description of change Author
0.1 [DD-MMM-YYYY] First draft.

Appendix A — Traceability across URS, DQ, FAT and SAT

URS ID Requirement summary DQ verdict FAT SAT test Result
URS-001 The system shall store and distribute Water for Injection meeting the requirements of… see DQ-WFI-001 Deferred
URS-002 The system shall deliver a peak instantaneous demand of [TO BE CONFIRMED] L/min and a… see DQ-WFI-001 Deferred
URS-003 The system shall operate continuously, 24 hours per day, 7 days per week, with planne… see DQ-WFI-001 Deferred
URS-004 The storage tank shall have a nominal capacity of [TO BE CONFIRMED] L, sized to buffe… see DQ-WFI-001 Deferred
URS-005 The distribution loop shall serve [TO BE CONFIRMED] points of use, listed with their … see DQ-WFI-001 Deferred
URS-006 The system shall recover to full specification within [TO BE CONFIRMED] hours followi… see DQ-WFI-001 Deferred
URS-007 WFI shall be stored and distributed under continuous hot circulation at a temperature… see DQ-WFI-001 Deferred
URS-008 The distribution loop shall maintain a return flow velocity of not less than 1.0 m/s,… see DQ-WFI-001 Deferred SAT-F-05
URS-009 The system shall be fitted with duty and standby distribution pumps with automatic ch… see DQ-WFI-001 Tested SAT-F-06
URS-010 Loop temperature shall be maintained by a heat exchanger of double tube sheet constru… see DQ-WFI-001 Tested
URS-011 The storage tank shall be fitted with a spray ball providing demonstrated full wetted… see DQ-WFI-001 Tested SAT-F-16
URS-012 The storage tank shall be fitted with a hydrophobic vent filter of 0.22 micrometre ra… see DQ-WFI-001 Tested SAT-F-15
URS-013 Points of use requiring water below loop temperature shall be served by dedicated poi… see DQ-WFI-001 Deferred SAT-F-21
URS-014 The system shall provide a thermal sanitisation cycle capable of raising every point … see DQ-WFI-001 Deferred
URS-015 Tank level shall be controlled automatically, with high, high-high, low and low-low a… see DQ-WFI-001 Tested
URS-016 The system shall deliver a minimum dynamic pressure of [TO BE CONFIRMED] bar g at the… see DQ-WFI-001 Deferred
URS-017 The control system shall continuously record loop supply temperature, loop return tem… see DQ-WFI-001 Tested SAT-F-24
URS-018 The system shall record every sanitisation cycle, capturing the temperature profile a… see DQ-WFI-001 Tested SAT-F-12
URS-019 All alarms shall be recorded with the alarm condition, time of onset, time of acknowl… see DQ-WFI-001 Tested
URS-020 Records shall be retained for not less than [TO BE CONFIRMED] years and shall be expo… see DQ-WFI-001 Deferred
URS-021 Records shall be attributable, legible, contemporaneous, original and accurate, and s… see DQ-WFI-001 Deferred
URS-022 The system clock shall synchronise with the site time server. Users shall not be able… see DQ-WFI-001 Deferred SAT-F-03
URS-023 The system shall support automated backup of all GMP records, and restoration of thos… see DQ-WFI-001 Tested
URS-024 No function shall permit deletion or overwriting of a recorded value. Corrections sha… see DQ-WFI-001 Tested
URS-025 The control system shall provide role-based access control with individual named user… see DQ-WFI-001 Tested
URS-026 The system shall provide at least the roles Operator, Supervisor, Engineer and Admini… see DQ-WFI-001 Tested
URS-027 Critical setpoints, including sanitisation temperature and hold time, alarm limits an… see DQ-WFI-001 Tested SAT-F-13
URS-028 The system shall enforce automatic session timeout after a configurable period of ina… see DQ-WFI-001 Tested
URS-029 The system shall maintain a secure, computer-generated, time-stamped audit trail reco… see DQ-WFI-001 Tested
URS-030 The audit trail shall not be editable or disableable by any user, including administr… see DQ-WFI-001 Tested SAT-F-07
URS-031 The system shall support periodic audit trail review, with a filterable view and an e… see DQ-WFI-001 Tested SAT-F-08
URS-032 The system shall interface with the upstream WFI generation system, exchanging demand… see DQ-WFI-001 Deferred SAT-F-01
URS-033 The system shall provide monitored signals to the site building management system for… see DQ-WFI-001 Deferred SAT-F-02
URS-034 The system shall provide the physical and electrical interface at each point of use d… see DQ-WFI-001 Deferred SAT-F-04
URS-035 Where sample results are managed in a laboratory information management system, the s… see DQ-WFI-001 Deferred SAT-F-22
URS-036 The system shall operate within the site utility envelope: electrical supply [TO BE C… see DQ-WFI-001 Deferred SAT-I-04
URS-037 All drain connections shall discharge through an air break to prevent backflow, and s… see DQ-WFI-001 Deferred SAT-I-10
URS-038 All hot surfaces accessible to personnel shall be insulated or guarded such that touc… see DQ-WFI-001 Tested
URS-039 Pipework shall be installed with a continuous fall of not less than 1 in 100 towards … see DQ-WFI-001 Deferred SAT-I-05
URS-040 Loop pipework routed through classified areas shall be finished and supported so as n… see DQ-WFI-001 Deferred SAT-I-11
URS-041 All product contact surfaces shall be stainless steel 316L, with a mechanically polis… see DQ-WFI-001 Tested
URS-042 All product contact welds shall be automatic orbital welds. A weld log shall be maint… see DQ-WFI-001 Tested
URS-043 The system shall be passivated after installation in accordance with a documented pro… see DQ-WFI-001 Deferred SAT-I-08
URS-044 Material certificates in accordance with EN 10204 Type 3.1 shall be provided for all … see DQ-WFI-001 Tested
URS-045 Elastomers and polymers in product contact shall comply with USP Class VI and 21 CFR … see DQ-WFI-001 Tested SAT-F-14
URS-046 All valves in product contact shall be sanitary diaphragm valves of zero static or ze… see DQ-WFI-001 Tested SAT-F-17
URS-047 No dead leg in the distribution system shall exceed three internal pipe diameters (3D… see DQ-WFI-001 Tested SAT-I-07
URS-048 The complete system, including the tank, loop, all branches and all points of use, sh… see DQ-WFI-001 Tested SAT-I-06
URS-049 The sanitisation cycle shall be initiated from the operator interface, shall run auto… see DQ-WFI-001 Tested SAT-F-11
URS-050 Sample valves at each sampling location shall be of sanitary design, self-draining, a… see DQ-WFI-001 Tested
URS-051 All instruments requiring calibration shall be accessible without dismantling major a… see DQ-WFI-001 Tested SAT-F-19
URS-052 The supplier shall provide a preventive maintenance schedule stating each task, its f… see DQ-WFI-001 Tested
URS-053 The storage tank shall be protected against overpressure and vacuum by a rupture disc… see DQ-WFI-001 Tested
URS-054 An emergency stop shall be provided at the skid and at each remote pump location, pla… see DQ-WFI-001 Tested
URS-055 Interlocks shall prevent operation of distribution pumps against a closed system and … see DQ-WFI-001 Tested SAT-F-09
URS-056 Sanitisation shall not be capable of being started without a positive confirmation st… see DQ-WFI-001 Tested SAT-F-10
URS-057 Noise emitted by the system shall not exceed 80 dB(A) measured at one metre under nor… see DQ-WFI-001 Tested
URS-058 The supplier shall provide, prior to Factory Acceptance Testing: general arrangement … see DQ-WFI-001 Tested
URS-059 The supplier shall provide FAT and SAT protocols for user review and approval not les… see DQ-WFI-001 Deferred
URS-060 The supplier shall provide IQ and OQ protocols and supporting documentation aligned w… see DQ-WFI-001 Deferred SAT-I-14
URS-061 The supplier shall provide operation and maintenance manuals, a spare parts list with… see DQ-WFI-001 Tested
URS-062 The supplier shall provide training for operators, maintenance personnel, and quality… see DQ-WFI-001 Deferred SAT-F-20
URS-063 The system shall comply with the current USP and Ph. Eur. monographs for Water for In… see DQ-WFI-001 Deferred
URS-064 WFI delivered at every point of use shall meet: conductivity in accordance with USP G… see DQ-WFI-001 Deferred
URS-065 The system shall be designed, installed and qualified in accordance with EU GMP Annex… see DQ-WFI-001 Deferred
URS-066 The control system shall comply with EU GMP Annex 11 and, where applicable to the sit… see DQ-WFI-001 Deferred SAT-F-23
URS-067 The system shall be designed and documented in accordance with GAMP 5, and the suppli… see DQ-WFI-001 Tested
URS-068 Equipment design shall follow ASME BPE for hygienic design, surface finish, fabricati… see DQ-WFI-001 Tested
URS-069 The system shall support a three-phase Performance Qualification: Phase 1 with daily … see DQ-WFI-001 Deferred
URS-070 Sample points shall be provided at the tank outlet, the loop supply, the loop return,… see DQ-WFI-001 Deferred SAT-I-12
URS-071 Temperature mapping ports shall be provided at each worst-case location listed in App… see DQ-WFI-001 Deferred SAT-I-13
URS-072 The supplier shall provide hydraulic calculations demonstrating that the minimum retu… see DQ-WFI-001 Deferred
URS-073 Every requirement in this specification shall be traceable through design qualificati… see DQ-WFI-001 Deferred
URS-074 The system shall permit challenge of the worst-case conditions listed in Appendix A d… see DQ-WFI-001 Deferred

Appendix B — Deviation Log

Completed during execution.

Deviation Test Description Classification Status

Appendix C — As-Built Document Register

Document Number Revision received Date
P&ID
Isometric drawings
General arrangement
Electrical schematics
Instrument index
Loop diagrams
Weld log
Boroscopy record
Slope verification record
Passivation certificate
Material certificates
Calibration certificates

Appendix D — Abbreviations

Term Definition
BMS Building Management System
DQ Design Qualification
DEV FAT deviation
FAT Factory Acceptance Test
HMI Human Machine Interface
IQ Installation Qualification
NTP Network Time Protocol
OQ Operational Qualification
P&ID Piping and Instrumentation Diagram
POU Point of use
PQ Performance Qualification
SAT Site Acceptance Test
SDEV SAT deviation
SPL SAT punch list item
URS User Requirements Specification
VSR Validation Summary Report
WFI Water for Injection

SAT ReportSite Acceptance Test Report

Download Word
Full document text — PRJ-2026-0009 · EQ-02

SITE ACCEPTANCE TEST REPORT

Water for Injection Storage and Distribution System

SAT-WFI-001-R · REVISION 0.1

Project reference PRJ-2026-0009
Equipment reference EQ-02 — WFI Storage and Distribution System
Document status Draft
Records execution of SAT-WFI-001 Rev 0.1
Site [Site name and location]
Supplier [Supplier name]
Test dates [DD-MMM-YYYY] to [DD-MMM-YYYY]
Prepared by [Enter author]
This report records the results of the tests defined in SAT-WFI-001 as observed at site. Acceptance criteria are reproduced from the approved protocol without amendment. Results were recorded by the persons named against each test and are reproduced without alteration. This report has no validity until reviewed and approved in accordance with the site quality system. Pharma4i does not perform or record document approval.

Related Documents

Document Number Rev Status Relationship
User Requirements Specification URS-WFI-001 0.1 Issued Source of requirements
Design Qualification DQ-WFI-001 0.1 Issued Source of open observations
FAT Protocol FAT-WFI-001 0.1 Issued Preceding test
FAT Report FAT-WFI-001-R 0.1 Issued Source of deferrals, deviations and punch list
SAT Protocol SAT-WFI-001 0.1 Draft This protocol
SAT Report SAT-WFI-001-R 0.1 Draft Records execution of this protocol
Installation Qualification IQ-WFI-001 Planned Receives requirements outstanding after SAT
Operational Qualification OQ-WFI-001 Planned Planned
Performance Qualification PQ-WFI-001 Planned Planned
Validation Summary Report VSR-WFI-001 Planned Planned

Table of Contents

1. Introduction

This report records the execution of SAT-WFI-001 Revision 0.1 at site. It reproduces the acceptance criteria from the approved protocol without amendment, records the result observed against each, and lists every deviation raised.

No acceptance criterion was amended during execution. Where a criterion could not be applied because URS-WFI-001 does not fix a value, the test is recorded as not executed and the finding is against the specification.

2. Summary of Results

Outcome Count Note
Pass 19
Fail 19 Each raised as a deviation; see Section 8.
Not executed 1 Acceptance criterion not defined in the specification.

Tests defined in the protocol: 39 (15 installation, 24 functional).

2.1 Deviations raised at Site Acceptance

Classification Count Effect
Critical 4 Prevents progression to Operational Qualification until closed and retested.
Major 7 Prevents progression unless a concession is approved by Quality Assurance.
Minor 7 May be carried with an agreed closure date.

2.2 Critical deviations

  • SDEV-001 (SAT-I-07) — Three branches exceed the 3D dead leg limit: one reworked skid branch at 3.4D and two site-installed branches at 3.6D and 4.1D.

  • SDEV-003 (SAT-I-06) — The branch serving POU-07 retains water after draining.

  • SDEV-009 (SAT-I-13) — No temperature mapping ports installed at the worst-case locations listed in the URS worst-case register.

  • SDEV-017 (SAT-F-21) — No point-of-use coolers installed. Four points of use require water below loop temperature and cannot be served as specified.

2.3 Factory Acceptance deviation closure

12 of 14 Factory Acceptance deviations were closed at Site Acceptance. 2 remain open.

  • DEV-001 remains open — Eight of nine reworked branches now at or below 3D; one at 3.4D. Two site-installed branches also exceed 3D.

  • DEV-011 remains open — Completion logic corrected, but acceptance values remain undefined in URS-014.

2.4 Requirements deferred from Factory Acceptance

18 of the 36 requirements deferred from Factory Acceptance were verified at Site Acceptance. 16 were deferred again to Operational or Performance Qualification, and the remainder could not be executed because the specification does not fix a value. Full disposition at Section 6.

3. Installation Verification Results

SAT-I-01 — Verify the equipment arrived undamaged and complete against the shipping record.

Test ID SAT-I-01
Traces to Installation verification
Objective Verify the equipment arrived undamaged and complete against the shipping record.

Method

1. Compare the delivered items against the packing list and shipping condition record.

2. Inspect all surfaces, connections and instruments for transit damage.

3. Confirm shock and tilt indicators, where fitted, have not been triggered.

Acceptance criterion

All items delivered, no transit damage, no triggered transit indicators.

Test instrument Result All items present. No damage. Tilt indicators intact.
Performed by Pass / Fail Pass Date

SAT-I-02 — Verify location, orientation and access against the site layout.

Test ID SAT-I-02
Traces to Installation verification
Objective Verify location, orientation and access against the site layout.

Method

1. Compare installed position against the general arrangement and site layout drawing.

2. Confirm maintenance access and instrument access clearances.

Acceptance criterion

Installed position matches the layout drawing. Access clearances as drawn.

Test instrument Tape measure Result Position correct. Clearance to the east wall is 640 mm against 750 mm drawn.
Performed by Pass / Fail Fail Date

Comment: Access to the heat exchanger head is restricted. SDEV-004.

SAT-I-03 — Verify levelling, anchoring and support.

Test ID SAT-I-03
Traces to Installation verification
Objective Verify levelling, anchoring and support.

Method

1. Check the skid is level to its installed datum.

2. Confirm all anchor bolts are fitted and torqued to the stated value.

3. Confirm pipe supports are installed at the intervals shown on the isometrics.

Acceptance criterion

Skid level within supplier tolerance. All anchors fitted and torqued. Supports at drawn intervals.

Test instrument Digital level, torque wrench Result Level within tolerance. All 12 anchors torqued. Two supports missing on the north riser.
Performed by Pass / Fail Fail Date

Comment: SDEV-005, minor. Punch item.

SAT-I-04 — Verify utility connections against the utility schedule.

Test ID SAT-I-04
Traces to URS-036
Objective Verify utility connections against the utility schedule.

Method

1. For each utility, confirm the connection is made at the stated point.

2. Record supply pressure, temperature and quality at each connection.

3. Confirm isolation and drain provision at each connection.

Acceptance criterion

ACCEPTANCE CRITERION NOT DEFINED IN THE URS. URS-036 leaves the utility envelope as [TO BE CONFIRMED].

Test instrument Calibrated gauges Result All six utilities connected. Heating medium supplied at 4.2 barg, 145 degrees C. Compressed air at 6.1 barg.
Performed by Pass / Fail Not executed Date

Comment: No specified envelope to verify against. Values recorded for information. Finding against the specification.

SAT-I-05 — Verify slope of site-installed pipework.

Test ID SAT-I-05
Traces to URS-039
Objective Verify slope of site-installed pipework.

Method

1. Measure fall on every horizontal run of site-installed pipework.

2. Record fall as a ratio against the drawn value.

Acceptance criterion

Continuous fall of not less than 1 in 100 towards designated drain points on all site-installed pipework.

Test instrument Digital level, accuracy 0.1 degrees or better Result 19 runs measured. 17 at 1:95 or better. Two runs in the north bay at 1:130.
Performed by Pass / Fail Fail Date

Comment: SDEV-002.

SAT-I-06 — Verify drainability of the complete installed system.

Test ID SAT-I-06
Traces to URS-048
Objective Verify drainability of the complete installed system.

Method

1. Fill the complete system with water.

2. Open all drain points and allow to drain for 30 minutes.

3. Inspect all low points, branches and points of use for retained water.

Acceptance criterion

No retained water anywhere in the installed system.

Test instrument Boroscope Result Retained water in one branch serving point of use POU-07.
Performed by Pass / Fail Fail Date

Comment: SDEV-003, critical. Same defect class as FAT DEV-002 but on site pipework.

SAT-I-07 — Verify dead leg dimensions on the complete installed system, including reworked skid branches.

Test ID SAT-I-07
Traces to URS-047 | Closes FAT DEV-001
Objective Verify dead leg dimensions on the complete installed system, including reworked skid branches.

Method

1. Measure every branch on the installed system from the internal wall of the main loop to the point of closure.

2. Express as a multiple of internal pipe diameter.

3. Record every branch, distinguishing reworked skid branches from site-installed branches.

Acceptance criterion

No dead leg exceeds three internal pipe diameters (3D) as required by URS-047.

Test instrument Calibrated rule / calipers Result 31 branches measured. Eight of the nine reworked skid branches now at or below 3D; one at 3.4D. Two site-installed branches at 3.6D and 4.1D.
Performed by Pass / Fail Fail Date

Comment: FAT DEV-001 partially closed. Three branches remain above 3D. SDEV-001.

SAT-I-08 — Verify passivation of the complete system.

Test ID SAT-I-08
Traces to URS-043
Objective Verify passivation of the complete system.

Method

1. Obtain the passivation certificate and procedure record.

2. Confirm the scope of passivation covers the complete installed system.

3. Confirm the final rinse water quality record.

Acceptance criterion

Passivation performed on the complete installed system to a documented procedure, with certificate and final rinse record.

Test instrument Result Certificate issued. Scope covers the skid only. Site-installed pipework was not included.
Performed by Pass / Fail Fail Date

Comment: SDEV-006, major.

SAT-I-09 — Verify cleanliness of the installed system before commissioning.

Test ID SAT-I-09
Traces to Installation verification
Objective Verify cleanliness of the installed system before commissioning.

Method

1. Boroscopically inspect accessible sections of the loop.

2. Confirm absence of construction debris, weld spatter and foreign material.

3. Confirm the final flush was performed and recorded.

Acceptance criterion

No debris or foreign material. Final flush performed and recorded.

Test instrument Boroscope Result 12 sections inspected. Clean. Final flush record provided.
Performed by Pass / Fail Pass Date

SAT-I-10 — Verify drain connections and air breaks.

Test ID SAT-I-10
Traces to URS-037
Objective Verify drain connections and air breaks.

Method

1. Inspect every drain connection on the installed system.

2. Confirm an air break is present and visible at each.

Acceptance criterion

All drains discharge through a visible air break to prevent backflow.

Test instrument Result All nine drains verified with visible air breaks.
Performed by Pass / Fail Pass Date

SAT-I-11 — Verify pipework routing and support in classified areas.

Test ID SAT-I-11
Traces to URS-040
Objective Verify pipework routing and support in classified areas.

Method

1. Inspect routing through the Grade C corridor and Grade D plant room.

2. Confirm clearance from walls and ceilings for inspection and cleaning.

3. Confirm support and finish do not compromise room cleanability.

Acceptance criterion

Routing clear of walls and ceilings, supports and finish compatible with room cleaning.

Test instrument Tape measure Result Routing clear. Two supports in the Grade C corridor have exposed threaded rod without a cleanable cover.
Performed by Pass / Fail Fail Date

Comment: SDEV-007, minor.

SAT-I-12 — Verify sample point installation and identification.

Test ID SAT-I-12
Traces to URS-070
Objective Verify sample point installation and identification.

Method

1. Confirm every sample point shown on the P&ID is installed.

2. Confirm each is individually tagged and matches the P&ID identifier.

3. Confirm each is accessible for sampling without contamination.

Acceptance criterion

All sample points installed, individually identified, accessible, and matching the P&ID.

Test instrument Result All 14 sample points installed and tagged. POU-11 sample valve is 1.9 m above floor level with no platform.
Performed by Pass / Fail Fail Date

Comment: SDEV-008, minor. Access platform required.

SAT-I-13 — Verify temperature mapping ports at the worst-case locations identified in the URS.

Test ID SAT-I-13
Traces to URS-071
Objective Verify temperature mapping ports at the worst-case locations identified in the URS.

Method

1. Compare installed thermowells and mapping ports against the worst-case locations listed in the URS.

2. Record which locations have a port and which do not.

Acceptance criterion

A mapping port is provided at every worst-case location listed in the URS worst-case register.

Test instrument Result No dedicated mapping ports installed. Only the four process thermowells are present.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-044, unresolved through DQ, FAT and now SAT. Without ports at the least favourable points, sanitisation acceptance cannot be demonstrated at OQ. SDEV-009, critical.

SAT-I-14 — Verify the turnover documentation package.

Test ID SAT-I-14
Traces to URS-060
Objective Verify the turnover documentation package.

Method

1. Review the turnover package against the URS documentation requirement.

2. Confirm weld logs, boroscopy records, slope verification records, material certificates and passivation certificate are present.

Acceptance criterion

Turnover package complete, containing every document required by URS-060.

Test instrument Result Weld logs, material certificates and O&M manuals present. Slope verification records for site pipework absent. Boroscopy record covers skid welds only.
Performed by Pass / Fail Fail Date

Comment: SDEV-010, major.

SAT-I-15 — Verify as-built drawings against the installed system.

Test ID SAT-I-15
Traces to Installation verification
Objective Verify as-built drawings against the installed system.

Method

1. Walk the system against the P&ID and isometrics.

2. Record every difference between the installed system and the drawings.

Acceptance criterion

As-built drawings match the installed system, with all field changes recorded.

Test instrument Result Three field routing changes in the north bay are not reflected on ISO-011.
Performed by Pass / Fail Fail Date

Comment: SDEV-011, minor. As-builts to be reissued.

4. Functional Test Results

SAT-F-01 — Verify the interface to the WFI generation system.

Test ID SAT-F-01
Traces to URS-032
Objective Verify the interface to the WFI generation system.

Method

1. With the generation system in service, confirm the demand signal is exchanged.

2. Simulate a generation fault and confirm the status signal is received.

3. Simulate an out-of-specification diversion and confirm the signal is received and alarmed.

Acceptance criterion

Demand, status and diversion signals exchanged correctly with equipment item EQ-01.

Test instrument Result All three signals verified. Diversion signal alarmed within 3 seconds.
Performed by Pass / Fail Pass Date

SAT-F-02 — Verify the interface to the site building management system.

Test ID SAT-F-02
Traces to URS-033
Objective Verify the interface to the site building management system.

Method

1. Raise three alarms and confirm annunciation at the BMS.

2. Attempt to issue a control command from the BMS.

Acceptance criterion

Alarms annunciate at the BMS. The BMS has no control authority over the WFI system.

Test instrument Result All three alarms annunciated. No control possible from BMS. Two alarm descriptions differ between the HMI and the BMS.
Performed by Pass / Fail Fail Date

Comment: SDEV-012, minor. Alarm text alignment.

SAT-F-03 — Verify time synchronisation with the site time server.

Test ID SAT-F-03
Traces to URS-022
Objective Verify time synchronisation with the site time server.

Method

1. Confirm the system is synchronised to the site NTP server.

2. Attempt to alter system time at each role level.

3. Force a synchronisation and confirm the event is recorded.

Acceptance criterion

System synchronises to the site time server. Time is not user-alterable. Synchronisation events are recorded.

Test instrument Result Synchronised to site NTP. Time alteration blocked at all roles. Sync events recorded in the audit trail.
Performed by Pass / Fail Pass Date

SAT-F-04 — Verify point-of-use interfaces.

Test ID SAT-F-04
Traces to URS-034
Objective Verify point-of-use interfaces.

Method

1. At each point of use, confirm the mechanical connection matches the point-of-use schedule.

2. Where a control interface is specified, confirm the signal exchange with the connected equipment.

Acceptance criterion

All point-of-use connections match the schedule. Control interfaces exchange signals as specified.

Test instrument Result All 12 mechanical connections correct. Control interfaces to the two formulation vessels are not installed.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-031. SDEV-013, major.

SAT-F-05 — Measure loop return velocity at design circulation flow.

Test ID SAT-F-05
Traces to URS-008
Objective Measure loop return velocity at design circulation flow.

Method

1. Establish loop circulation at the design flow.

2. Record flow at the loop return.

3. Calculate return velocity and Reynolds number from the measured flow and the installed pipe bore.

Acceptance criterion

Return velocity not less than 1.0 m/s, or demonstrated turbulent flow with Reynolds number greater than 10,000.

Test instrument Calibrated flow meter, accuracy 2% of reading or better Result Measured 0.87 m/s at design circulation flow. Reynolds number 41,200.
Performed by Pass / Fail Fail Date

Comment: Velocity below the URS figure although flow is strongly turbulent. Note that URS-008 permits either criterion; the Reynolds number criterion is met. Recorded as a fail against the velocity figure pending a user decision on which criterion applies. SDEV-014, major.

SAT-F-06 — Verify automatic duty rotation following software update.

Test ID SAT-F-06
Traces to URS-009 | Closes FAT DEV-006
Objective Verify automatic duty rotation following software update.

Method

1. Confirm the duty rotation function is present in the updated software.

2. Force the rotation interval and observe changeover.

3. Confirm the rotation event is recorded.

Acceptance criterion

Duty rotates automatically at a configurable interval and the event is recorded.

Test instrument Result Rotation function present, interval configurable, changeover observed at 168 hours simulated. Event recorded.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-006 closed.

SAT-F-07 — Verify that the audit trail cannot be disabled, following removal of the disable function.

Test ID SAT-F-07
Traces to URS-030 | Closes FAT DEV-009
Objective Verify that the audit trail cannot be disabled, following removal of the disable function.

Method

1. Log in as Administrator.

2. Search the maintenance menu for any audit trail disable function.

3. Attempt to disable, edit or delete audit trail entries.

Acceptance criterion

No function exists to disable, edit or delete the audit trail, at any role level including Administrator.

Test instrument Result Disable function removed from the software. No disable, edit or delete possible at any role.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-009 closed by retest against the original criterion.

SAT-F-08 — Verify audit trail export.

Test ID SAT-F-08
Traces to URS-031 | Closes FAT DEV-010
Objective Verify audit trail export.

Method

1. Filter the audit trail by date range and user.

2. Export the filtered record.

3. Confirm the export is human-readable and retains metadata.

Acceptance criterion

Audit trail exportable over a selected period, human-readable, retaining metadata.

Test instrument Result Export produced in CSV and PDF. Metadata retained.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-010 closed.

SAT-F-09 — Verify the sanitisation start interlock following modification.

Test ID SAT-F-09
Traces to URS-055 | Closes FAT DEV-007
Objective Verify the sanitisation start interlock following modification.

Method

1. Open a point of use to an operator-accessible outlet.

2. Attempt to initiate a sanitisation cycle.

3. Close the point of use and repeat.

Acceptance criterion

Sanitisation cannot be initiated while any point of use is open to an operator-accessible outlet.

Test instrument Result Sanitisation start correctly blocked with POU-03 open. Started normally with all points closed.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-007 closed.

SAT-F-10 — Verify sanitisation start confirmation and point-of-use lockout indication.

Test ID SAT-F-10
Traces to URS-056
Objective Verify sanitisation start confirmation and point-of-use lockout indication.

Method

1. Initiate a sanitisation cycle.

2. Confirm a positive confirmation step is required.

3. Confirm point-of-use lockout indication is visible at each point.

Acceptance criterion

Positive confirmation required before start. Every point of use visibly indicated as locked out for the duration.

Test instrument Result Confirmation step present. Lockout indication present at 10 of 12 points; POU-09 and POU-11 have no local indicator.
Performed by Pass / Fail Fail Date

Comment: SDEV-015, major.

SAT-F-11 — Verify sanitisation cycle completion logic following modification.

Test ID SAT-F-11
Traces to URS-049 | Closes FAT DEV-011
Objective Verify sanitisation cycle completion logic following modification.

Method

1. Initiate a cycle in simulation mode.

2. Force a simulated low temperature at one monitored location.

3. Observe the cycle outcome.

Acceptance criterion

The cycle cannot be declared successful where any monitored location failed to achieve the required temperature and hold.

Test instrument Result With a forced low temperature the cycle now reports Failed and raises an alarm. However the acceptance temperature and hold time remain [TO BE CONFIRMED] in URS-014, so the values used are supplier defaults.
Performed by Pass / Fail Fail Date

Comment: The logic defect is corrected, but the acceptance values are still undefined in the specification, so the cycle cannot be qualified. FAT DEV-011 partially closed. See Section 11.

SAT-F-12 — Verify the initiating operator is recorded on the sanitisation record.

Test ID SAT-F-12
Traces to URS-018 | Closes FAT DEV-013
Objective Verify the initiating operator is recorded on the sanitisation record.

Method

1. Run a simulated cycle under a named account.

2. Review the cycle record.

Acceptance criterion

The cycle record contains the temperature profile, hold achieved, initiating operator and outcome.

Test instrument Result All four elements recorded including the initiating operator.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-013 closed.

SAT-F-13 — Verify calibration parameter access restriction following the user decision.

Test ID SAT-F-13
Traces to URS-027 | Closes FAT DEV-008
Objective Verify calibration parameter access restriction following the user decision.

Method

1. Confirm the user decision on whether Supervisor is an authorised role.

2. Attempt to change calibration parameters at each role level.

Acceptance criterion

Critical setpoints and calibration parameters modifiable only by roles the user has authorised, with every change recorded.

Test instrument Result User confirmed Supervisor is an authorised role for calibration parameters, recorded in the change control. Access verified as configured; all changes recorded.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-008 closed by documented user decision, not by rework.

SAT-F-14 — Verify elastomer compliance documentation.

Test ID SAT-F-14
Traces to URS-045 | Closes FAT DEV-014
Objective Verify elastomer compliance documentation.

Method

1. Review the revised elastomer schedule.

2. Confirm compliance statements and stated service life at loop temperature.

Acceptance criterion

Elastomers comply with USP Class VI and 21 CFR 177.2600, with stated service life at continuous loop temperature.

Test instrument Result Revised schedule provides both compliance statements and a stated service life of 24 months at 85 degrees C continuous.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-014 closed.

SAT-F-15 — Verify in-place vent filter integrity testing following modification.

Test ID SAT-F-15
Traces to URS-012 | Closes FAT DEV-005
Objective Verify in-place vent filter integrity testing following modification.

Method

1. Confirm the integrity test connection is installed.

2. Perform an integrity test with the filter in place.

3. Confirm the sterile boundary is not broken during the test.

Acceptance criterion

Integrity testing possible in place, without breaking the sterile boundary.

Test instrument Filter integrity tester Result Test connection installed. Integrity test performed in place. Sterile boundary maintained.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-005 closed.

SAT-F-16 — Repeat spray ball coverage test following modification.

Test ID SAT-F-16
Traces to URS-011 | Closes FAT DEV-004
Objective Repeat spray ball coverage test following modification.

Method

1. Coat the vessel internal surface including headspace with riboflavin.

2. Operate the spray ball at design flow and pressure.

3. Inspect all internal surfaces under ultraviolet light.

Acceptance criterion

No residual fluorescence on any internal surface including the headspace and internal fittings.

Test instrument UV inspection lamp, riboflavin solution Result No residual fluorescence. Coverage complete including the level probe boss and vent nozzle.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-004 closed by retest against the original criterion.

SAT-F-17 — Verify drainability of the reworked skid branches.

Test ID SAT-F-17
Traces to URS-046 | Closes FAT DEV-002
Objective Verify drainability of the reworked skid branches.

Method

1. Fill the skid pipework.

2. Drain and inspect the two reworked branches.

Acceptance criterion

No retained water in the reworked branches.

Test instrument Result Both reworked branches now drain fully.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-002 closed.

SAT-F-18 — Verify slope of the re-supported skid runs.

Test ID SAT-F-18
Traces to URS-039 | Closes FAT DEV-003
Objective Verify slope of the re-supported skid runs.

Method

1. Measure fall on the two runs re-supported after FAT.

Acceptance criterion

Fall not less than 1 in 100.

Test instrument Digital level Result Both runs now at 1:92 and 1:88.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-003 closed. Note this does not close SAT-I-05, which concerns site pipework.

SAT-F-19 — Verify the disposition agreed for the loop return conductivity cell.

Test ID SAT-F-19
Traces to URS-051 | Closes FAT DEV-012
Objective Verify the disposition agreed for the loop return conductivity cell.

Method

1. Confirm the concession recorded in change control.

2. Confirm the isolation arrangement, if provided.

Acceptance criterion

Instrument removable without breaching the loop, or a documented concession accepted by Quality Assurance.

Test instrument Result Concession accepted; calibration to be performed during planned shutdown, recorded in the maintenance schedule.
Performed by Pass / Fail Pass Date

Comment: FAT DEV-012 closed by concession.

SAT-F-20 — Verify training delivery.

Test ID SAT-F-20
Traces to URS-062
Objective Verify training delivery.

Method

1. Confirm training was delivered to operators, maintenance, QA and validation personnel.

2. Review attendance records and training content.

Acceptance criterion

Training delivered to all groups required by URS-062, covering operation, maintenance, audit trail review and user administration.

Test instrument Result Operator and maintenance training delivered. QA and validation training on audit trail review and user administration not yet delivered.
Performed by Pass / Fail Fail Date

Comment: SDEV-016, major.

SAT-F-21 — Verify point-of-use cooler arrangement.

Test ID SAT-F-21
Traces to URS-013
Objective Verify point-of-use cooler arrangement.

Method

1. Inspect the installed system for point-of-use coolers at the four points requiring water below loop temperature.

Acceptance criterion

Point-of-use coolers installed at every point of use requiring water below loop temperature.

Test instrument Result No coolers installed. The design does not include them.
Performed by Pass / Fail Fail Date

Comment: Unresolved from DQ-OBS-011 through FAT and SAT. Four points of use cannot be served as specified. SDEV-017, critical. Design resolution required before OQ.

SAT-F-22 — Verify data export for laboratory correlation.

Test ID SAT-F-22
Traces to URS-035
Objective Verify data export for laboratory correlation.

Method

1. Attempt to export online monitoring data in a defined format.

Acceptance criterion

Online monitoring data exportable in a defined format for correlation with laboratory results.

Test instrument Result No export capability. Not in the design.
Performed by Pass / Fail Fail Date

Comment: Confirms DQ-OBS-033. Desirable requirement. SDEV-018, minor.

SAT-F-23 — Confirm 21 CFR Part 11 applicability and scope.

Test ID SAT-F-23
Traces to URS-066
Objective Confirm 21 CFR Part 11 applicability and scope.

Method

1. Confirm with the site whether Part 11 applies.

2. Where it applies, confirm the supplier scope includes the required controls.

Acceptance criterion

Part 11 applicability confirmed and, where applicable, the required controls are within the scope of supply.

Test instrument Result Site confirmed Part 11 applies. Supplier scope includes access control, audit trail and record retention. Electronic signature is not in scope and is not required by URS-025 to URS-031.
Performed by Pass / Fail Pass Date

Comment: Closes DQ-OBS-047.

SAT-F-24 — Verify instrument loop checks on the installed system.

Test ID SAT-F-24
Traces to URS-017
Objective Verify instrument loop checks on the installed system.

Method

1. For each installed instrument, apply a simulated input at 0, 50 and 100 percent of span.

2. Confirm the value at the HMI and the recorded value.

3. Confirm calibration certificates are current.

Acceptance criterion

Every loop reads correctly at three points within instrument accuracy, with current calibration certificates.

Test instrument Calibrated signal simulator Result All 17 installed loops verified. All calibration certificates current.
Performed by Pass / Fail Pass Date

5. Factory Acceptance Deviation Closure

FAT dev Class Verified by Outcome Status
DEV-001 Critical SAT-I-07 Eight of nine reworked branches now at or below 3D; one at 3.4D. Two site-installed branches also exceed 3D. Not closed
DEV-002 Major SAT-F-17 Both reworked skid branches now drain fully. Closed
DEV-003 Major SAT-F-18 Both re-supported runs now at 1:92 and 1:88. Closed
DEV-004 Major SAT-F-16 Coverage test repeated; no residual fluorescence. Closed
DEV-005 Major SAT-F-15 Integrity test connection installed; test performed in place. Closed
DEV-006 Major SAT-F-06 Duty rotation function added and verified. Closed
DEV-007 Critical SAT-F-09 Sanitisation start interlock added and verified. Closed
DEV-008 Minor SAT-F-13 User confirmed Supervisor as an authorised role, recorded in change control. Closed by concession
DEV-009 Critical SAT-F-07 Disable function removed from the software; retested at all role levels. Closed
DEV-010 Major SAT-F-08 Audit trail export function provided and verified. Closed
DEV-011 Critical SAT-F-11 Completion logic corrected, but acceptance values remain undefined in URS-014. Not closed
DEV-012 Minor SAT-F-19 Concession accepted; calibration during planned shutdown. Closed by concession
DEV-013 Major SAT-F-12 Initiating operator now recorded on the cycle record. Closed
DEV-014 Minor SAT-F-14 Compliance statements and service life provided. Closed

6. Requirements Deferred from Factory Acceptance — Disposition

URS ID Disposition Test / stage Basis
URS-001 Deferred again PQ WFI quality against the monograph requires the system in service with laboratory testing.
URS-002 Deferred again OQ Peak demand remains [TO BE CONFIRMED] in the URS. No criterion exists to test against.
URS-003 Deferred again PQ Requires extended operation in service.
URS-004 Deferred again OQ Tank capacity requirement remains [TO BE CONFIRMED] in the URS. Installed vessel is 5,000 L.
URS-005 Verified at SAT SAT-F-04 12 points of use installed and verified against the schedule.
URS-006 Deferred again PQ Requires operation in service following a planned shutdown.
URS-007 Deferred again OQ Requires loop at operating temperature with mapping at the least favourable point. Mapping ports are not installed; see SAT-I-13.
URS-008 Verified at SAT SAT-F-05 Return velocity measured at design circulation flow. Result 0.87 m/s; see SDEV-014.
URS-013 Verified at SAT SAT-F-21 Verified as not installed. Design resolution required.
URS-014 Deferred again OQ Sanitisation temperature and hold time remain [TO BE CONFIRMED] in the URS.
URS-016 Deferred again OQ Minimum pressure at the remote point remains [TO BE CONFIRMED] in the URS.
URS-020 Deferred again OQ Retention period remains [TO BE CONFIRMED] in the URS.
URS-021 Deferred again OQ Enduring and available over the retention period requires operation in service.
URS-022 Verified at SAT SAT-F-03 Synchronised to the site time server.
URS-032 Verified at SAT SAT-F-01 Interface to EQ-01 verified.
URS-033 Verified at SAT SAT-F-02 BMS interface verified; alarm text mismatch raised.
URS-034 Verified at SAT SAT-F-04 Mechanical interfaces verified; control interfaces not installed.
URS-035 Verified at SAT SAT-F-22 Verified as not provided.
URS-036 Not executed SAT-I-04 Utility envelope remains [TO BE CONFIRMED] in the URS. Values recorded for information.
URS-037 Verified at SAT SAT-I-10 All drains verified with air breaks.
URS-039 Verified at SAT SAT-I-05 Site pipework slope measured; two runs below requirement.
URS-040 Verified at SAT SAT-I-11 Routing verified; support finish finding raised.
URS-043 Verified at SAT SAT-I-08 Passivation certificate covers skid only.
URS-063 Deferred again PQ Water quality against the monograph requires the system in service.
URS-064 Deferred again PQ Requires WFI in service and laboratory testing.
URS-069 Deferred again PQ The three-phase programme runs in service over one year.
URS-070 Verified at SAT SAT-I-12 Sample points installed and identified; access finding raised.
URS-071 Verified at SAT SAT-I-13 Verified as not installed. Blocks OQ sanitisation qualification.
URS-072 Outstanding DQ closure Hydraulic calculation at the worst-case demand condition remains outstanding at DQ-OBS-045.
URS-073 Deferred again VSR Traceability across the programme is closed at the Validation Summary Report.
URS-074 Deferred again OQ Ability to challenge worst-case conditions is confirmed in operation.
URS-059 Verified at SAT SAT protocol was provided for review before testing.
URS-060 Verified at SAT SAT-I-14 Turnover package incomplete; see SDEV-010.
URS-062 Verified at SAT SAT-F-20 Training partially delivered; see SDEV-016.
URS-065 Deferred again VSR Assessed across the qualification programme.
URS-066 Verified at SAT SAT-F-23 Part 11 applicability confirmed.

7. Worst-Case Condition Outcomes

Ref Condition At SAT Basis Outcome / deferral
WC-07 Longest branch and standby pump leg Challenged SAT-I-07 measured every branch on the installed system. SAT-F-06 verified duty rotation. Duty rotation now closed. Three branches still exceed 3D; SDEV-001.
WC-09 Highest point and longest horizontal run Challenged SAT-I-05 and SAT-I-06 measured slope and drainability across the complete installed system. Two runs below slope requirement and one branch retains water. SDEV-002 and SDEV-003.
WC-05 Tank at minimum operating level Re-challenged SAT-F-16 repeated the spray ball coverage test after modification. Closed. Coverage complete including headspace.
WC-06 Maximum tank discharge rate Closed at FAT Verified at FAT-011 and confirmed unchanged by installation. No further action.
WC-01 Maximum simultaneous demand Not challengeable at SAT Requires all points of use in service drawing simultaneously, which is an operational condition. Deferred to OQ. Supplier hydraulic calculation at this condition still outstanding at DQ-OBS-045.
WC-02 Coldest point during normal circulation Not challengeable at SAT Requires mapping at the least favourable point. Mapping ports are not installed. Deferred to OQ and blocked by SDEV-009.
WC-03 Least favourable point during sanitisation Not challengeable at SAT Requires mapping ports and defined acceptance values. Deferred to OQ and blocked by SDEV-009 and by the undefined values in URS-014.
WC-04 Point-of-use cooler branch Not challengeable No coolers installed. Blocked by SDEV-017. Cannot be challenged at any stage until the design is resolved.
WC-08 Most hydraulically remote point of use Not challengeable at SAT Requires operational draw at the remote point. Deferred to OQ.
WC-10 Extended low-demand period Not challengeable at SAT Requires extended operation in service. Deferred to PQ.
WC-11 Worst-case feed water quality Not challengeable at SAT Requires seasonal variation in service. Deferred to PQ Phase 3.

8. Deviation Register

Ref Class Test Description Disposition / status
SDEV-001 Critical SAT-I-07 Three branches exceed the 3D dead leg limit: one reworked skid branch at 3.4D and two site-installed branches at 3.6D and 4.1D.

Contractor to rework the two site branches. Supplier to address the remaining skid branch. Retest before OQ.

Status: Open

SDEV-002 Major SAT-I-05 Two site-installed runs in the north bay have a fall of 1:130 against the 1:100 required by URS-039.

Contractor to re-support both runs. Retest before OQ.

Status: Open

SDEV-003 Critical SAT-I-06 The branch serving POU-07 retains water after draining.

Contractor to modify the branch geometry. Retest before OQ.

Status: Open

SDEV-004 Minor SAT-I-02 Clearance to the east wall is 640 mm against 750 mm drawn, restricting access to the heat exchanger head.

User to accept by concession or relocate. Maintenance access assessment required.

Status: Open

SDEV-005 Minor SAT-I-03 Two pipe supports missing on the north riser.

Contractor to fit. Punch item.

Status: Open

SDEV-006 Major SAT-I-08 Passivation certificate covers the skid only; site-installed pipework was not passivated.

Contractor to passivate site-installed pipework and issue a certificate covering the complete system. Retest before OQ.

Status: Open

SDEV-007 Minor SAT-I-11 Two supports in the Grade C corridor have exposed threaded rod without a cleanable cover.

Contractor to fit covers.

Status: Open

SDEV-008 Minor SAT-I-12 Sample valve at POU-11 is 1.9 m above floor level with no access platform.

User to provide a fixed platform or accept sampling from a step. EHS assessment required.

Status: Open

SDEV-009 Critical SAT-I-13 No temperature mapping ports installed at the worst-case locations listed in the URS worst-case register.

Contractor to install mapping ports at the locations identified in the URS. Without them, sanitisation acceptance cannot be demonstrated at OQ. Unresolved since DQ-OBS-044.

Status: Open

SDEV-010 Major SAT-I-14 Turnover package incomplete: slope verification records for site pipework absent, boroscopy record covers skid welds only.

Contractor to complete the turnover package before IQ.

Status: Open

SDEV-011 Minor SAT-I-15 Three field routing changes in the north bay are not reflected on ISO-011.

Contractor to reissue as-built isometrics.

Status: Open

SDEV-012 Minor SAT-F-02 Two alarm descriptions differ between the HMI and the BMS.

Supplier to align alarm text.

Status: Open

SDEV-013 Major SAT-F-04 Control interfaces to the two formulation vessels are not installed.

Confirm scope. Unresolved since DQ-OBS-031.

Status: Open

SDEV-014 Major SAT-F-05 Measured return velocity 0.87 m/s against the 1.0 m/s stated in URS-008, although Reynolds number 41,200 satisfies the alternative turbulent flow criterion in the same requirement.

User decision required on which criterion applies. If the velocity figure is retained, the loop requires hydraulic modification. Note that URS-008 records 1 m/s as a design convention, not a regulatory limit.

Status: Open

SDEV-015 Major SAT-F-10 Point-of-use lockout indication absent at POU-09 and POU-11.

Supplier to fit local indicators.

Status: Open

SDEV-016 Major SAT-F-20 Training for QA and validation personnel on audit trail review and user administration not delivered.

Supplier to deliver before OQ.

Status: Open

SDEV-017 Critical SAT-F-21 No point-of-use coolers installed. Four points of use require water below loop temperature and cannot be served as specified.

Design resolution required. Unresolved since DQ-OBS-011. This is a scope gap, not an installation defect.

Status: Open

SDEV-018 Minor SAT-F-22 No data export capability for laboratory correlation.

Desirable requirement. Confirm whether it is carried forward.

Status: Open

9. Punch List

Item Description Against Owner Due
SPL-01 Rework three branches exceeding 3D SDEV-001 Contractor / Supplier Before OQ
SPL-02 Re-support two north bay runs to 1:100 SDEV-002 Contractor Before OQ
SPL-03 Modify POU-07 branch to drain SDEV-003 Contractor Before OQ
SPL-04 Passivate site-installed pipework and issue certificate SDEV-006 Contractor Before OQ
SPL-05 Install temperature mapping ports at URS worst-case locations SDEV-009 Contractor Before OQ
SPL-06 Fit two missing pipe supports on north riser SDEV-005 Contractor Before IQ
SPL-07 Complete turnover package SDEV-010 Contractor Before IQ
SPL-08 Reissue as-built isometrics SDEV-011 Contractor Before IQ
SPL-09 Fit cleanable covers to Grade C supports SDEV-007 Contractor Before IQ
SPL-10 Align HMI and BMS alarm text SDEV-012 Supplier Before OQ
SPL-11 Fit lockout indicators at POU-09 and POU-11 SDEV-015 Supplier Before OQ
SPL-12 Deliver QA and validation training SDEV-016 Supplier Before OQ
SPL-13 Resolve point-of-use cooler scope SDEV-017 User / Supplier Before OQ
SPL-14 Decide velocity criterion for URS-008 SDEV-014 User Before OQ
SPL-15 Fix sanitisation temperature and hold time in URS-014 DEV-011 User Before OQ
SPL-16 Fix boroscopy percentage in URS-042 FAT PL-013 User Before IQ
SPL-17 Provide access platform or accept concession at POU-11 SDEV-008 User Before OQ
SPL-18 Confirm control interface scope for formulation vessels SDEV-013 User Before OQ

10. Requirements Remaining to be Verified

The following are not verified at Site Acceptance and are carried into Installation, Operational and Performance Qualification. This list is the direct input to the Installation Qualification protocol.

URS ID Verified at Reason not verified at Site Acceptance
URS-001 PQ WFI quality against the monograph requires the system in service with laboratory testing.
URS-002 OQ Peak demand remains [TO BE CONFIRMED] in the URS. No criterion exists to test against.
URS-003 PQ Requires extended operation in service.
URS-004 OQ Tank capacity requirement remains [TO BE CONFIRMED] in the URS. Installed vessel is 5,000 L.
URS-006 PQ Requires operation in service following a planned shutdown.
URS-007 OQ Requires loop at operating temperature with mapping at the least favourable point. Mapping ports are not installed; see SAT-I-13.
URS-014 OQ Sanitisation temperature and hold time remain [TO BE CONFIRMED] in the URS.
URS-016 OQ Minimum pressure at the remote point remains [TO BE CONFIRMED] in the URS.
URS-020 OQ Retention period remains [TO BE CONFIRMED] in the URS.
URS-021 OQ Enduring and available over the retention period requires operation in service.
URS-036 SAT-I-04 Utility envelope remains [TO BE CONFIRMED] in the URS. Values recorded for information.
URS-063 PQ Water quality against the monograph requires the system in service.
URS-064 PQ Requires WFI in service and laboratory testing.
URS-069 PQ The three-phase programme runs in service over one year.
URS-072 DQ closure Hydraulic calculation at the worst-case demand condition remains outstanding at DQ-OBS-045.
URS-073 VSR Traceability across the programme is closed at the Validation Summary Report.
URS-074 OQ Ability to challenge worst-case conditions is confirmed in operation.
URS-065 VSR Assessed across the qualification programme.

11. Conclusion

Of 39 tests defined in SAT-WFI-001 Revision 0.1: 19 passed, 19 failed and 1 could not be executed because the acceptance criterion is not defined in URS-WFI-001.

18 deviations were raised at Site Acceptance: 4 critical, 7 major and 7 minor. 12 of 14 Factory Acceptance deviations were closed; 2 remain open. 18 punch list items are recorded.

Of the eleven worst-case conditions identified in URS-WFI-001, two were challenged at site, one was re-challenged and closed, one had been closed at Factory Acceptance, and seven remain deferred to Operational or Performance Qualification. One of those seven cannot be challenged at any stage until the point-of-use cooler scope is resolved.

The system is [ accepted for qualification / accepted subject to closure of the punch list / not accepted ].

The bracketed judgement is drafted from the results recorded in this document. It is a judgement for the reviewer and must be confirmed, amended or replaced by qualified personnel before this report is issued. Pharma4i does not make this determination.

Note for the reviewer: four critical deviations are open. Three concern the installed pipework and are correctable. The fourth, SDEV-017, is a scope gap rather than a defect — no point-of-use coolers exist and four points of use cannot be served as specified. That has been visible since DQ-OBS-011 and has now passed through three qualification stages unresolved. Separately, SDEV-009 blocks Operational Qualification entirely: without mapping ports at the worst-case locations, sanitisation acceptance cannot be demonstrated at the least favourable point. On the results recorded here, a conclusion of accepted for qualification would not be supportable.

12. Attendance and Signatures

The persons below witnessed execution and confirm that the results recorded in this report are those observed at site.

Role Name Department Signature Date
Author Engineering
Reviewer CQV / Validation
Reviewer Operations
Reviewer Automation / IT
Reviewer EHS
Reviewer Contamination Control
Quality approval Quality Assurance

13. Revision History

Revision Date Description of change Author
0.1 [DD-MMM-YYYY] First draft.

Appendix A — Traceability across URS, DQ, FAT and SAT

URS ID Requirement summary DQ verdict FAT SAT test SAT result
URS-001 The system shall store and distribute Water for Injection meeting the requirements of… see DQ-WFI-001 Deferred Deferred again
URS-002 The system shall deliver a peak instantaneous demand of [TO BE CONFIRMED] L/min and a… see DQ-WFI-001 Deferred Deferred again
URS-003 The system shall operate continuously, 24 hours per day, 7 days per week, with planne… see DQ-WFI-001 Deferred Deferred again
URS-004 The storage tank shall have a nominal capacity of [TO BE CONFIRMED] L, sized to buffe… see DQ-WFI-001 Deferred Deferred again
URS-005 The distribution loop shall serve [TO BE CONFIRMED] points of use, listed with their … see DQ-WFI-001 Deferred Verified at SAT
URS-006 The system shall recover to full specification within [TO BE CONFIRMED] hours followi… see DQ-WFI-001 Deferred Deferred again
URS-007 WFI shall be stored and distributed under continuous hot circulation at a temperature… see DQ-WFI-001 Deferred Deferred again
URS-008 The distribution loop shall maintain a return flow velocity of not less than 1.0 m/s,… see DQ-WFI-001 Deferred SAT-F-05 Fail
URS-009 The system shall be fitted with duty and standby distribution pumps with automatic ch… see DQ-WFI-001 Tested SAT-F-06 Pass
URS-010 Loop temperature shall be maintained by a heat exchanger of double tube sheet constru… see DQ-WFI-001 Tested
URS-011 The storage tank shall be fitted with a spray ball providing demonstrated full wetted… see DQ-WFI-001 Tested SAT-F-16 Pass
URS-012 The storage tank shall be fitted with a hydrophobic vent filter of 0.22 micrometre ra… see DQ-WFI-001 Tested SAT-F-15 Pass
URS-013 Points of use requiring water below loop temperature shall be served by dedicated poi… see DQ-WFI-001 Deferred SAT-F-21 Fail
URS-014 The system shall provide a thermal sanitisation cycle capable of raising every point … see DQ-WFI-001 Deferred Deferred again
URS-015 Tank level shall be controlled automatically, with high, high-high, low and low-low a… see DQ-WFI-001 Tested
URS-016 The system shall deliver a minimum dynamic pressure of [TO BE CONFIRMED] bar g at the… see DQ-WFI-001 Deferred Deferred again
URS-017 The control system shall continuously record loop supply temperature, loop return tem… see DQ-WFI-001 Tested SAT-F-24 Pass
URS-018 The system shall record every sanitisation cycle, capturing the temperature profile a… see DQ-WFI-001 Tested SAT-F-12 Pass
URS-019 All alarms shall be recorded with the alarm condition, time of onset, time of acknowl… see DQ-WFI-001 Tested
URS-020 Records shall be retained for not less than [TO BE CONFIRMED] years and shall be expo… see DQ-WFI-001 Deferred Deferred again
URS-021 Records shall be attributable, legible, contemporaneous, original and accurate, and s… see DQ-WFI-001 Deferred Deferred again
URS-022 The system clock shall synchronise with the site time server. Users shall not be able… see DQ-WFI-001 Deferred SAT-F-03 Pass
URS-023 The system shall support automated backup of all GMP records, and restoration of thos… see DQ-WFI-001 Tested
URS-024 No function shall permit deletion or overwriting of a recorded value. Corrections sha… see DQ-WFI-001 Tested
URS-025 The control system shall provide role-based access control with individual named user… see DQ-WFI-001 Tested
URS-026 The system shall provide at least the roles Operator, Supervisor, Engineer and Admini… see DQ-WFI-001 Tested
URS-027 Critical setpoints, including sanitisation temperature and hold time, alarm limits an… see DQ-WFI-001 Tested SAT-F-13 Pass
URS-028 The system shall enforce automatic session timeout after a configurable period of ina… see DQ-WFI-001 Tested
URS-029 The system shall maintain a secure, computer-generated, time-stamped audit trail reco… see DQ-WFI-001 Tested
URS-030 The audit trail shall not be editable or disableable by any user, including administr… see DQ-WFI-001 Tested SAT-F-07 Pass
URS-031 The system shall support periodic audit trail review, with a filterable view and an e… see DQ-WFI-001 Tested SAT-F-08 Pass
URS-032 The system shall interface with the upstream WFI generation system, exchanging demand… see DQ-WFI-001 Deferred SAT-F-01 Pass
URS-033 The system shall provide monitored signals to the site building management system for… see DQ-WFI-001 Deferred SAT-F-02 Fail
URS-034 The system shall provide the physical and electrical interface at each point of use d… see DQ-WFI-001 Deferred SAT-F-04 Fail
URS-035 Where sample results are managed in a laboratory information management system, the s… see DQ-WFI-001 Deferred SAT-F-22 Fail
URS-036 The system shall operate within the site utility envelope: electrical supply [TO BE C… see DQ-WFI-001 Deferred SAT-I-04 Not executed
URS-037 All drain connections shall discharge through an air break to prevent backflow, and s… see DQ-WFI-001 Deferred SAT-I-10 Pass
URS-038 All hot surfaces accessible to personnel shall be insulated or guarded such that touc… see DQ-WFI-001 Tested
URS-039 Pipework shall be installed with a continuous fall of not less than 1 in 100 towards … see DQ-WFI-001 Deferred SAT-I-05 Fail
URS-040 Loop pipework routed through classified areas shall be finished and supported so as n… see DQ-WFI-001 Deferred SAT-I-11 Fail
URS-041 All product contact surfaces shall be stainless steel 316L, with a mechanically polis… see DQ-WFI-001 Tested
URS-042 All product contact welds shall be automatic orbital welds. A weld log shall be maint… see DQ-WFI-001 Tested
URS-043 The system shall be passivated after installation in accordance with a documented pro… see DQ-WFI-001 Deferred SAT-I-08 Fail
URS-044 Material certificates in accordance with EN 10204 Type 3.1 shall be provided for all … see DQ-WFI-001 Tested
URS-045 Elastomers and polymers in product contact shall comply with USP Class VI and 21 CFR … see DQ-WFI-001 Tested SAT-F-14 Pass
URS-046 All valves in product contact shall be sanitary diaphragm valves of zero static or ze… see DQ-WFI-001 Tested SAT-F-17 Pass
URS-047 No dead leg in the distribution system shall exceed three internal pipe diameters (3D… see DQ-WFI-001 Tested SAT-I-07 Fail
URS-048 The complete system, including the tank, loop, all branches and all points of use, sh… see DQ-WFI-001 Tested SAT-I-06 Fail
URS-049 The sanitisation cycle shall be initiated from the operator interface, shall run auto… see DQ-WFI-001 Tested SAT-F-11 Fail
URS-050 Sample valves at each sampling location shall be of sanitary design, self-draining, a… see DQ-WFI-001 Tested
URS-051 All instruments requiring calibration shall be accessible without dismantling major a… see DQ-WFI-001 Tested SAT-F-19 Pass
URS-052 The supplier shall provide a preventive maintenance schedule stating each task, its f… see DQ-WFI-001 Tested
URS-053 The storage tank shall be protected against overpressure and vacuum by a rupture disc… see DQ-WFI-001 Tested
URS-054 An emergency stop shall be provided at the skid and at each remote pump location, pla… see DQ-WFI-001 Tested
URS-055 Interlocks shall prevent operation of distribution pumps against a closed system and … see DQ-WFI-001 Tested SAT-F-09 Pass
URS-056 Sanitisation shall not be capable of being started without a positive confirmation st… see DQ-WFI-001 Tested SAT-F-10 Fail
URS-057 Noise emitted by the system shall not exceed 80 dB(A) measured at one metre under nor… see DQ-WFI-001 Tested
URS-058 The supplier shall provide, prior to Factory Acceptance Testing: general arrangement … see DQ-WFI-001 Tested
URS-059 The supplier shall provide FAT and SAT protocols for user review and approval not les… see DQ-WFI-001 Deferred Verified at SAT
URS-060 The supplier shall provide IQ and OQ protocols and supporting documentation aligned w… see DQ-WFI-001 Deferred SAT-I-14 Fail
URS-061 The supplier shall provide operation and maintenance manuals, a spare parts list with… see DQ-WFI-001 Tested
URS-062 The supplier shall provide training for operators, maintenance personnel, and quality… see DQ-WFI-001 Deferred SAT-F-20 Fail
URS-063 The system shall comply with the current USP and Ph. Eur. monographs for Water for In… see DQ-WFI-001 Deferred Deferred again
URS-064 WFI delivered at every point of use shall meet: conductivity in accordance with USP G… see DQ-WFI-001 Deferred Deferred again
URS-065 The system shall be designed, installed and qualified in accordance with EU GMP Annex… see DQ-WFI-001 Deferred Deferred again
URS-066 The control system shall comply with EU GMP Annex 11 and, where applicable to the sit… see DQ-WFI-001 Deferred SAT-F-23 Pass
URS-067 The system shall be designed and documented in accordance with GAMP 5, and the suppli… see DQ-WFI-001 Tested
URS-068 Equipment design shall follow ASME BPE for hygienic design, surface finish, fabricati… see DQ-WFI-001 Tested
URS-069 The system shall support a three-phase Performance Qualification: Phase 1 with daily … see DQ-WFI-001 Deferred Deferred again
URS-070 Sample points shall be provided at the tank outlet, the loop supply, the loop return,… see DQ-WFI-001 Deferred SAT-I-12 Fail
URS-071 Temperature mapping ports shall be provided at each worst-case location listed in App… see DQ-WFI-001 Deferred SAT-I-13 Fail
URS-072 The supplier shall provide hydraulic calculations demonstrating that the minimum retu… see DQ-WFI-001 Deferred Outstanding
URS-073 Every requirement in this specification shall be traceable through design qualificati… see DQ-WFI-001 Deferred Deferred again
URS-074 The system shall permit challenge of the worst-case conditions listed in Appendix A d… see DQ-WFI-001 Deferred Deferred again

Appendix B — Test Instruments Used

Instrument Used in Required accuracy Cal. cert / due
Digital level SAT-I-03, SAT-I-05, SAT-F-18 Accuracy 0.1 degrees or better
Boroscope SAT-I-06, SAT-I-09 Suitable for the smallest pipe bore in scope
Calibrated rule / calipers SAT-I-07 Resolution 1 mm or better
Torque wrench SAT-I-03 Accuracy 4% of reading or better
Tape measure SAT-I-02, SAT-I-11 Class II or better
Calibrated pressure gauges SAT-I-04 Accuracy 1% of span or better
Flow meter SAT-F-05 Accuracy 2% of reading or better
Signal simulator SAT-F-24 Accuracy 0.1% of span or better
Filter integrity tester SAT-F-15 Manufacturer specified for the filter type
UV inspection lamp SAT-F-16 365 nm

Appendix C — As-Built Document Register

Document Number Revision received Date
P&ID P&ID-005 Rev C
As-built isometrics ISO-011 Rev B
General arrangement GA-002 Rev C
Electrical schematics ELE-014 Rev 4
Instrument index IDX-009 Rev 2
Weld log WL-006 As issued
Boroscopy record BR-006 As issued
Slope verification record Not provided
Passivation certificate PASS-041 As issued
Material certificates MTC pack As issued

As-built isometrics were received at Rev B. Three field routing changes are not reflected; see SDEV-011. Slope verification records for site-installed pipework were not provided; see SDEV-010.

Appendix D — Software Configuration Recorded at Site

Item Version at FAT Version at SAT
PLC application [From FAT-037] Updated — duty rotation, audit trail, interlock
HMI application [From FAT-037] Updated — audit export, lockout indication
PLC firmware [From FAT-037] Unchanged

Software was modified between Factory and Site Acceptance to close deviations DEV-006, DEV-007, DEV-009, DEV-010 and DEV-011. The change is recorded under site change control and the modified functions were retested at SAT-F-06 to SAT-F-11.

Appendix E — Abbreviations

Term Definition
BMS Building Management System
DQ Design Qualification
DEV FAT deviation
FAT Factory Acceptance Test
HMI Human Machine Interface
IQ Installation Qualification
NTP Network Time Protocol
OQ Operational Qualification
P&ID Piping and Instrumentation Diagram
POU Point of use
PQ Performance Qualification
SAT Site Acceptance Test
SDEV SAT deviation
SPL SAT punch list item
URS User Requirements Specification
VSR Validation Summary Report
WFI Water for Injection